LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

MINGGU KE: 022


PERIODE : 04 Januari 2021 s/d 10 Januari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/TAMBRAUW KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I KONTRAK TA.2021
KONTRAK TA.2020 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 Adendum I SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 - - - - - 0.37 0.58
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 - - - - - 0.40 0.77
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 - - - - - 0.58 0.96
DIVISI 2. DRAINASE
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 - - - - - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 - - - - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 - - - - - 3.33 0.00
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - - - - - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 - - - - - 431.69 41.45
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - 6.90 0.62 - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 - - - - - 44,900.90 25.42
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - - -
7.6.(14a) M' 12 mm 90.00
Pemancangan Tiang Pancang Baja Diameter 400 mm tebal 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 - - - 100.00
(A) Rencana Kemajuan Pekerjaan (%) - 3.32 3.32
(B) Realisasi Kemajuan Pekerjaan (%) - - -
(C) Deviasi (%) (+/-) - (3.32) (3.32)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

JOHNY MALONDA RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19640625 199103 1 009 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 023
PERIODE : 11 Januari 2021 s/d 17 Januari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/TAMBRAUW KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I KONTRAK TA.2021
KONTRAK TA.2020 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 Adendum I SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 - - - - - - 0.37 0.58
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 - - - - - - 0.40 0.77
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 - - - - - - 0.58 0.96
0 DIVISI 2. DRAINASE 0 - - -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97
0 DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 - - - - - - 3.33 0.00
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - - - - - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
0 DIVISI 7. STRUKTUR 0 - - - - - - - - - - - - - -
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 - - - - - - 431.69 41.45
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 - - 14,468.67 8.19 14,468.67 8.19 30,432.23 17.23
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.0 100.00 - 8.19 8.19 81.63
(A) Rencana Kemajuan Pekerjaan (%) 3.32 6.98 10.30
(B) Realisasi Kemajuan Pekerjaan (%) - 8.19 8.19
(C) Deviasi (%) (+/-) (3.32) 1.22 (2.10)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

JOHNY MALONDA RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19640625 199103 1 009 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 024
PERIODE : 18 Januari 2021 s/d 24 Januari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I
KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 SISA PEKERJAAN
MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 - - - - - - 0.37 0.58
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 - - - - - - 0.40 0.77
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 - - - - - - 0.58 0.96
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 - - - - - - 3.33 0.00
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - - - - - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 - - 121.49 11.67 121.49 11.67 310.19 29.78
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 14,468.67 8.19 - - 14,468.67 8.19 30,432.23 17.23
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 8.19 11.67 19.86 69.96
(A) Rencana Kemajuan Pekerjaan (%) 10.30 6.98 17.27
(B) Realisasi Kemajuan Pekerjaan (%) 8.19 11.67 19.86
(C) Deviasi (%) (+/-) (2.10) 4.69 2.59
Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,
KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

JOHNY MALONDA RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19640625 199103 1 009 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 025
PERIODE : 25 Januari 2021 s/d 31 Januari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I
KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 - - - - - - 0.37 0.58
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 - - - - - - 0.40 0.77
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 - - - - - - 0.58 0.96
0 DIVISI 2. DRAINASE 0 - -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 - - - - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 - - - - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 - - - - - - 3.33 0.00
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - - - - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 121.49 11.67 - - 121.49 11.67 310.19 29.78
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 14,468.67 8.19 11,964.18 6.77 26,432.86 14.97 18,468.05 10.46
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 19.86 6.77 26.63 73.37
(A) Rencana Kemajuan Pekerjaan (%) 17.27 8.36 25.63
(B) Realisasi Kemajuan Pekerjaan (%) 19.86 6.77 26.63
(C) Deviasi (%) (+/-) 2.59 (1.58) 1.01
Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,
KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

