Anda di halaman 1dari 13

LUAS TANAH 108 M2

LUAS BANGUNAN 45 M2
ANGGARAN BIAYA 79890000 RUPIAH
NO URAIAN PEKERJAAN VOLUME HARGA SATUAN
A PEKERJAAN TANAH
1 GALIAN PONDASI 27.00 M3 Rp 26,081.63
2 URUGAN KEMBALI 10.80 M3 Rp 26,081.63
3 URUGAN PASIR PAWAH PONDASI 2.70 M3 Rp 193,689.80
4 URUGAN PASIR BAWAH LANTAI 4.50 M3 Rp 193,689.80
TOTAL
B PEKERJAAN PASANGAN BETON
1 PASANGAN BATU KALI PONDASI 14.4 M3 Rp 474,805.56
2 BALOK SLOOF BETON 15/20 1.5 M3 Rp 1,160,819.44
3 PASANGAN BATA TRANSRAM 28.8 M3 Rp 93,126.58
4 PASANGAN BATA BIASA 90 M3 Rp 50,676.58
5 PLESTERAN TRANSRAM 57.6 M2 Rp 50,640.86
6 PLESTERAN BIASA 180 M2 Rp 50,283.72
7 KOLOM PRAKTIS 1 M3 Rp 1,691,480.44
8 RING BALOK 1.5 M3 Rp 1,691,480.44
9 PLAT KANOPI DAN ATAP 0.875 M3 Rp 898,319.44
TOTAL
C PEKERJAAN PINTU DAN JENDELA
1 PINTU DAN JENDELA UTAMA 2 BH Rp 797,335.19
2 PINTU R TIDUR 2 BH Rp 797,335.19
3 PINTU KM/ WC 1 BH Rp 423,585.19
7 JENDELA 2 DAUN 3 BH Rp 1,999,670.37
9 JENDELA MATI R TIDUR 3 BH Rp 999,835.19
10 BV KACA 1 BH Rp 538,585.19
TOTAL

D PEEKRJAAN ATAP
1 RANGKA ATAP BAJA RINGAN 67.5 M2 Rp 241,751.00
2 PENUTUP ATAP 67.5 M2 Rp 278,085.00
3 KERPUS/ BUBUNGAN 8 M' Rp 35,933.00
5 LISPLANK GRC RANGKA KAYU 45 M' Rp 393,585.00
TOTAL
E PEKERJAAN LANGIT-LANGIT
PLAFOND GYPSUM 45 M2 Rp 42,550.00
TOTAL
F PEKERJAAN LANTAI
KERAMIK LANTAI 45 m2 Rp 133,981.00
KERAMIK LANTAI KM/ WC 3 m2 Rp 133,981.00
KERAMIK DINDING KM/WC 9 m2 Rp 133,981.00
KERAMIK MEJA DAPUR 3 m2 Rp 133,981.00
LANTAI RABAT 0.675 m3 Rp 35,933.00
TOTAL
G PEKERJAAN CAT
CAT DINDING 270 M2 Rp 48,289.00
CAT PLAFOND 90 M2 Rp 47,273.00
CAT LISPLANK 9 M2 Rp 47,273.00

H PEKERJAAN LISTRIK
TITIK LAMPU 6 TITIK Rp 286,824.00
SAKLAR 5 BH Rp 286,824.00
LAMPU DOWNLIGHT + PL 14 W 6 BH Rp 59,180.00
STOP KONTAK 5 BH Rp 28,600.00

G PEKERJAAN SANITASI
CLOSED DUDUK 1 bh Rp 800,000.00
HAND SHOWER 1 bh Rp 145,000.00
KRAN AIR 1 bh Rp 50,000.00
FLOOR DRAIN 1 bh Rp 65,000.00
WASH BAK 1 bh Rp 525,000.00
KRAN DAPUR 1 bh Rp 65,000.00
SALURAN AIR BERSIH 14 bh Rp 20,000.00
SALURAN AIR BEKAS 11 bh Rp 20,000.00
SALURAN AIR KOTOR 7 bh Rp 20,000.00
SEPTITANK 1 bh Rp 2,550,000.00
PERESAPAN 1 bh Rp 250,000.00
TOTAL
TOTAL KESELURUHAN
JUMLAH HARGA

Rp 704,204
Rp 281,682
Rp 522,962
Rp 871,604
Rp 2,380,452.27

Rp 6,837,200.00
Rp 1,741,229.17
Rp 2,682,045.63
Rp 4,560,892.60
Rp 2,916,913.79
Rp 9,051,070.40
Rp 1,691,480.44
Rp 2,537,220.67
Rp 786,029.51
Rp 32,804,082.22

Rp1,594,670
Rp1,594,670
Rp423,585
Rp5,999,011
Rp2,999,506
Rp538,585
Rp13,150,028

Rp 16,318,192.50
Rp 18,770,737.50
Rp 287,464.00
Rp 17,711,325.00
Rp 53,087,719.00

