Anda di halaman 1dari 1

Awal impounding 02-Agu-21

DATA OPERASI BENDUNGAN BENDO


PENGISIAN AWAL
1 Hari ke - 103 Jumat 12 November 2021 17.00.00 WIB BOBOT
3
2 Volume Total EL.+ 220.62 46,439,969.29 m
Volume Efektif 38,069,659.65 m3
3 MAW EL. + 196.70 m
3
4 Volume saat ini 15,430,255.30 m 40.53 %
Luas Genangan 86.18 Ha 48.38 %
Sebelumnya hari ke- 103 Jumat 12 November 2021 12.00.00 wib
5 MAW EL. + 196.50 m
Volume 15,255,887.50 m3
Kenaikan Elevasi 0.20 m

6 Q-Outflow 0
3
#1 Pintu 1 Elv. 186.82 100.00% 0.000 m /det
#2 Emergency 400mm 100.00% 0.397 m3/det
7 Penguapan 0.00 mm/hari 0.000 m3/det
8 Q-Inflow 9.956 m3/det 5

Dam Instruments
9 Rembesan di waduk (mm)
V-notch 2 (kanan) 95 3.930 liter/det
V-notch 3 (kiri) 16 0.046 liter/det
TOTAL 3.976 liter/det
10 Drainase tebing
V-notch 1 20 0.080 liter/det
V-notch 4 44 0.574 liter/det
TOTAL 0.654 liter/det
14 Curah Hujan Sta. Bendungan Bendo mm
STa. Sooko mm
STa. Poedak mm
15 Temperature max °C
16 Temperature min °C
17 Wind Run Km/hari
18 Barrometer mb

Keterangan: v-notch dilaporkan pada jam 17:00 wib