Anda di halaman 1dari 46

REKAPITULASI

RENCANA ANGGARAN BIAYA

PEKERJAAN : REHABILITASI PUSKESMAS MOTI


LOKASI : DESA BAJIMINASA KECAMATAN GANTARANG KEKE KAB. BANTAENG

No URAIAN PEKERJAAN JUMLAH HARGA (Rp.)


A PEKERJAAN PERSIAPAN 17,155,000.00
B PEKERJAAN TANAH 52,367,148.84
C PEKERJAAN PONDASI LAJUR 145,131,424.99
D PEKERJAAN BETON BERTULANG 825,930,093.58
E PEKERJAAN DINDING 690,569,704.05
F PEKERJAAN LANTAI 503,741,186.06
G PEKERJAAN ATAP 375,411,937.40
H PEKERJAAN KUSEN PINTU DAN JENDELA 362,202,935.09
I PEKERJAAN PLAFON 243,848,545.97
J PEKERJAAN PENGECATAN 134,960,094.41
K PEKERJAAN PLUMBING & SANITAIR 163,523,070.67
L PEKERJAAN ELEKTRIKAL 97,958,612.00
M PEKERJAAN LANDSCAPE 26,503,743.72
N PEKERJAAN INTERIOR 26,876,098.30
O JASA KONSULTAN PERENCANA 130,156,080.00
P JASA KONSULTAN PENGAWAS 86,770,720.00
REAL COST 3,883,106,395.10
PPn 10% 388,310,639.51
TOTAL COST 4,271,417,034.61
DIBULATKAN 4,271,417,000.00
Terbilang :
Empat Milyar Dua Ratus Tujuh Puluh Satu Juta Empat Ratus Tujuh Belas Ribu Rupiah