Rp 1,914,750.00
Rp 1,914,750.00

Rp 6,029,145.00
Rp 401,943.00
Rp 1,205,829.00
Rp 401,943.00
Rp 24,254.78
Rp 8,063,114.78

Rp 13,038,030.00
Rp 4,254,570.00
Rp 425,457.00
Rp 17,718,057.00

Rp 1,720,944.00
Rp 1,434,120.00
Rp 355,080.00
Rp 143,000.00
Rp 3,653,144.00

Rp 800,000.00
Rp 145,000.00
Rp 50,000.00
Rp 65,000.00
Rp 525,000.00
Rp 65,000.00
Rp 280,000.00
Rp 220,000.00
Rp 140,000.00
Rp 2,550,000.00
Rp 250,000.00
Rp 5,090,000.00
Rp 137,861,347.04
TIME SCHEDULE & KURVA - S

Bobot
WAKTU PELAKSANAAN = 90 HARI KALENDER
NO URAIAN Nilai Pekerjaan Pekerjaan KET.
Minggu Ke

96.56 8091 9378 336


(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14
1-7 8-14 15-21 22-28 29-35 36-42 43-49 50-56 57-63 64-70 71-77 78-84 85-89 90

89 .7 7929 1296 3612


83.588 60837 5149 1
79.93 6405 65146 62
A PEKERJAAN TANAH 2,380,452.27 1.73% 0.017 100

100

10 0
73 .6 7301 5659 7684
B PEKERJAAN PASANGAN BETON 32,804,082.22 23.79% 0.048 0.048 0.048 0.048 0.048

56.4408 4051 8931 5


C PEKERJAAN PINTU DAN JENDELA 13,150,027.78 9.54% 0.024 0.024 0.024 0.024 75
D PEEKRJAAN ATAP 53,087,719.00 38.51% 0.096 0.096 0.096 0.096

39.988 2840 0290 18


E PEKERJAAN LANGIT-LANGIT 1,914,750.00 1.39% 0.007 0.007

27.0 7635 27928 129


50

18.8297 8056 7837 9


F PEKERJAAN LANTAI 8,063,114.78 5.85% 0.012 0.012 0.012 0.012 0.012

10.583 2083 4286 29


G PEKERJAAN CAT 17,718,057.00 12.85% 0.064 0.064

2.33 6636 11788 787


25

1.1 6831 8058 9439 3


H PEKERJAAN LISTRIK 3,653,144.00 2.65% 0.013 0.013

I PEKERJAAN SANITASI 5,090,000.00 3.69% 0.018 0.018


0

0
Jumlah Bobot Pekerjaan 137,861,347.043 100.00%
Kemajuan Pekerjaan Mingguan 0.017 0.048 0.048 0.048 0.090 0.090 0.120 0.132 0.179 0.179 0.012 0.025 0.013 -
Kemajuan Pekerjaan Kumulatif - - 0.017 0.065 0.112 0.160 0.250 0.340 0.460 0.592 0.771 0.950 0.962 0.987 1.000 1.000

48
MENENTUKAN KOEFISIEN

P M
L M
T M

HASIL TEST
P 1M
L 1M
T 1M TANAH PASANGAN BETON ATAP
V 1 M3 36 288 67.5
BERAPA CANGKUL 555 KALI
WAKTU 7 JAM 98 196 98
KOEFISIEN 0.142857 0.367347 0.680556 1.451852
HARGA DASAR SATUAN UPAH

HARGA HARGA SATUAN


JAM KERJA
No. URAIAN SATUAN SATUAN PER HARI EFFEKTIF
( Rp.) ( Rp.)

1. mandor Jam 13,142.86 92,000.00 7 jam /hari


2. pekerja Jam 8,875.00 71,000.00 7 jam /hari
3. tukang batu Jam 10,375.00 83,000.00 7 jam /hari
4. kepala tukang batu Jam 11,000.00 88,000.00 7 jam /hari
5. tukang kayu Jam 10,375.00 83,000.00 7 jam /hari
6. kepala tukang kayu Jam 11,000.00 88,000.00 7 jam /hari
7. tukang besi Jam 10,375.00 83,000.00 7 jam /hari
8. kepala tukang besi Jam 11,000.00 88,000.00 7 jam /hari
9. tukang cat Jam 10,375.00 83,000.00 7 jam /hari
10. kepala tukang cat Jam 11,000.00 88,000.00 7 jam /hari
11. tukang plitur Jam 10,375.00 83,000.00 7 jam /hari
12 kepala tukang plitur Jam 11,000.00 88,000.00 7 jam /hari

