Minggu Ke
No. Uraian Pekerjaan Bobot
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
A. PEK. PERSIAPAN
1 Pek. Pembongkaran dan Pembersihan Lokasi 0.270% 0.216% 0.054%
2 Pek. Pengukuran dan Bouwplank 0.162% 0.000% 0.081% 0.081%
3 Papan Kegiatan 0.029% 0.029% 0.000% 0.000%
4 Keselamatan dan Kesehatan Kerja 0.270% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015%
0.000%
B. PEK. STRUKTUR 0.000%
I. PEKERJAAN TANAH DAN PONDASI 0.000%
1 Galian Tanah 0.000%
2 Galian Tanah Cadas 3.067% 0.315% 0.315% 2.436%
3 Urugan Tanah Kembali 0.087% 0.087%
4 Urugan Tanah 0.362% 0.175% 0.094% 0.094%
5 Pemadatan dan Pemerataan Tanah ( per 20cm ) 0.202% 0.202%
6 Urugan Pasir 0.120% 0.023% 0.095% 0.003%
7 Pas. Pondasi Batu Belah 1 : 6 10.560% 0.841% 3.539% 3.146% 3.035%
8 Pas. Aanstamping 0.762% 0.211% 0.254% 0.214% 0.083%
9 Buangan Tanah 0.553% 0.553%
0.000%
C. PEK. ARSITEKTUR 0.000%
I. PEKERJAAN PASANGAN 0.000%
1 Pas. Bata Merah 1/2 Bata Camp. 1:6 5.359% 2.778% 0.645% 0.645% 0.645% 0.645%
2 Pas. Rollag Bata Merah Camp. 1:4 0.083% 0.083%
3 Pek. Plesteran Camp. 1:3 0.000%
4 Pek. Plesteran Camp. 1:4 4.325% 0.356% 0.992% 0.992% 0.992% 0.992%
5 Pek. Acian 2.177% 0.007257 0.726% 0.726%
6 Pek. Grass Block T:8cm 0.000%
7 Pek. Paving T 6cm 1.429% 0.714% 0.714%
8 Pas. Lantai Keramik 30x30 cm 6.103% 2.034% 2.034% 2.034%
9 Pas. Lantai Homogenous Tile 60x60 cm 0.000%
10 Pas. Lantai Keramik 20x20 cm 0.230% 0.230%
11 Pas. Keramik Dinding 20x40 cm 0.955% 0.955%
12 Pas. Batu Alam Andesit 0.906% 0.453% 0.453%
13 Pas. Ornamen Batik GRC Cetak 0.846% 0.423% 0.423%
14 Pas. Roster Beton 20x20 cm 0.190% 0.190%
15 Pas. Plafond Gypsumboard tebal 9mm 0.681% 0.341% 0.341%
16 Pas. Partisi Gypsumboard tebal 9mm 1.965% 0.982% 0.982%
17 Pas. Compon Beton 0.974% 0.487% 0.487%
18 Pas. List GRC 0.272% 0.136% 0.136%
0.000%
D. PEK. MEKANIKAL DAN ELEKTRIKAL 0.000%
I. PEKERJAAN AIR BERSIH 0.000%
1 Pas. Kran dia. 1/2" 0.055% 0.055%
2 Pas. Stop Kran 0.038% 0.038%
3 Pengadaan dan Pemasangan Tangki Air 0.000%
Plastik ( Water Toren) Kapasitas 500 liter 0.000%
4 Pas. Gate Valve 1' 0.038% 0.038%
5 Pas. Pipa PVC AW 1/2" 0.178% 0.178%
6 Pas. Pipa PVC AW 1" 0.081% 0.081%
7 Fiting dan Assesories 0.000%
0.000%
E. PEKERJAAN LAIN LAIN 0.000%
1 Pekerjaan dan Pengadaan Interior Backdrop dan Meja Pelayanan 0.000%
Plywood Finishing HPL dan Aksesoriesnya 0.000%
2 Pekerjaan dan Pengadaan Interior Backdrop Ruang Lurah 0.000%
Plywood finishing HPL dan Aksesoriesnya 0.000%
3 Pekerjaan dan Pengadaan Taman dan Tanaman Hias 0.000%
4 Pekerjaan dan Pengadaan Letter & Logo Akrilik Kantor Kelurahan Manding 0.000%
5 Pekerjaan dan Pengadaan Letter & Logo GRC Cetak Kantor Kelurahan Manding0.151% 0.151%
6 Pekerjaan Perbaikan Bekas Bongkaran Bangunan Lama 0.162% 0.162%