Anda di halaman 1dari 7

Tabel 1.

1 Rincian Biaya Unit Bak Pengumpul dan Bar Screen

Harga Satuan Total Harga


No Nama Pekerjaan Besaran Satuan (Rp) (Rp)
Pekerjaan Tanah

1 Galian tanah 270 m3 151,250 40,837,500

2 Pemadatan tanah 5 m3 2,750 13,750


Pekerjaan Konstruksi Beton

1 Struktur beton k-225 265 m3 520,000 156,350,000

2 Pekerjaan lantai k-175 54.93 m3 610,000 38,451,000

3 Pembesian 55 Batang 76,000 4,180,000

4 Bekisting 159 m2 82,000 13,038,000

5 Plester dan acian 159 m2 34,450 5,477,550

6 Water proofing 159 m2 65,000 10,335,000


Pekerjaan Mekanikal

1 Pompa submersible 2 buah 132,490,000 264,980,000

2 Pipa D 300 mm 5 m 765,000 3,825,000

3 Bend 90° 2 buah 2,564,000 5,128,000

4 Pintu air 2 buah 700,000 1,400,000

5 Besi galvanize 1 m 24,000 24,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja Terampil 10 8jam/hari 35,000 350,000

Total Biaya 544,434,800


Tabel 1.2 Rincian Biaya Unit Screw Pump

Harga Satuan Total Harga


No Nama Pekerjaan Besaran Satuan (Rp) (Rp)
Pekerjaan Tanah

1 Galian tanah 8.46 m3 15,250 1,279,575


Mengurug dengan pasir
2 urug 0.56 m3 212,000 118,720
pemadatan tanah
3 (stamper) 0.53 m2 2,750 1,457
Pekerjaan
Konstruksi beton

1 Struktur beton k-225 5.29 m3 520,000 3,121,100

2 Pekerjaan lantai K-175 0.26 m3 610,000 182,000

3 Pembesian 45 Batang 76,000 3,420,000

4 Bekisting 9.2 m2 82,000 754,400

5 Plester dan acian 9.2 m2 34,450 316,940

6 Water proofing 9.2 m2 65,000 598,000


Pekerjaan
Mekanikal

1 Pompa Ulir 3 buah 165,000,000 495,000,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja terampil 7 8jam/hari 35,000 245,000

Total Biaya 505,082,192

Tabel 1.3 Rincian Biaya Unit Grit Chamber

Harga Satuan
No Nama Pekerjaan Besaran Satuan (Rp) Total Harga (Rp)
Pekerjaan Tanah

1 Galian tanah 5.76 m3 151,250 871,200


Mengurug dengan
2 pasir urug 0.5 m3 212,000 106,000
pemadatan tanah
3 (stamper) 0.48 m2 2,750 1,320
Pekerjaan Konstruksi beton

1 Struktur beton k-225 5.28 m3 520,000 2,745,600

2 Pekerjaan lantai K-175 0.24 m3 610,000 146,400

3 Pembesian 50 Batang 76,000 3,800,000

4 Bekisting 36.52 m2 82,000 2,994,640

5 Plester dan acian 36.52 m2 34,450 1,258,114

6 Water proofing 36.52 m2 65,000 2,373,800


Pekerjaan Mekanikal

1 Pipa dimensi 300 mm 5 m 765,000 3,825,000

2 Bend 90° 2 buah 2,564,000 5,128,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja terampil 8 8jam/hari 35,000 280,000

Total Biaya 23,575,074

Tabel 1.4 Rinciang Biaya Unit Bak Ekualisasi

Harga Satuan Total Harga


No Nama Pekerjaan Besaran Satuan (Rp) (Rp)
Pekerjaan Tanah

1 Galian tanah 82.15 m3 151,250 12,425,188


Mengurug dengan
2 pasir urug 22.6 m3 212,000 4,791,200
pemadatan tanah
3 (stamper) 31.78 m2 2,750 87,395
Pekerjaan Konstruksi beton

1 Struktur beton k-225 189 m3 510,000 96,390,000

2 Pekerjaan lantai K-175 38 m3 610,000 23,180,000


3 Pembesian 120 Batang 76,000 9,120,000

4 Bekisting 435 m2 82,000 35,670,000

5 Plester dan acian 435 m2 34,450 14,985,750

6 Water proofing 435 m2 65,000 28,275,000


Pekerjaan Mekanikal

1 Bend 90° 2 Buah 2,564,000 5,128,000

2 Pipa diameter 250 mm 10 m 724,000 7,240,000

3 Pompa submersible 1 Buah 123,490,000 123,490,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja terampil 5 8jam/hari 35,000 175,000

