PEKERJA 16,034,375.00
RINCIAN RENCANA ANGGARAN BIAYA
DESA MADOLAOLI KECAMATAN GUNUNGSITOLI
TAHUN ANGGARAN 2018
1 BIDANG :
2 KEGIATAN : Pembangunan Bronjong di Sungai Sihamba Dusun I Desa Madolaoli
3 WAKTU PELAKSANAAN :
4 SUMBER DANA :
5 RINCIAN PENDANAAN :
KODE HARGASATUAN
URAIAN SATUAN VOLUME JUMLAH
REKENING (Rp)
1 2 3 4 5 6
Pembangunan Bronjong di Sungai Sihamba
Dusun I Desa Madolaoli
Belanja Barang dan Jasa
Belanja ATK
- Kertas HVS Rim 6.00 44,800.00 268,800.00
- Binder Clip No. 260 Lusin 6.00 24,640.00 147,840.00
- Binder Clip No. 200 Lusin 6.00 16,800.00 100,800.00
- Map Biasa Bh 9.00 1,120.00 10,080.00
- Map Plastik Folio Tali Lusin 2.00 33,600.00 67,200.00
- Materai 6000 Bh 30.00 6,000.00 180,000.00
- Materai 3000 Bh 20.00 3,000.00 60,000.00
- Hekter No. 3 Merk Max Bh 2.00 72,736.60 145,473.20
- Isi Hekter No. 3 Kotak 5.00 5,600.00 28,000.00
- Klip Kertas Segitiga Doss 5.00 31,322.54 156,612.70
- Pena Snowman Lusin 2.00 44,800.00 89,600.00
Jumlah 1,254,405.90
Belanja Cetak dan Penggandaan
- Fotocopy Lbr 1,208.00 280.00 338,240.00
- Jilid Bh 7.00 6,500.00 45,500.00
- Papan Proyek Bh 1.00 672,000.00 672,000.00
Jumlah 1,055,740.00
Upah Kerja
- Pekerja HOK 160.34 100,000.00 16,034,375.00
- Tukang HOK - - -
- Kepala Tukang HOK - - -
- Mandor HOK - - -
Jumlah 16,034,375.00
Honorarium TPK
- Ketua Org/Bln 3.00 - -
- Sekretaris Org/Bln 3.00 2,400,000.00 7,200,000.00
- Anggota Org/Bln 3.00 2,100,000.00 6,300,000.00
Jumlah 13,500,000.00
Upah Jasa Angkut
- Ongkos Batu Gunung Belah 15/20 m3 469.79 160,703.00 75,496,260.61
- Ongkos Kawat Bronjong Tipe 1 Unit 79.00 5,000.00 395,000.00
- Ongkos Kawat Bronjong Tipe 2 Unit 154.50 5,000.00 772,500.00
- Ongkos Kawat Bronjong Tipe 3 Unit 22.50 5,000.00 112,500.00
Jumlah 76,776,260.61
Belanja Modal
Bahan
- Batu Gunung Belah 15/20 m3 469.79 217,485.00 102,171,734.44
Bronjong Kawat Galvanis Lapis PVC Mesh 8 x 10 Ø
- Unit 79.00 334,500.00 26,425,500.00
2.70 mm Uk. 2 x 1 x 0.5 m (Tipe 1)
Bronjong Kawat Galvanis Lapis PVC Mesh 8 x 10 Ø
- Unit 154.50 488,370.00 75,453,165.00
2.70 mm Uk. 3 x 1 x 0.5 m (Tipe 2)
Bronjong Kawat Galvanis Lapis PVC Mesh 8 x 10 Ø
- Unit 22.50 669,000.00 15,052,500.00
2.70 mm Uk. 3 x 1.5 x 0.5 m (Tipe 3)
- Gerobak Sorong Merk Artco Buah 7.00 508,000.00 3,556,000.00
- Tang Ukuran Sedang Buah 4.00 46,000.00 184,000.00
- Linggis Besar Buah 4.00 137,345.76 549,383.05
Jumlah 223,392,282.49
JUMLAH TOTAL 332,013,064.00
Madolaoli, 2018
Volume Jumlah
Kategori Harga Satuan
No Uraian Sat Ket
Sumber Biaya Sumber
Total APBDes Swadaya APBDes Swadaya Total Jumlah
Lain Lain
2 3 4 5 6 7=4-5-6 8 9 10 = 5 x 9 11 = 6 x 9 12 = 7 x 9 13 14
I Jenis Kegiatan Pekerjaan penggalian tanah keras
Ukuran/Dimensi 60.00 M3
A Bahan :
1 Tidak ada
Sub Total (A) -
B Alat :
1 Cangkul Swadaya
2 Sekop Swadaya
3 Linggis Besar Buah 4.00 4.00 137,345.76 549,383.05
4 Ember Swadaya
Sub Total (B) 549,383.05
C Upah :
1 Pekerja HOK 60.00 60.00 100,000.00 6,000,000.00
2 Mandor HOK
Sub Total (C) 6,000,000.00
Sub Total (A+B+C) 6,549,383.05
II Jenis Kegiatan Pekerjaan Pengurugan kembali galian tanah (1/3 dari pekerjaan galian)
Ukuran/Dimensi 20.00 M3
A Bahan :
1 Tidak ada
Sub Total (A)
B Alat :
1 Cangkul Swadaya
2 Skop Swadaya
3 Ember Swadaya
