KEGIATAN : PEMBUATAN BANGUNAN BAMBU

PEKERJAAN : PROYEK PEMBANGUNAN MAHKOTA QURAN PATROL


LOKASI : GARUT
TA : 2021

HARGA SATUAN JUMLAH HARGA BOBOT DES '21 JAN '22 FEB '22
No URAIAN PEKERJAAN VOL SAT
(Rp.) (Rp.) (%) 20 - 26 27 - 2 3-9 10 - 16 17 - 23 24 - 30 31 - 6 7 -13
I. ASRAMA DAN RUMAH USTAD
1. Pek. Asrama A 18,00 m2 Rp 903.704 Rp 16.266.667 17,12% 8,56% 8,56%
2. Pek. Asrama B 18,00 m2 Rp 903.704 Rp 16.266.667 17,12% 8,56% 8,56%
3. Pek. Rumah Ustad 18,00 m2 Rp 903.704 Rp 16.266.667 17,12% 8,56% 8,56%
II. MUSHOLA
1. Pek. Mushola 30,00 m2 Rp 900.000 Rp 27.000.000 28,42% 9,47% 9,47% 9,47%
III. TOILET
2
1. Pek. Toilet 16,00 m Rp 1.200.000 Rp 19.200.000 20,21% 6,74% 6,74% 6,74%
Jumlah Total Rp 95.000.000 100% 8,56% 17,12% 17,12% 18,04% 9,47% 16,21% 6,74% 6,74%
Dibulatkan Rp 95.000.000 8,56% 25,68% 42,81% 60,84% 70,32% 86,53% 93,26% 100,0%
Realisasi 6,66% 19,49%
Kumulatif Realisasi 6,66% 26,15%
Deviasi -1,90% 0,47%

Garut, …………………..
Disetujui, Kontraktor Pelaksana
CV. LOKANATA BERLIMA DESRI

Hilman Saeful Anwar Gilang Rachmat Sutanto


Project Manager Site Manager