Total Biaya 361,002,533

Tabel 1.5 Rincian Biaya Unit Aerated Lagoon

Harga Satuan Total Harga


No Nama Pekerjaan Besaran Satuan (Rp) (Rp)
Pekerjaan Tanah

1 Galian tanah 24 m3 151,250 3,630,000


Mengurug dengan
2 pasir urug 5 m3 212,000 1,060,000
pemadatan tanah
3 (stamper) 25 m2 2,750 68,750
Pekerjaan Konstruksi beton

1 Struktur beton k-225 1287 m3 520,000 669,240,000

2 Pekerjaan lantai K-175 258 m3 610,000 157,380,000

3 Pembesian 200 Batang 76,000 15,200,000

4 Bekisting 250 m2 82,000 20,500,000

5 Plester dan acian 250 m2 34,450 8,612,500


6 Water proofing 250 m2 65,000 16,250,000
Pekerjaan Mekanikal

1 Bend 90° 3 Buah 2,564,000 7,692,000

2 Pipa diameter 250 mm 20 m 724,000 14,480,000

3 Pipa WAS diameter 50 m 47,500 2,375,000

4 Flow meter 1 Buah 10,500,000 10,500,000

5 Aerator 1 Buah 127,650,000 127,650,000

6 Tee all flange 1 Buah 1,230,000 1,230,000

7 Gate vale 1 Buah 1,030,000 1,030,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja terampil 20 8jam/hari 35,000 700,000

Total Biaya 1,057,643,250

Tabel 1.6 Rincian Biaya Unit Kolam Maturasi

Harga Satuan Total Harga


No Nama Pekerjaan Besaran Satuan (Rp) (Rp)
Pekerjaan Tanah

1 Galian tanah 22 m3 151,250 3,327,500


Mengurug dengan
2 pasir urug 5 m3 212,000 1,060,000
pemadatan tanah
3 (stamper) 10 m2 2,750 27,500
Pekerjaan Konstruksi beton

1 Struktur beton k-225 45 m3 520,000 23,400,000

2 Pekerjaan lantai K-175 10 m3 610,000 6,100,000

3 Pembesian 150 Batang 76,000 11,400,000

4 Bekisting 20 m2 82,000 1,640,000


5 Plester dan acian 20 m2 34,450 689,000

6 Water proofing 20 m2 65,000 1,300,000


Pekerjaan Mekanikal

1 Bend 90° 2 Buah 2,564,000 5,128,000

2 Pipa diameter 250 mm 10 m 724,000 7,240,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja terampil 15 8jam/hari 35,000 525,000

Total Biaya 61,882,000

Tabel 1.7 Rincian Biaya Unit Pengering Lumpur

Harga Satuan Total Harga


No Nama Pekerjaan Besaran Satuan (Rp) (Rp)
Pekerjaan Tanah

1 Galian tanah 1410 m3 151,250 213,262,500


Mengurug dengan
2 pasir urug 282 m3 212,000 59,784,000
pemadatan tanah
3 (stamper) 200 m2 2,750 550,000
Pekerjaan Konstruksi beton

1 Struktur beton k-225 616 m3 520,000 320,320,000

2 Pekerjaan lantai K-175 320 m3 610,000 195,200,000

3 Pembesian 200 Batang 76,000 15,200,000

4 Bekisting 160.5 m2 82,000 13,161,000

5 Plester dan acian 160.5 m2 34,450 5,529,225

6 Water proofing 160.5 m2 65,000 10,432,500

7 Pasir 282 m3 120,000 33,840,000

8 Kerikil 564 m3 135,000 76,140,000


Pekerjaan Mekanikal

1 Bend 90° 2 Buah 2,564,000 5,128,000

2 Underdrain 1 Buah 1,540,000 1,540,000

3 Pompa lumpur 1 Buah 136,000,000 136,000,000


Tenaga Kerja

1 Mandor 1 8jam/hari 45,000 45,000

2 Pekerja terampil 10 8jam/hari 35,000 350,000

Total Biaya 1,086,482,225

Tabel 1.8 Rekapitulasi Perhitungan Biaya

Harga Jadi Jumlah


No Nama Pekerjaan (Rp)/unit Unit Harga Total (Rp)
Biaya Unit Bak
Pengumpul dan Bar
1 Screen 544,434,800 2 1,088,869,600
Biaya Unit Screw
2 Pump 505,082,192 2 1,010,164,384
Biaya Unit Grit
3 Chamber 23,575,074 2 47,150,148

4 Biaya Unit Ekualisasi 361,002,533 2 722,005,065


Biaya Unit Aerated
5 Lagoon 1,057,643,250 2 2,115,286,500
Biaya Unit Kolam
6 Maturasi 61,882,000 2 123,764,000
Biaya Unit Pengering
7 Lumpur 1,086,482,225 2 2,172,964,450

Total Biaya 7,280,204,147

PPN 10% 728,020,414.70

Total Biaya Akhir 8,008,224,562