Anda di halaman 1dari 1

RENCANA ANGGARAN BIAYA

BIDANG : Pelaksanaan pembangunan desa


KEGIATAN : Kegiatan Plat Deker 1.5 X 1 X 5
WAKTU PELAKSANAAN :
Rincian pengadaan

VOLUME
No. URAIAN SAT. Harga Satuan
TOTAL Swad. TOTAL Swadaya

I BAHAN

1 Semen Tiga Roda @ 50 Kg 31.04 Zak 80,000 2,483,240


2 Pasir Pasang 4.34 m3 200,000 868,000
3 Besi Beton Ø10 mm SNI P=12m' (Polos ) 17.85 Ujng 87,000 1,552,950
4 Bendrat 0.34 Kg 22,500.00 7,650
Sub Total (1) 4,911,840 0.00

II ALAT

1 Ember Cor 4.00 Bh 20,000 80,000


2 Slang Ukur 25.00 M 20,000 500,000
3 Sekop 2.00 Bh 100,000 200,000
4 Linggis 1.00 Bh 130,000 130,000
5 Papan proyek 1.00 Bh 150,000 150,000
Sub Total (2) 1,060,000 0.00

III UPAH
1 Pekerja 14.71 HOK 100,000 1,470,950
2 Tukang 5.42 HOK 125,000 677,844
3 Kep. Tukang/ Kep. Kelompok 7.00 HOK 150,000 1,050,113
4 Pengadaan Batu 8.61 HOK 240,000 2,306,400
5 Pengadaan Kerikil 0.92 HOK 275,000 528,000
Sub Total 3) 6,033,306 0.00

TOTAL (1+2+3) 12,005,146 0.00


Dibulatkan 12,005,000

Tolondadu I ………………….. 2021 Di setujui mengesahkan


TPK Tolondadu I Sangadi Tolondadu I

……………………………. …………………………………….