JOHNY MALONDA RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19640625 199103 1 009 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 026
PERIODE : 01 Februari 2021 s/d 07 Februari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I
KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 - - - - - - 0.37 0.58
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 - - - - - - 0.40 0.77
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 - - 0.08 0.13 0.08 0.13 0.50 0.83
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 - - - - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 - - - - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 - - 3.33 0.00 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - - - - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 121.49 11.67 20.59 1.98 142.08 13.64 289.61 27.81
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 26,432.86 14.97 9,054.42 5.13 35,487.28 20.09 9,413.63 5.33
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 26.63 7.24 33.87 66.13
(A) Rencana Kemajuan Pekerjaan (%) 25.63 8.36 33.99
(B) Realisasi Kemajuan Pekerjaan (%) 26.63 7.24 33.87
(C) Deviasi (%) (+/-) 1.01 (1.12) (0.12)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 027
PERIODE : 08 Februari 2021 s/d 14 Februari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I
KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 - - 0.07 0.11 0.07 0.11 0.30 0.47
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 - - 0.05 0.10 0.05 0.10 0.35 0.68
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.08 0.13 0.05 0.08 0.13 0.21 0.45 0.75
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 142.08 13.64 - - 142.08 13.64 289.61 27.81
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 35,487.28 20.09 4,970.00 2.81 40,457.28 22.91 4,443.63 2.52
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 33.87 3.10 36.97 52.85
(A) Rencana Kemajuan Pekerjaan (%) 33.99 10.18 44.17
(B) Realisasi Kemajuan Pekerjaan (%) 33.87 3.10 36.97
(C) Deviasi (%) (+/-) (0.12) (7.08) (7.20)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 028
PERIODE : 15 Februari 2021 s/d 21 Februari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I
KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 0.07 0.11 0.05 0.08 0.12 0.19 0.25 0.39
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 0.05 0.10 0.05 0.10 0.10 0.19 0.30 0.58
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.13 0.21 0.05 0.08 0.18 0.30 0.40 0.67
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 142.08 13.64 59.65 5.73 201.73 19.37 229.96 22.08
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 40,457.28 22.91 4,443.63 2.52 44,900.90 25.42 - -
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 36.97 8.50 45.47 44.35
(A) Rencana Kemajuan Pekerjaan (%) 44.17 10.99 55.16
(B) Realisasi Kemajuan Pekerjaan (%) 36.97 8.50 45.47
(C) Deviasi (%) (+/-) (7.20) (2.49) (9.69)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 029
PERIODE : 22 Februari 2021 s/d 28 Februari 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I
KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
TA.2020-2021 TA.2021 SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN MINGGU LALU MINGGU INI S/D MINGGU INI
BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 0.12 0.19 - - 0.12 0.19 0.25 0.39
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 0.10 0.19 - - 0.10 0.19 0.30 0.58
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.18 0.30 - - 0.18 0.30 0.40 0.67
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 - - - - - - 181.93 8.97
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 - - - - - - 1,428.45 1.21
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 201.73 19.37 - - 201.73 19.37 229.96 22.08
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 44,900.90 25.42 - - 44,900.90 25.42 - -
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - - - - - 376.52 16.98