Jakarta, 29 Juli 2019


Penyedia,
CV. SINAR CAHAYA MUDA

BETMAN LUBIS, SE
Direktur
HARGA DASAR SATUAN BAHAN HARGA PEROLEHAN

HARGA Harga
No. URAIAN KODE SATUAN SATUAN No.
( Rp.)
1 Pasir cor M01a m³ 250,000.00###
2 Pasir cor M01b kg 178.57###
3 Pasir Pasang M09 KG 160.00###
4 Pasir Urug M17 m³ 150,000.00###
5 Tanah Urug M25 m³ 65,000.00###
6 Sirtu M26 m³ 150,000.00###
7 Batu pecah 2/3 cm (split) M27 m³ 260,000.00###
8 Batu pecah 2/3 cm (split) M28 Kg 184.62###
9 Air M30 liter 50.00###
10 Batu belah M31a m³ 220,000.00###
11 PC M31b kg 1,250.00###
12 Semen warna (40 kg) M35 zak 680,000.00###
13 Semen putih (40 kg) M35 zak 92,500.00###
14 Batu Bata M36 bh 750.00###
15 Kapur Pasang M37 m³ 270,000.00###
16 Besi Beton (Polos/Ulir) M38.a kg 13,250.00###
17 Kawat bendrat M38.b kg 19,800.00###
18 Besi Profil Siku M38.b kg 13,800.00###
19 Besi Profil C M39.a kg 13,800.00###
20 Paku usuk/ reng/ eternit M39.b kg 15,000.00###
21 Paku Sekrup M39.c kg 15,000.00###
22 Keramik Lantai KM/WC 20/20 cm Roman Anti Selip M40 m² 95,000.00###
23 Keramik Dinding 20/25 Roman m² 97,500.00
24 Keramik 20/20 cm Roman Polos Dinding muda m² 94,500.00
25 Keramik 20/20 cm Roman Polos meja pantry M41 m² 95,000.00###
26 Keramik 5/20 cm sekualitas Roman Motif Teracota M42 m² 115,000.00
###
27 Keramik List Dinding 7 x 20 cm sekualitas Asia Tile M43 bh 7,500.00###
28 Keramik lantai 40/40 cm sekualitas Asia (warna muda) M56 m² 59,000.00 B e n s
29 Granite Tile Niro Granite Splash Beige M57 m² 175,000.00 S o l a r
30 Granite Tile Niro Unpolish 60/60 cm M58 m² 257,500.00 Minyak
31 Lem Kayu M59 kg 25,000.00 Minyak
32 Granit anti selip 8 x30 cm (ujung pas keramik tangga) M65.a bh 11,500.00 PCI Gird
33 Kalsiboard 1,2 x2,4 m tebal 4 mm M65.b lbr 85,000.00 PCI Gird
34 Bambu Ori M65.c bt 15,000.00 PCI Gird
35 Papan Sengon tebal 2 cm M65.d m³ 2,000,000.00 PCI Gird
36 kayu jati balok M65.e m³ 22,500,000.00 PCI Gird
37 kayu jati papan M65.f m³ 25,000,000.00 PCI Gird
38 kayu jati reng M66 m³ 8,625,000.00 Tiang P
39 kayu kruing 5/7 cm M67 m³ 6,730,000.00 Tiang P
40 kayu kamper balok 6/12 M68 m³ 9,100,000.00 Mini Tim
41 kayu kamper papan M69 m³ 10,250,000.00 Mikro P
42 kayu kruing papan 20 cm M70.a m³ 7,500,000.00 Joint So
43 kayu bangkirai balok M70.b m³ 12,100,000.00 Joint So
44 kayu bangkirai 5/7 cm M71 m³ 9,000,000.00 Elastom
45 kayu bangkirai papan M72.a m³ 14,000,000.00 Elastom
46 kayu meranti/ lanan bekisting M72.b m³ 6,000,000.00 Elastom
47 balok kayu meranti/ lanan M72.c m³ 5,250,000.00 Elastom
48 tripleks 9 mm M73 lbr 121,000.00 Anchora
49 tripleks 4 mm M74 lbr 62,700.00 Ducting
50 rangka holo galvanis 4/4 cm, panj 4 m profile tebal 0,65 M75 M 3,166.67 Ducting
51 rangka holo galvanis 2/4 cm, panj 4 m profile tebal 0,65 M76 M 2,583.33 Expansi
52 rod (besi penggantung) M77 m 4,500.00 Expansi
53 gypsum jaya board 9 mm M78 lbr 75,000.00 Expansi
HARGA Harga
No. URAIAN KODE SATUAN SATUAN No.
( Rp.)
1 Pasir cor M01a m³ 250,000.00###
54 GRC tebal 6 mm (1,2 x2,4) M79 lbr 155,000.00 Expansi
55 meni kayu cap pedang M80 kg 28,000.00 Expansi
56 woodplank tekstur kayu tebal 8 mm M81 ljr (4m) 79,000.00 Strip Be
57 cat genteng sekualitas mowilex kg 74,000.00 Bunker
58 cat tembok sekualitas catylac kg 30,000.00 Pemant
59 cat kayu sekualitas duco nippe M82 kg 65,000.00 Arbocel
60 cat mowilex weather shield M83 kg 120,000.00 Cat
61 cat mowilex interior M84 kg 80,000.00
62 cat lantai tennocote WA M85 kg 55,000.00
63 alkalie kg 25,000.00
64 minyak cat affiner B liter 16,000.00
