PEKERJAAN : Rehabiltasi ruang kelas dengan tingkat kerusakan minimal sedang beserta perabotnya SD Negeri 02 Parit Limau Manis (DAK Reguler SD Tahun 2021)
NOMOR KONTRAK : 602/025/Tender.JK.R.Kelas.SDN.02.Parit.Limau.Manis/S.Per/PEND-II.B/2021
TANGGAL : 16 Juli 2021
AMANDEMEN : 0
TANGGAL : 0
TAHUN ANGGARAN : 2021
SUMBER DANA : DAK Reguler
LOKASI : SD Negeri 02 Parit Limau Manis
WAKTU PELAKSANAAN
Bulan 1 ( Satu ) Bulan 2 ( Dua ) Bulan 3 ( Tiga ) Bulan 4 ( Empat ) KET
BOBOT
BOBOT
NO. URAIAN PEKERJAAN KONTRAK M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17
ADD (%)
(%)
16-Jul-2021 23-Jul-2021 30-Jul-2021 6-Aug-2021 13-Aug-2021 20-Aug-2021 27-Aug-2021 3-Sep-2021 10-Sep-2021 17-Sep-2021 24-Sep-2021 1-Oct-2021 8-Oct-2021 15-Oct-2021 22-Oct-2021 29-Oct-2021 5-Nov-2021
22-Jul-2021 29-Jul-2021 5-Aug-2021 12-Aug-2021 19-Aug-2021 26-Aug-2021 2-Sep-2021 9-Sep-2021 16-Sep-2021 23-Sep-2021 30-Sep-2021 7-Oct-2021 14-Oct-2021 21-Oct-2021 28-Oct-2021 4-Nov-2021 12-Nov-2021
100 %
1 PEKERJAAN PENDAHULUAN 0,99 0,33 0,33 0,33
2 PEKERJAAN LANTAI RUANG KELAS 50,08 4,17 4,17 4,17 4,17 4,17 4,17 4,17 4,17 4,17 4,17 4,17 4,17
50 %
5 PEKERJAAN PLAFON 9,51 3,17 3,17 3,17
0%
9 PELAKSANAAN K3 0,56 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03
RENCANA KEMAJUAN PERMINGGU 0 0,36 0,36 0,36 5,26 5,26 8,43 9,59 11,76 8,59 8,59 8,59 9,21 7,42 6,79 6,79 2,62 0,03
RENCANA KOMULATIF PERMINGGU 0 0,36 0,72 1,09 6,34 11,60 20,03 29,62 41,38 49,97 58,55 67,14 76,35 83,77 90,56 97,35 99,97 100,00
RALISASI KEMAJUAN PERMINGGU 0 0,66 0,39 1,91 5,45 8,04 7,82 9,73 15,99 10,43 7,94
REALISASI KOMULATIF SAMPAI MINGGU KE 0 0,66 1,05 2,96 8,41 16,45 24,27 34,00 49,99 60,42 68,36
DEVIASI ( + ) ( - ) 0,30 0,33 1,88 2,07 4,85 4,24 4,38 8,61 10,46 9,81
1 4 12 25