Produktifitas Konstruksi 1
Produktifitas Konstruksi 1
Labour 40%
•Largest cost
Materials 40% component
General Conditions • Most volatile
& Indirect Costs 10%
Overhead 5%
• Most critical
to control
Profit 5%
Total 100%
Hypothetical Tender
Profit 5%
Total 100%
Hypothetical Tender
Labour 45%
Materials 40%
General Conditions Wipes out all
profit!
& Indirect Costs 10%
Overhead 5%
Profit 0%
Total 100%
Mengukur Produktifitas
Data sebuah perusahaan konstruksi menunjukkan
bahwa indek produktifitas untuk pengecoran beton
3.50 m3/pekerja/jam (m3/pj). Jika akan melakukan
pengecoran dengan volume 202 m3 dan di kerja kan
oleh 9 pekerja dengan jam kerja 7.5 jam per hari.
Berapa indeknya dan Produktifitasnya ??
18
Planning and scheduling
• Lack of project planning and scheduling is one
of the important reasons of low construction
productivity.
19
Control
• Problems arise every day that could not have been
foreseen.
Adverse weather
Material delivery delays Can disrupt the original
Labor disputes plans
Job accidents
21
Supervision
• Although unnecessary supervision will
increase the cost of work, insufficient
supervision will result in confusion delays and
decrease productivity.
• The labor productivity is increased by
increasing the number of man hours per day
that the field supervisor spent in contact with
the crew.
22
Material and tool availability
• Unavailability of material and tool had a significant
adverse impact on the productivity of labor.
– Material unavailability loss between 6.4 and 8.4 man-
hr/week
– Tool unavailability loss between 3.4 and 5.1 man-hr/week
23
Work redoing and delays
• Work redone maintained a position as one of
three worst problems leading to poor
productivity.
• The amount of times spent on rework was
between 4.9 – 7.7 man-hr/week.
• Causes of work redone were mainly due to
engineering and management inefficiencies.
• Craftsmen spent an average of 14.3% of their
time redoing work.
24
Lack of motivation
• The greater the worker motivation, the
greater his expenditure of effort.
• Lack of material, frequent change orders,
conflict of crews because of improper
scheduling, lack of equipment, etc. frustrate
the worker and produce low productivity.
25
Site layout
• Site layout of the project is a very important
organization tasks.
• The assigned location of different job
components affects productivity, safety,
workers satisfaction, and communication.
• Approximately, 7% of a day is nonproductive
because of a non optimal site layout.
26
Information and communication
• Lack of information, uncertainty regarding
design factors, site conditions, client wishes,
and regulatory requirement result in design
delay, redesign and substantial loss of
productivity.
• Approximately, 9% of a day is nonproductive
because of poor or inadequate
communications at the job site.
27
Authority and decision making
• Group participation in decision making has
been proven to be an effective method of
increasing productivity.
• Participation of work group in changing work
methods increases productivity by 14%
compared to non participating groups.
28
Productivity VS Quality
• Quality means; inspection, quality control,
quality assurance, and total quality
management.
• Low quality of construction will cause redoing
work.
• Redoing work affects the production rate and
decrease the output.
• When output decreases, productivity
decreases.
29
Production rate increase
• Use shifts
– Use two or more shifts instead of one shifts
• Apply overtime
– Increase shift period to 10 hours instead of 8
hours
• Increase resources
– Use more resources to increase production rate
30
Overtime Effect on Output
Production rate
a c d 50 hr/week
60 hr/week
b
Time
10 -12 week
31
Methods to improve construction
productivity
32
Example 3
• The following data are given for a construction operation:
• Quantity of work = 4680 units
• Number of laborer = 4 laborers
• Normal conditions:
– 42 hours/workweek – 7 hours/day – 6 days/week
– Production rates = 3 units/man-hour
– Labor cost = 3 L.E./hour/labor
• Scheduled conditions:
– 60 hours/workweek – 10 hours/day – 6 days/week
– Production rates = as shown in table
– Labor cost = 3 L.E./hour/labor (for 7 hour/day) & 4.5
L.E./hour/labor (for hours over 7 hour/day)
33
Example 3
Week number 1 2 3 4 5 6 7 8 9 10 11 12
Av. Commutative % normal 83 88 88 83 79 74 70 67 66 65 64 63
production rate
35
Example 3
Scheduled overtime:
For 9 weeks:
(3 units/man-hours x0.66) x 4 labors
Quantity of Production
x 10=hours/day x 6 days/week x 9 weeks
= 4276.8 units
36
Example 3
Using scheduled overtime will take 10 weeks
38
The problems that can be appeared in material management applications are the
following:
• running out of materials,
• extensive multiple-handling of materials,
• Improperly sorted or marked materials, which makes to define them difficult,
• wrong or damaged materials that exceed acceptable specification tolerances, or
production errors pointing to a poor quality,
• unsystematic flow of materials,
• production rates of materials in plant incongruous with those on site.