65 minyak bekisting liter 9,000.00
66 plamur kayu merk pedang kg 28,000.00
67 water profing aquaprof kg 47,500.00
68 lem kayu kg 25,000.00
69 dempul kg 28,000.00
70 batu apung kg 9,700.00
71 politur impra liter 72,000.00
72 plamur tembok kg 27,000.00
73 amplas lbr 4,000.00
74 kaca bening 5 mm sekualitas ashahi m² 115,000.00
75 kaca flora warna 3 mm sekualitas ashahi bh 120,000.00
76 kunci tanam sekualitas merk solid bh 300,000.00
77 kunci tanam kamar mandi sekualitas ALPHA bh 75,000.00
78 engsel; 4" nylon bh 20,000.00
79 engsel 3" nylon bh 16,000.00
80 kait angin bh 16,000.00
81 expagnolet sekualitas solid bh 250,000.00
82 handel/ pegangan pintu 1 35,000.00
83 spring knip 1 12,000.00
84 handel jendela 1 12,500.00
85 profil kaca m 8,000.00
86 skrup metal roof bh 300.00
87 sealent tube 75,000.00
88 wastafel sekualitas TOTO unit 900,000.00
89 urinoir sekualitas TOTO UNIT 1,800,000.00
90 was bak stainless 1 lubang sekualitas royal/ waren UNIT 250,000.00
91 kloset jongkok sekualitas toto UNIT 450,000.00
92 kloset duduk sekualitas toto UNIT 2,460,000.00
93 floor drain stainless bh 40,000.00
94 roof drain kuningan bh 65,700.00
95 kran air d 3/4 sekualitas san ei bh 75,000.00
96 stop kran d1 bh 45,000.00
97 seal tape bh 3,750.00
98 galvalum lebar 60 cm tbl 0,3 m' 38,500.00
99 galvalum lebar 90 cm tbl 0,3 m' 43,000.00
100 buis beton d 20 cm m' 65,000.00
101 buis beton d 30 cm m' 72,000.00
102 buis beton u 20 cm m' 55,000.00
103 buis beton u 30 cm m' 60,000.00
104 ijuk kg 11,500.00
105 pipa pvc d 1/2 4m type AW sesuai sekualitas maspion ljr 22,500.00
106 pipa pvc d 3/4 4m type AW sesuai sekualitas maspion ljr 28,700.00
107 pipa pvc d 1 1/4 4m type AW sesuai sekualitas maspion ljr 67,600.00
HARGA Harga
No. URAIAN KODE SATUAN SATUAN No.
( Rp.)
1 Pasir cor M01a m³ 250,000.00###
108 pipa pvc d 1" 4m type AW sesuai sekualitas maspion ljr 39,200.00
109 pipa pvc d 3" 4m type AW sesuai sekualitas maspion ljr 170,000.00
110 pipa pvc d 4" 4m type AW sesuai sekualitas maspion ljr 281,000.00
111 pipa pvc d 6" 4m type AW sesuai sekualitas maspion ljr 616,000.00
112 pipa pvc d 2" 4m type AW sesuai sekualitas maspion ljr 86,500.00
113 kaca bening tebal 12 mm m2 440,000.00
114 kaca dop tebal 5 mm m2 165,000.00
115 kaca bening teball 8 mm m2 310,000.00
116 kaca bening tebal 10 mm m2 365,000.00
117 kaca flora warna tebal 5 mm m2 160,000.00
118 kaca es tebal 5 mm m2 160,000.00
119 pipa besi hitam d 6" (15,4 cm) tebal 6,2 mm lonjor 2,190,000.00
120 pipa besi hitam d 4" (10,16 cm) tebal 4,2 mm lonjor 804,000.00
121 pipa besi hitam d 2" (5,08 cm) tebal 2 mm lonjor 165,000.00
122 pipa besi hitam d 3" (7,62 cm) tebal 3 mm lonjor 603,000.00
123 batu andesit bakar 20 x 20 cm tebal 3 cm m2 320,000.00
124 paving segienam tebal 8 cm k 300 m2 140,250.00
125 grass block 8 cm sekualitas diamond m2 96,000.00
126 list profil gypsum sedang m 9,000.00
127 rot drat m' 4,250.00
128 lem kuning (fox) kg 35,650.00
129 kalsiboard 6 mm m2 120,000.00
130 GRC 6 mm (1,2 x 2,4) m lbr 155,000.00
131 mandor hari 92,000.00
132 pekerja hari 71,000.00
133 tukang batu hari 83,000.00
134 kepala tukang batu hari 88,000.00
135 tukang kayu hari 83,000.00
136 kepala tukang kayu hari 88,000.00
137 tukang besi hari 83,000.00
138 kepala tukang besi hari 88,000.00
139 tukang cat hari 83,000.00
140 kepala tukang cat hari 88,000.00
141 tukang plitur hari 83,000.00
142 kepala tukang plitur hari 88,000.00
ATAP M2 50,000.00
KANOPI BUAH 400,000.00
PINTU KAMAR MANDI/ WC BUAH 200,000.00
BOUVENLIGHT BUAH 300,000.00