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 45.47 - 45.47 54.53
(A) Rencana Kemajuan Pekerjaan (%) 55.16 9.94 65.11
(B) Realisasi Kemajuan Pekerjaan (%) 45.47 - 45.47
(C) Deviasi (%) (+/-) (9.69) (9.94) (19.63)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 030
PERIODE : 01 Maret 2021 s/d 07 Maret 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
SISA PEKERJAAN
MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 0.12 0.19 0.05 0.08 0.17 0.26 0.20 0.31
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 0.10 0.19 0.10 0.19 0.20 0.39 0.20 0.39
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.18 0.30 0.20 0.33 0.38 0.63 0.20 0.34
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 - - 90.97 4.49 90.97 4.49 90.97 4.49
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 - - 714.23 0.60 714.23 0.60 714.23 0.60
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - - - - - 450.19 0.18
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 201.73 19.37 53.61 5.15 255.34 24.52 176.35 16.93
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 44,900.90 25.42 - - 44,900.90 25.42 - -
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 - - 188.26 8.49 188.26 8.49 188.26 8.49
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 45.47 19.33 64.81 35.19
(A) Rencana Kemajuan Pekerjaan (%) 65.11 8.20 73.30
(B) Realisasi Kemajuan Pekerjaan (%) 45.47 19.33 64.81
(C) Deviasi (%) (+/-) (19.63) 11.14 (8.50)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 031
PERIODE : 08 Maret 2021 s/d 14 Maret 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
SISA PEKERJAAN
MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 0.17 0.26 0.05 0.08 0.22 0.34 0.15 0.24
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 0.20 0.39 0.05 0.10 0.25 0.48 0.15 0.29
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.38 0.63 0.05 0.08 0.43 0.71 0.15 0.25
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 90.97 4.49 - - 90.97 4.49 90.97 4.49
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 714.23 0.60 714.23 0.60 1,428.45 1.21 - -
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 - - 450.19 0.18 450.19 0.18 - -
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 255.34 24.52 121.49 11.67 376.83 36.18 54.86 5.27
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 44,900.90 25.42 - - 44,900.90 25.42 - -
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 188.26 8.49 - - 188.26 8.49 188.26 8.49
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 64.81 12.70 77.51 22.49
(A) Rencana Kemajuan Pekerjaan (%) 73.30 8.64 81.94
(B) Realisasi Kemajuan Pekerjaan (%) 64.81 12.70 77.51
(C) Deviasi (%) (+/-) (8.50) 4.07 (4.43)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 032
PERIODE : 15 Maret 2021 s/d 21 Maret 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
SISA PEKERJAAN
MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 0.22 0.34 0.05 0.08 0.27 0.42 0.10 0.16
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 0.25 0.48 0.05 0.10 0.30 0.58 0.10 0.19
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.43 0.71 0.05 0.08 0.48 0.79 0.10 0.17
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 90.97 4.49 - - 90.97 4.49 90.97 4.49
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 1,428.45 1.21 - - 1,428.45 1.21 - -
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 450.19 0.18 - - 450.19 0.18 - -
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 376.83 36.18 - - 376.83 36.18 54.86 5.27
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 44,900.90 25.42 - - 44,900.90 25.42 - -
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 188.26 8.49 188.26 8.49 376.52 16.98 - -
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 77.51 8.75 86.26 13.74
(A) Rencana Kemajuan Pekerjaan (%) 81.94 8.79 90.73
(B) Realisasi Kemajuan Pekerjaan (%) 77.51 8.75 86.26
(C) Deviasi (%) (+/-) (4.43) (0.04) (4.47)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