Judicious planning of labour resources are the foremost agent in fulfilling these
constraints. Poor planning, however, can adversely affect labour productivity through
the need for rework and can result in lost time for workers, since operatives
are often paid on work done satisfactorily alone. Most workers take considerable pride
in the work they have accomplished that can be seen from the very start of
construction through completion. For workers to go back again and take apart what
has been completed can be extremely frustrating and can cause them to put forth less
effort for the remainder of the work.
Remuneration is seen as the most important reason of why an individual has to work
in a job. Because it both meets the physiological needs that are the most basic
requirement of people, and gives esteem in a society. The amount of pay and on-time
payment is the most vital factors required to meet the first hierarchy need of
Maslow. A worker, for example, will probably quit the job if a higher wage is offered by
another firm. Despite Herzberg’s argument that money is not a satisfier and
thus not a motivator, the present survey coupled with previous works such as
McKenzie and Harris (1984), Price (1992), Ogunlana and Chang (1998), and Yisa et al.
(2000) seems to indicate the contrary.
To follow-up and supervise labour while working is a vital aspect of any organization
because both it can result in extensions of project time and cost, and the quality
on site is controlled through inspection of the work completed by the gang. In this
context, labour-only subcontracting makes some aspects of site management more
difficult. The supervision level of labor-only gangs tends to be lower than that of
employed workers, and the general contractor has little control, at best, over
subcontractors’ workforce. In other words, the lump poses the problem of which lump
workers cannot be controlled, while firms possessing employed workforce have their
own effect on labour relations. Moreover, subcontractors have no control over other
subcontractors’ labourers.
Experience is the warranty of success and productivity in any job. Working with
experienced crews in the sector has many advantages. If experienced labour is known
to be available, supervisors do not have to explain details of how to perform the tasks
to experienced workers.
However construction productivity can be defined in many ways. First, it is how well,
how quickly, and at what cost construction projects can be constructed.
Second, it was defined by The American Association of Cost Engineers as a relative
measure of labor efficiency, which is defined as the output per hour worked, either
good or bad depending based on the reality that productivity changes over time.
Third, a common measurement of construction productivity is factor productivity (H.
Thomas et al., 1990), which is defined as:
In the Table 3-1, each item includes information related to the crew code, which
describes the crew composition in terms of labor, material, and equipment categories.
Table 3-1, shows how the manual data is arranged in the R.S. Means manual. The
numbers 1 and 2 are the division and line numbers. The number 3 represents the
description list of each individual activity. The crew column number 5 designates the
typical crew used to install the item. Number 6 indicates the productivity (daily output
per man-hours). Number 7 identifies the column that lists units for each individual
construction task. Numbers 8 and 9 show the bare and total costs for the whole
activity.
Work Study
Productivity Variables
• Labor %
– Education, diet, & 2.5
sanitation
• Capital 2.0
Mgmt
– Equipment
1.6
1.5
– Building
• Product quality
– Defects, scrap, rework
Fulfillment
Recognition
Affiliation
Security
Physiological
Maslow ‘s hierarchy of needs
• At the bottom of the hierarchy are physiological needs. These are the basic
needs that must be met to sustain life itself. Satisfying ones physiological
needs will be the primary concern of any person and until one has done so
one will not be concerned with any other issues.
• However, once workers feel reasonably sure of fulfilling their physiological
needs, they will seek to satisfy the next need in the hierarchy, that of
security.
• Security is taken to mean a feeling of protection against physical and
psychological harm, as well as security of employment.
• For workers who have already satisfied their physiological and their security
needs, the next motivating factor is that of affiliation, that is wanting to
belong to a group or an organization and to associate with others.
• Next on the hierarchical scale is the need to be recognized, and this is
followed by the need for fulfillment (also called “self-actualization”).
• This last need expresses the desire of people or workers to be given an
opportunity to show their particular talents.
Modifying Jobs to Provide
Broader Range of Needs Satisfaction
• Cross – training – workers perform multiple jobs
• Job enlargement is a “horizontal” expansion of job tasks; that is,
the worker is assigned more tasks at the same general skill level.
– In a manufacturing setting, job enlargement might mean having a worker
do several tasks at a work station rather than only one or two.
– In a bank, it might mean training a person to write car loans, and
installment loans rather than only one of these.
Job Enrichment involves “vertical” expansion of a job’s
responsibilities and skills.
It may mean that a production worker is involved in the design of the
product or production process is responsible for his own quality testing,
handles customer complaints, or deals directly with suppliers.
• Team production -- organizing workers into teams; assigning
management responsibility to teams
METHODS ANALYSIS AND IMPROVEMENT
• Specifying the tasks and responsibilities of a job is only the first
step in the job design process.
• The next step is to determine how to perform the tasks, that is,
determine the best work methods.
– Best work methods are
• the most efficient physical movements of the worker,
• the best sequence in which to perform movements or
tasks, and
• the best way to coordinate the workers actions with
those of machines and other workers.
• This information must be conveyed to the workers through training
and appropriate supervision and feedback.
METHODS ANALYSIS
Performance Allowance
Rating Fraction