Jakarta, 29 Juli 2019


Penyedia,
CV. SINAR CAHAYA MUDA

BETMAN LUBIS, SE
Direktur
ANALISA HARGA SATUAN PEKERJAAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : menggali 1 m3 tanah biasa sedalam 1 meter
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. pekerja (L01) Org/hari 0.3673 71,000.00 26,081.63

JUMLAH HARGA TENAGA 26,081.63

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26,081.63

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : mengurug kembali 1 m3 galian (SNI 2007)
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.3673 71,000.00 26,081.63

JUMLAH HARGA TENAGA 26,081.63

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26,081.63

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : mengurug kembali 1m3 pasir urug (SNI 2007)
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.3673 71,000.00 26,081.63

JUMLAH HARGA TENAGA 26,081.63

B. BAHAN
1. pasir urug m3 1.0000 150,000.00 150,000.00

JUMLAH HARGA BAHAN 150,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 176,081.63


E. OVERHEAD & PROFIT 10% x D 17,608.16
F. HARGA SATUAN PEKERJAAN ( D + E ) 193,689.80

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : mengurug 1 m3 tanah urug mendatangkan (SNI 2002)
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.3673 71,000.00 26,081.63 1.365462 0.195066


2. Mandor Org/hari 0.0250 92,000.00 2,300.00 0.682731 0.097533

JUMLAH HARGA TENAGA 28,381.63

B. BAHAN
1. pasir urug m3 1.2000 150,000.00 180,000.00

JUMLAH HARGA BAHAN 180,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 208,381.63


E. OVERHEAD & PROFIT 10% x D 20,838.16
F. HARGA SATUAN PEKERJAAN ( D + E ) 229,219.80

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Membuang 1 m3 tanah sejauh 30 meter (SNI 2007)

TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.3673 71,000.00 26,081.63 1.365462 0.195066


2. Mandor Org/hari 0.0100 92,000.00 920.00 0.682731 0.097533

JUMLAH HARGA TENAGA 27,001.63

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 27,001.63


E. OVERHEAD & PROFIT 10% x D 2,700.16
F. HARGA SATUAN PEKERJAAN ( D + E ) 29,701.80

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : memadatkan 1m3 tanah (per 20 cm)
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.5000 71,000.00 35,500.00 1.365462 0.195066


2. Mandor Org/hari 0.0500 92,000.00 4,600.00 0.682731 0.097533

JUMLAH HARGA TENAGA 40,100.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 40,100.00


E. OVERHEAD & PROFIT 10% x D 4,010.00
F. HARGA SATUAN PEKERJAAN ( D + E ) (100 kg) 44,110.00
HARGA SATUAN PEKERJAAN 441.10

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : urugan sirtu mendatangkan
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.2500 71,000.00 17,750.00 1.365462 0.195066


2. Mandor Org/hari 0.0250 92,000.00 2,300.00 0.682731 0.097533
JUMLAH HARGA TENAGA 20,050.00

B. BAHAN
1. Sirtu m3 1.20 150,000.00 180,000.00
JUMLAH HARGA BAHAN 180,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 200,050.00


E. OVERHEAD & PROFIT 10% x D 20,005.00
F. HARGA SATUAN PEKERJAAN ( D + E ) (100 kg) 220,055.00

#NAME?
#NAME?
#NAME?

#NAME?
#NAME?

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : memasang 1 m3 pondasi batu kosong (aanstamping) (SNI 2007)
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066


3. Tukang Batu Org/hari 0.6806 83,000.00 56,486.11

JUMLAH HARGA TENAGA 104,805.56

B. BAHAN
1. Batu belah 15/20 cm m3 1.00 220,000.00 220,000.00
2. Pasir Urug m3 1.00 150000 150,000.00

JUMLAH HARGA BAHAN 370,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 474,805.56

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : MEMASANG SLOOF BETON 15/20
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC m3 1.00 92,500.00 92,500.00
2. PASIR m3 2.00 250000 500,000.00
3. BATU m3 2.00 260,000.00 520,000.00

JUMLAH HARGA BAHAN 1,112,500.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,160,819.44


ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PASANG BATA TRANSRAM
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC kg 1.00 1,250.00 1,250.00
2. PASIR kg 2.00 178.57 357.14
3. BATA buah 57.6 750.00 43,200.00
JUMLAH HARGA BAHAN 44,807.14

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 93,126.58

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PASANG BATA BIASA
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC kg 1.00 1,250.00 1,250.00
2. PASIR kg 2.00 178.57 357.14
3. BATA buah 1 750.00 750.00
JUMLAH HARGA BAHAN 2,357.14