MINGGU KE: 033
PERIODE : 22 Maret 2021 s/d 28 Maret 2021 No & Tgl. KONTRAK : 02/HK.02.03/PJ.GUHMA/PJN.III/PPK3.2/APBN/2020, Tgl. 05 Agustus 2020
Nilai Kon. TA.2020-2021 Rp 5,031,381,000
SATKER : PELAKSANAAN JALAN NASIONAL WILAYAH III PROV. PAPUA BARAT (MAYBRAT) Nilai Kon. TA.2020 Rp 1,138,540,000
PPK : 3.2 No & Tgl. ADD I TA.2021: 02/HK.02.03/ADD-I/PJ.GUHMA/PJN.III/PPK3.2/APBN/2021, Tgl. 04 Januari 2021
PAKET : PENGGANTIAN JEMBATAN GUHMA Nilai Kon. TA.2021 Rp 3,892,841,000
PROV./KAB. : PAPUA BARAT/MAYBRAT KONTRAKTOR : CV. IRENIA STAR
KONSULTAN : PT. WINSOLUSI KSO PT. DELTA TAMA WAJA CORPORA
KONTRAK Kontrak Adendum I KONTRAK TA.2020 KONTRAK TA.2021 REALISASI PEKERJAAN
SISA PEKERJAAN
MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN BOBOT BOBOT BOBOT BOBOT
VOLUME VOLUME VOLUME VOLUME BOBOT BOBOT BOBOT BOBOT
(%) (%) (%) (%) VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.95 1.00 3.95 0.70 12.23 0.30 1.53 - - - - - - 0.30 1.53
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.21 1.00 1.21 0.63 3.35 0.37 0.58 0.27 0.42 0.05 0.08 0.32 0.50 0.05 0.08
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 1.50 1.00 1.50 0.60 3.97 0.40 0.77 0.30 0.58 0.05 0.10 0.35 0.68 0.05 0.10
1.21 Manajemen Mutu Ls 1.00 1.28 1.00 1.28 0.42 2.35 0.58 0.96 0.48 0.79 0.05 0.08 0.53 0.87 0.05 0.09
DIVISI 2. DRAINASE -
2.2.(1) Pasangan Batu dengan Mortar M3 167.46 6.39 181.93 6.94 - - 181.93 8.97 90.97 4.49 - - 90.97 4.49 90.97 4.49
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1) Galian Biasa M3 3,805.30 2.49 1,428.45 0.93 - - 1,428.45 1.21 1,428.45 1.21 - - 1,428.45 1.21 - -
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 45.61 0.03 48.94 0.03 45.61 0.11 3.33 0.00 3.33 0.00 - - 3.33 0.00 - -
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 141.02 0.10 - - - - - -
3.2.(1b) Timbunan Biasa dari hasil galian M3 412.82 0.12 450.19 0.14 - - 450.19 0.18 450.19 0.18 - - 450.19 0.18 - -
3.2.(2a) Timbunan Pilihan dari sumber galian M3 113.75 0.70 124.70 0.77 - - 124.70 0.99 - - - - - - 124.70 0.99
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 473.34 35.16 448.38 33.31 16.69 5.48 431.69 41.45 376.83 36.18 - - 376.83 36.18 54.86 5.27
7.1 (7a) Beton strukur, fc’20 MPa M3 7.08 0.49 6.90 0.48 - - 6.90 0.62 - - - - - - 6.90 0.62
7.1 (10) Beton, fc’10 Mpa M3 14.68 0.74 14.68 0.74 14.68 3.28 - - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 496.21 0.20 496.21 0.20 496.21 0.90 - - - - - - - - - -
7.3 (3) Baja Tulangan Sirip BjTS 420A Kg 62,607.71 27.43 66,717.24 29.23 21,816.34 42.24 44,900.90 25.42 44,900.90 25.42 - - 44,900.90 25.42 - -
7.6.(8a) Penyediaan Tiang Pancang Baja Diameter 400 mm tebalM'
12 mm 90.00 5.16 90.00 5.16 90.00 22.79 - - - - - - - - -
7.6.(14a) Pemancangan Tiang Pancang Baja Diameter 400 mm tebal
M' 12 mm 90.00 0.75 90.00 0.75 90.00 3.30 - - - - - - - - -
7.9.(1) Pasangan Batu M3 345.35 12.05 376.52 13.14 - - 376.52 16.98 376.52 16.98 - - 376.52 16.98 - -
7.13.(1) Sandaran (Railing) M' 47.20 0.09 47.20 0.09 - - 47.20 0.12 - - - - - - 47.20 0.12
7.14.(1) Papan Nama Jembatan Buah 2.00 0.02 2.00 0.02 - - 2.00 0.02 - - - - - - 2.00 0.02
:7.16.(3a) Pipa Drainase PVC diameter 150 mm M' 6.00 0.01 6.00 0.01 - - 6.00 0.01 - - - - - - 6.00 0.01
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(5) Patok Pengarah Buah 40.00 0.13 40.00 0.13 - - 40.00 0.17 - - - - - - 40.00 0.17
JUMLAH 100.00 100.00 100.00 100.00 86.26 0.26 86.51 13.49
(A) Rencana Kemajuan Pekerjaan (%) 90.73 8.65 99.38
(B) Realisasi Kemajuan Pekerjaan (%) 86.26 0.26 86.51
(C) Deviasi (%) (+/-) (4.47) (8.40) (12.87)

Disetujui Oleh, Diperiksa Oleh: Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN Konsultan Supervisi KONTRAKTOR PELAKSANA
PPK 3.2 PT. WINSOLUSI KONSULTAN KSO CV. IRENIA STAR
PT. DELTA TAMA WAJA CORPORA

MAYSON W. IROTH, ST RISWAN RAZAK, ST. HERU KRISWANTO


NIP. 19790514 201412 1002 Inspection Engineer Jembatan Site Manager