Sub Total (B)
C Upah :
1 Pekerja HOK 10.00 10.00 100,000.00 1,000,000.00
2 Mandor HOK
Sub Total (C) 1,000,000.00
Sub Total (A+B+C) 1,000,000.00
III Jenis Kegiatan Pekerjaan Bronjong Tipe 1
Ukuran/Dimensi 79.00 M3
A Bahan :
1 Batu Gunung Belah 15/20 cm m3 102.70 102.70 217,485.00 22,335,709.50
Ongkos Angkut m3 102.70 102.70 160,703.00 16,504,198.10
2 Kawat Bronjong Tipe 1 Unit 79.00 79.00 334,500.00 26,425,500.00
Ongkos Angkut Unit 79.00 79.00 5,000.00 395,000.00
Sub Total (A) 65,660,407.60
B Alat :
1 Tang Buah 46,000.00 Swadaya
2 Gerobak Sorong Buah 2.00 2.00 508,000.00 1,016,000.00
3 Sarung Tangan Swadaya
Sub Total (B) 1,016,000.00
C Upah :
1 Pekerja HOK 19.75 19.75 100,000.00 1,975,000.00
2 Mandor HOK
Sub Total (C) 1,975,000.00
Sub Total (A+B+C) 68,651,407.60
IV Jenis Kegiatan Pekerjaan Bronjong Tipe 2
Ukuran/Dimensi 154.50 M3
A Bahan :
1 Batu Gunung Belah 15/20 cm m3 301.28 301.28 217,485.00 65,522,793.38
Ongkos Angkut m3 301.28 301.28 160,703.00 48,415,796.33
2 Kawat Bronjong Tipe 2 Unit 154.50 154.50 488,370.00 75,453,165.00
Ongkos Angkut Unit 154.50 154.50 5,000.00 772,500.00
Sub Total (A) 190,164,254.70
B Alat :
1 Tang Buah 2.00 2.00 46,000.00 92,000.00 Swadaya
2 Gerobak Sorong Buah 2.00 2.00 508,000.00 1,016,000.00
3 Sarung Tangan Swadaya
Sub Total (B) 1,108,000.00
C Upah :
1 Pekerja HOK 57.94 57.94 100,000.00 5,793,750.00
2 Mandor HOK
Sub Total (C) 5,793,750.00
Sub Total (A+B+C) 197,066,004.70
V Jenis Kegiatan Pekerjaan Bronjong Tipe 3
Ukuran/Dimensi 22.50 M3
A Bahan :
1 Batu Gunung Belah 15/20 cm m3 65.81 65.81 217,485.00 14,313,231.56
Ongkos Angkut m3 65.81 65.81 160,703.00 10,576,266.19
2 Kawat Bronjong Tipe 3 Unit 22.50 22.50 669,000.00 15,052,500.00
Ongkos Angkut Unit 22.50 22.50 5,000.00 112,500.00
Sub Total (A) 40,054,497.75
B Alat :
1 Tang Buah 2.00 2.00 46,000.00 92,000.00
2 Gerobak Sorong Buah 3.00 3.00 508,000.00 1,524,000.00
3 Sarung Tangan Swadaya
Sub Total (B) 1,616,000.00
C Upah :
1 Pekerja HOK 12.66 12.66 100,000.00 1,265,625.00
2 Mandor HOK
Sub Total (C) 1,265,625.00
Sub Total (A+B+C) 42,936,122.75
Dana APBDes 316,202,918.10
Dana APBDes 316,202,918.10
Biaya Umum 15,810,145.90
Total Biaya
Dibuat Oleh:
Disetujui/Mengesahkan: Kepala Seksi Pembangunan
KEPALA DESA MADOLAOLI TIM PENGELOLA KEGIATAN (TPK)
Dibuat Oleh:
Disetujui/Mengesahkan: Kepala Seksi Pembangunan
KEPALA DESA MADOLAOLI TIM PENGELOLA KEGIATAN (TPK)
HARGA UPAH
UPAH KERJA
NO JENIS PEKERJA SATUAN (Rp) KETERANGAN
HARGA
NO URAIAN SATUAN KETERANGAN
(Rp)
Dibuat Oleh:
Disetujui/Mengesahkan: Kepala Seksi Pembangunan
KEPALA DESA MADOLAOLI TIM PENGELOLA KEGIATAN (TPK)
A. BAHAN
1. Material Bahan Lokal
1.1. Batu Gunung Belah 15/20 cm m3 179,000.00 17,900.00 17,900.00 2,685.00 217,485.00
2. Material Pabrikasi
B. ALAT
1 Gerobak Sorong Merk Artco Buah 508,000.00
2 Tang Ukuran Sedang Buah 46,000.00
3 Linggis Besar Buah 133,437.88
Disetujui/Mengesahkan:
KEPALA DESA MADOLAOLI
FEBRIANTO LAOLI
HARGA BAHAN
MATAN GUNUNGSITOLI
10.00 508,000.00
10.00 46,000.00
10.00 137,345.76
Dibuat Oleh:
Kepala Seksi Pembangunan
TIM PENGELOLA KEGIATAN (TPK)
Dimensi
No Uraian Volume Satuan Keterangan
p l t n
1 2 3 4 5 6 7 8 9
Dibuat Oleh:
Kepala Seksi Pembangunan
TIM PENGELOLA KEGIATAN (TPK)