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 50,676.58

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PLESTERAN TRASRAM
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC kg 1.00 1,250.00 1,250.00
2. PASIR kg 6.00 178.57 1,071.42
JUMLAH HARGA BAHAN 2,321.42

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 50,640.86

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PLESTERAN BIASA
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC kg 1.00 1,250.00 1,250.00
2. PASIR kg 4.00 178.57 714.28
JUMLAH HARGA BAHAN 1,964.28

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 50,283.72

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : KOLOM PRAKTIS
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.00 48,319.44 1.365462 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC kg 1.00 1,250.00 1,250.00
2. PASIR kg 2.00 178.57 357.14
3. BATU kg 3.00 184.62 553.86
4. TULANGAN BESI kg 4.00 13250 53,000.00
5. PAPAN KRUNG kg 0.10 6,730,000.00 673,000.00
6. BALOK KAYU kg 0.10 9000000 900,000.00
7. PAKU kg 1.00 15,000.00 15,000.00
JUMLAH HARGA BAHAN 1,643,161.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,691,480.44

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : RING BALOK
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 0.6806 71,000.0000 48,319.4444 1.36546184738956 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. PC kg 1.00 1,250.00 1,250.00
2. PASIR kg 2.00 178.57 357.14
3. BATU kg 3.00 184.62 553.86
4. TULANGAN BESI kg 4.00 13,250.00 53,000.00
5. PAPAN KRUNG kg 0.10 6,730,000.00 673,000.00
6. BALOK KAYU kg 0.10 9,000,000.00 900,000.00
7. PAKU kg 1.00 15,000.00 15,000.00
JUMLAH HARGA BAHAN 1,643,161.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,691,480.44

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : ATAP DAN KANOPI
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Org/hari 1.4519 71,000.0000 48,319.4444 1.36546184738956 0.195066

JUMLAH HARGA TENAGA 48,319.44

B. BAHAN
1. ATAP M2 1.00 50,000.00 50,000.00
2. KANOPI BUAH 2.00 400,000.00 800,000.00
JUMLAH HARGA BAHAN 850,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 898,319.44

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PASANG PINTU DAN JENDELA UTAMA
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG KAYU Org/hari 1.4519 83,000.00 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. HANDEL JENDELA BH 1.0000 12500 12,500.00
2. HANDEL PINTU BH 1.0000 35,000.00 35,000.00
3. KAYU JATI PAPAN M2 0.02 25,000,000.00 375,000.00
4. KACA BENING 5 MM M2 0.75 115,000.00 86,250.00
5. CAT KAYU KG 1.00 65,000.00 65,000.00
JUMLAH HARGA BAHAN 573,750.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 797,335.19

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PASANG PINTU
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG KAYU Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. HANDEL PINTU BH 1.0000 320,000.00 320,000.00
2. KAYU JATI PAPAN M2 0.02 20,000.00 300.00
3. CAT KAYU KG 1.00 65,000.00 65,000.00
JUMLAH HARGA BAHAN 385,300.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 608,885.19

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PASANG PINTU KAMAR MANDI
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG KAYU Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. PINTU KAMAR MANDI/ WC BH 1.0000 200000 200,000.00

JUMLAH HARGA BAHAN 200,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 423,585.19

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : JENDELA 1 DAUN
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG KAYU Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. KAYU JATI PAPAN BH 0.0250 25,000,000.00 625,000.00
KACA BENING 5 MM BH 0.7500 115,000.00 86,250.00
3. CAT KAYU KG 1.00 65,000.00 65,000.00

JUMLAH HARGA BAHAN 776,250.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 999,835.19

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : BOUVENLIGHT KACA MATI
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG KAYU Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. BOUVENLIGHT BH 1.0000 300,000.00 300,000.00
2. PAKU KG 1.0000 15,000.00 15,000.00

JUMLAH HARGA BAHAN 315,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 538,585.19


ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : RANGKA ATAP BAJA RINGAN
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG BESI Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. rangka holo galvanis 4/4 cm, panj 4 m profile tebal M 1.0000 3,166.67 3,166.67
2. PAKU KG 1.0000 15,000.00 15,000.00

JUMLAH HARGA BAHAN 18,166.67

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 241,751.85


241,751.00

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PENUTUP ATAP
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG BESI Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. ATAP M 1.0000 50,000.00 50,000.00
2. BESI PENGGANTUNG KG 1.0000 4,500.00 4,500.00

JUMLAH HARGA BAHAN 54,500.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 278,085.19


278,085.00

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : TALANG
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG BESI Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. PIPA PVC D 4" BH 1.0000 281,000.00 281,000.00
2. BESI PENGGANTUNG KG 1.0000 4,500.00 4,500.00
3. GALVALUM 1.00 43,000.00 43,000.00

JUMLAH HARGA BAHAN 328,500.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 552,085.19


552,085.00

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : LISPLANK GRC RANGKA KAYU
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 1.4519 71,000.0000 103,081.4815
2. TUKANG BESI Org/hari 1.4519 83,000.0000 120,503.70

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 223,585.19

B. BAHAN
1. GRC BH 1.0000 155,000.00 155,000.00
2. PAKU KG 1.0000 15,000.00 15,000.00

JUMLAH HARGA BAHAN 170,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 393,585.19


393,585.00

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PEMASANGAN LANTAI KERAMIK
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 0.3673 71,000.0000 26,081.6327
2. TUKANG BATU Org/hari 0.3673 83,000.0000 30,489.80

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 56,571.43

B. BAHAN
1. KERAMIK BH 1.0000 59,000.00 59,000.00
2. PASIR PASANG KG 1.0000 160.00 160.00
3. SEMEN PORTLAND KG 1.00 1,250.00 1,250.00
4. SEMEN WARNA KG 1.00 17,000.00 17,000.00
JUMLAH HARGA BAHAN 77,410.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 133,981.43


133,981.00

ANALISA HARGA SATUAN

PROP / KAB / KODYA : SURAKARTA


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : PEMASANGAN LANTAI/DINDING KM
TAHUN : 2021

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1. Pekerja (L01) Org/hari 0.3673 71,000.0000 26,081.6327
2. TUKANG BATU Org/hari 0.3673 83,000.0000 30,489.80

1.36546184738956 0.195066

JUMLAH HARGA TENAGA 56,571.43

B. BAHAN
1. KERAMIK BH 1.0000 59,000.00 59,000.00
2. PASIR PASANG KG 1.0000 160.00 160.00
3. SEMEN PORTLAND KG 1.00 1,250.00 1,250.00
4. SEMEN WARNA KG 1.00 17,000.00 17,000.00
JUMLAH HARGA BAHAN 77,410.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 133,981.43


133,981.00

AN-UM 1 A.4.5.1.7. Pemasangan 1 m2 plafond gypsum board ukuran (120x240x9) mm, tebal 9 mm
A TENAGA
Pekerja 0.1000 OH 92,000.00 9,200.00

Mandor 0.0050 OH 178,200.00 891.00


JUMLAH UPAH TENAGA KERJA 10,091.00
B BAHAN
Gypsumboard 0.3640 Lembar 80,500.00 29,302.00
Paku skrup 0.1100 Kg 28,700.00 3,157.00
JUMLAH HARGA BAHAN 32,459.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 42,550.00
E Overhead & Profit (max) = - % x 42,550.00 -
F Harga Satuan Pekerjaan (D+E) 42,550.00
G Dibulatkan 42,550.00
AN-UM 1 A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu/Saklar
A TENAGA
Upah 1.0000 Lot 47,804.00 47,804.00
JUMLAH UPAH TENAGA KERJA 47,804.00
B BAHAN
Pipa listrik 5/8 " 3.0000 btg 2,800.00 8,400.00
Kabel NYM 3 x 1,5 mm (ETERNA) 24.0000 m 9,130.00 219,120.00
T Dus 3.0000 buah 1,100.00 3,300.00
L Bow 4.0000 buah 1,100.00 4,400.00
Las Dop 3.0000 buah 300.00 900.00
Klem 24.0000 buah 100.00 2,400.00
Mangkok 1.0000 buah 500.00 500.00
JUMLAH HARGA BAHAN 239,020.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 286,824.00
E Overhead & Profit (max) = - % x 286,824.00 -
F Harga Satuan Pekerjaan (D+E) 286,824.00
G Dibulatkan 286,824.00
AN-UM 2 A.8.4.6.1 (K3) Pemasangan 1 buah titik Stop Kontak
A TENAGA
Upah 1.0000 Lot 64,805.60 64,805.60
JUMLAH UPAH TENAGA KERJA 64,805.60
B BAHAN
Pipa listrik 5/8 " 3.0000 btg 2,800.00 8,400.00
Kabel NYM 3 x 2,5 mm (ETERNA) 24.0000 m 12,672.00 304,128.00
T Dus 3.0000 buah 1,100.00 3,300.00
L Bow 4.0000 buah 1,100.00 4,400.00
Las Dop 3.0000 buah 300.00 900.00
Klem 24.0000 buah 100.00 2,400.00
Mongkok 1.0000 buah 500.00 500.00
JUMLAH HARGA BAHAN 324,028.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 388,833.60
E Overhead & Profit (max) = - % x 388,833.60 -
F Harga Satuan Pekerjaan (D+E) 388,833.60
G Dibulatkan 388,833.00
3 listrik 1 BH STOP KONTAK setara BROCO
A BAHAN
1 bh Stop Kontak setara BROCO 1.0000 Bh 26,000.00 26,000.00
JUMLAH HARGA BAHAN 26,000.00
Jumlah 26,000.00
Keuntungan + Overhead Max = 10.0000 % x 26,000.00 2,600.00
Jumlah 28,600.00
Dibulatkan 28,600.00
4 listrik 1 BH SAKLAR SINGLE setara BROCO
A BAHAN
1 bh Saklar Single setara BROCO 1.0000 Bh 20,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
Jumlah 20,000.00
Keuntungan + Overhead Max = 10.0000 % x 20,000.00 2,000.00
Jumlah 22,000.00
Dibulatkan 22,000.00
5 listrik 1 BH SAKLAR DOUBLE setara BROCO
A BAHAN
1 bh Saklar Double setara BROCO 1.0000 Bh 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
Jumlah 25,000.00
Keuntungan + Overhead Max = 10.0000 % x 25,000.00 2,500.00
Jumlah 27,500.00
Dibulatkan 27,500.00
2014 6 listrik 1 BH LAMPU SL 14 WATT LENGKAP DG FITTING (setara PHILIPS)
A BAHAN
1 bh lampu SL 14 Watt setara PHILIPS 1.0000 Bh 40,000.00 40,000.00
1 bh Fitting Lampu 1.0000 Bh 13,800.00 13,800.00
JUMLAH HARGA BAHAN 53,800.00
Jumlah 53,800.00
Keuntungan + Overhead Max = 10.0000 % x 53,800.00 5,380.00
Jumlah 59,180.00
Dibulatkan 59,180.00
6 A.4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) setara SANLEX
A TENAGA
Pekerja 0.0200 OH 92,000.00 1,840.00
Tukang Cat 0.0630 OH 110,000.00 6,930.00
Kepala Tukang 0.0063 OH 150,000.00 945.00
Mandor 0.0030 OH 178,200.00 534.60
JUMLAH UPAH TENAGA KERJA 10,249.60
B BAHAN
Plamuur 0.1000 Kg 11,500.00 1,150.00
Cat Dasar setara Sanlex 0.1000 Kg 28,000.00 2,800.00
Cat Penutup setara Sanlex 0.2600 Kg 28,000.00 7,280.00
JUMLAH HARGA BAHAN 11,230.00
C PERALATAN
Rol Cat 0.0100 Bh 28,000.00 280.00
Ampelas 0.5000 Lbr 48,900.00 24,450.00
Steger Werk 0.0450 Lot 46,209.60 2,079.43
JUMLAH HARGA ALAT 26,809.43
D Jumlah (A+B+C) 48,289.03
E Overhead & Profit (max) = - % x 48,289.03 -
F Harga Satuan Pekerjaan (D+E) 48,289.03
G Dibulatkan 48,289.00
7 A.4.7.1.10 Pengecatan 1 m2 Plafond baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) setara SANLEX
A TENAGA
Pekerja 0.0200 OH 92,000.00 1,840.00
Tukang Cat 0.0630 OH 83,000.00 5,229.00
Kepala Tukang 0.0063 OH 88,000.00 554.40
Mandor 0.0030 OH 178,200.00 534.60
JUMLAH UPAH TENAGA KERJA 8,158.00
B BAHAN
Plamuur 0.1000 Kg 11,500.00 1,150.00
Cat Dasar setara Sanlex 0.1000 Kg 28,000.00 2,800.00
Cat Penutup setara Sanlex 0.3000 Kg 28,000.00 8,400.00
JUMLAH HARGA BAHAN 12,350.00
C PERALATAN
Rol Cat 0.0100 Bh 28,000.00 280.00
Ampelas 0.5000 Lbr 48,900.00 24,450.00
Steger Werk 0.0450 Lot 45,238.00 2,035.71
JUMLAH HARGA ALAT 26,765.71
D Jumlah (A+B+C) 47,273.71
E Overhead & Profit (max) = - % x 47,273.71 -
F Harga Satuan Pekerjaan (D+E) 47,273.71
G Dibulatkan 47,273.00
8 A.4.7.1.10 KERPUS/ BUBUNGAN
A TENAGA
Pekerja 0.0200 OH 92,000.00 1,840.00
Tukang Cat 0.0630 OH 83,000.00 5,229.00
Kepala Tukang 0.0063 OH 88,000.00 554.40
Mandor 0.0030 OH 92,000.00 276.00
JUMLAH UPAH TENAGA KERJA 7,899.40
B BAHAN
SEMEN 1.0000 Kg 1,250.00 1,250.00
PASIR 2.0000 Kg 178.57 357.14
AIR 3.0000 Kg 50.00 150.00
JUMLAH HARGA BAHAN 1,757.14
C PERALATAN
Rol Cat 0.0100 Bh 28,000.00 280.00
Ampelas 0.5000 Lbr 48,900.00 24,450.00
Steger Werk 0.0450 Lot 34,386.54 1,547.39
JUMLAH HARGA ALAT 26,277.39
D Jumlah (A+B+C) 35,933.93
E Overhead & Profit (max) = - % x 35,933.93 -
F Harga Satuan Pekerjaan (D+E) 35,933.93
G Dibulatkan 35,933.00