Bantaeng, Juni 2021

Dibuat Oleh :
Konsultant Perencana
CV. ALMAHYRA ENGINEER CONSULTANT

ISMAIL KADIR, ST
Direktur
RENCANA ANGGARAN BIAYA

PEKERJAAN : REHABILITASI PUSKESMAS MOTI


LOKASI : DESA BAJIMINASA KECAMATAN GANTARANG KEKE KAB. BANTAENG

HARGA SATUAN JUMLAH HARGA


No URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Biaya pembongkaran gedung eksisting dan pembersihan bekas bongkaran ls 1.00 6,340,000.00 6,340,000.00
2 Biaya Kesehatan dan Keselamatan Kerja (K3) ls 1.00 10,815,000.00 10,815,000.00
JUMLAH HARGA PEKERJAAN PERSIAPAN 17,155,000.00
B PEKERJAAN TANAH
3
1 Galian Tanah m 233.57 82,912.50 19,365,532.68
3
2 Urugan Kembali m 77.86 55,750.00 4,340,432.98
3
3 Urugan tanah (peninggian peil) m 156.33 165,165.00 25,820,393.10
3
4 Pemadatan urugan m 156.33 18,171.65 2,840,790.09
JUMLAH HARGA PEKERJAAN TANAH 52,367,148.84
C PEKERJAAN PONDASI LAJUR
3
1 Pasangan Batu Kosong m 63.87 503,398.50 32,154,075.79
3
2 Pasangan Batu Gunung m 124.05 910,736.75 112,977,349.21
JUMLAH HARGA PEKERJAAN PONDASI LAJUR 145,131,424.99
D PEKERJAAN BETON BERTULANG
Lantai Bawah BOC-1,22 s/d TOC+3,95
1 Poerplat PP1 110/110
3
Lantai kerja m 3.27 1,003,560.24 3,278,631.32
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 10.62 1,271,939.67 13,505,137.40
Pembesian kg 1,323.14 17,551.60 23,223,136.27
2
Bekisting m 38.61 197,103.50 7,610,166.14
2 Poerplat PP2 90/90
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 4.56 1,271,939.67 5,795,275.11
Pembesian kg 441.05 17,551.60 7,741,045.42
2
Bekisting m 14.85 197,103.50 2,926,986.98
3 Padestal K1 40/40
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 6.35 1,271,939.67 8,077,325.66
Pembesian kg 902.44 17,551.60 15,839,260.99
2
Bekisting m 31.75 331,001.00 10,509,943.75
4 Padestal K2 30/30
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 1.98 1,271,939.67 2,524,164.27
Pembesian kg 343.34 17,551.60 6,026,219.00
2
Bekisting m 13.23 331,001.00 4,379,143.23
5 Sloof SL-1 20/30
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 11.88 1,271,939.67 15,110,643.25
Pembesian kg 1,992.74 17,551.60 34,975,740.28
2
Bekisting m 79.20 207,691.00 16,449,127.20
6 Sloof SL-2 15/20
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 7.23 1,271,939.67 9,196,123.79
Pembesian kg 1,230.55 17,551.60 21,598,051.17
2
Bekisting m 32.13 207,691.00 6,673,804.13
7 Kolom K1 40/40
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 15.98 1,271,939.67 20,330,683.64
Pembesian kg 2,008.18 17,551.60 35,246,707.15
2
Bekisting m 79.92 331,001.00 26,453,599.92
8 Kolom K2 30/30
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m3 5.00 1,271,939.67 6,353,338.64
Pembesian kg 764.03 17,551.60 13,409,992.83
2
Bekisting m 33.30 331,001.00 11,022,333.30
9 Kolom Praktis
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m3 5.15 1,271,939.67 6,544,797.36
Pembesian kg 1,758.45 17,551.60 30,863,578.11
2
Bekisting m 23.39 331,001.00 7,741,699.64
10 Balok latei 10/20
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 3.27 1,271,939.67 4,154,409.34
Pembesian kg 493.69 17,551.60 8,664,981.48
2
Bekisting m 20.41 340,076.00 6,942,226.45
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6
Lantai Atas TOC+3,95 s/d +TOC+8,00
11 Balok B1 20/35
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 10.44 1,271,939.67 13,281,594.00
Pembesian kg 3,016.53 17,551.60 52,944,881.14
2
Bekisting m 149.82 340,076.00 50,950,186.32
12 Balok B2 15/25
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m3 3.69 1,271,939.67 4,690,213.93
Pembesian kg 986.53 17,551.60 17,315,262.44
2
Bekisting m 77.53 340,076.00 26,366,432.36
13 Plat lantai
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m3 42.31 1,271,939.67 53,818,947.17
2
Pemasangan 1 m2 Wiremesh M8 (1 lapis) m 338.50 82,369.77 27,882,165.60
2
Floordeck/Bondek galvanis T=0,75, L= 1 m m 271.45 232,237.50 63,040,869.38
14 Kolom K2 30/30
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 4.38 1,271,939.67 5,574,911.56
Pembesian kg 647.70 17,551.60 11,368,142.07
2
Bekisting m 29.22 331,001.00 9,671,849.22
14 Kolom Praktis
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 1.72 1,271,939.67 2,192,372.45
Pembesian kg 590.48 17,551.60 10,363,937.66
2
Bekisting m 15.67 331,001.00 5,186,620.17
15 Balok latei 10/20
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 1.06 1,271,939.67 1,345,203.39
Pembesian kg 159.86 17,551.60 2,805,732.78
2
Bekisting m 8.81 340,076.00 2,997,203.15
16 Pet beton t=8 cm
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 1.06 1,271,939.67 1,347,238.50
Pembesian kg 81.69 17,551.60 1,433,804.25
2
Bekisting m 6.62 388,751.00 2,573,531.62
17 Ringbalk 10/20
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 6.88 1,271,939.67 8,748,401.03
Pembesian kg 1,039.61 17,551.60 18,246,813.61
2
Bekisting m 45.85 340,076.00 15,593,618.19
18 Dak beton t=12 cm
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 1.44 1,271,939.67 1,831,593.12
Pembesian kg 143.64 17,551.60 2,521,069.70
2
Bekisting m 12.00 388,751.00 4,665,012.00
19 Tangga
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 3.71 1,271,939.67 4,712,536.47
Pembesian kg 274.84 17,551.60 4,823,811.54
2
Bekisting m 9.43 388,751.00 3,663,978.18
20 Meja Lab., Dapur dan Pantry
3
Beton f'c 21.7 Mpa, slump ( 12 ± 2 ) cm, w/c = 0,56 m 0.65 1,271,939.67 831,848.54
Pembesian kg 40.35 17,551.60 708,238.65
2
Bekisting m 6.54 388,751.00 2,542,431.54
JUMLAH HARGA PEKERJAAN BETON BERTULANG 825,930,093.58
E PEKERJAAN DINDING
2
1 Pasangan Batu Bata, 1pc : 4psr m 1,804.27 126,656.20 228,521,791.99
2
2 Plesteran Dinding, 1pc : 4psr m 3,505.32 74,004.61 259,409,557.92
2
3 Acian dinding (Dinding luar) m 870.45 42,997.35 37,427,021.81
Keramik dinding 30x60cm Rg. UGD, Rg. Persalinan, Toilet dan Rg. 2
4 m 209.15 365,648.97 76,476,943.63
Wudhu (t:1.2 m), Meja Laboratorium, Dapur & Pantry (t:0,6 m)
5 Dinding ACP Pvdf 0,3 mm, rangka besi hollow 40.40.1 m2 69.56 831,957.50 57,874,749.11
6 Pek. Curtain wall, rangka alumunium 4" powder coating, putih (Tipe DK7) m 66.76 162,254.95 10,832,140.46
2
7 Kaca t: 8 mm panasap/rayban warna biru (Tipe DK7) m 23.23 344,761.34 8,010,495.26
2
8 Dinding partisi, gypsum board rangka metal stud, 2 rangkap m 50.93 235,957.87 12,017,003.88
JUMLAH HARGA PEKERJAAN DINDING 690,569,704.05
F PEKERJAAN LANTAI
1 Urugan pasir bawah lantai t:30cm m3 68.40 199,485.00 13,645,172.97
2
2 Rolag bata teras dan selasar m 32.32 126,656.20 4,093,528.38
3
3 Rabat beton bawah lantai m 9.64 1,003,560.24 9,673,818.97
2
4 Lantai Granit setara Indogress, Motif Uk. 60 x 60, polish m 805.59 472,687.27 380,791,192.46
2
5 Lantai Granit setara Garuda Uk. 60 x 60, unpolish m 23.29 472,687.27 11,008,886.52
2
6 Plint dinding Granit setara Garuda 10 x 60 cm, polish m 73.74 472,687.27 34,854,541.23
2
7 Lantai Keramik warna Uk. 30 x 30, polish m 41.10 256,700.15 10,550,376.06
2
8 Lantai Keramik warna Uk. 30 x 30, unpolish m 152.41 256,700.15 39,123,669.47
JUMLAH HARGA PEKERJAAN LANTAI 503,741,186.06
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6
G PEKERJAAN ATAP
2
1 Rangka Atap Baja Ringan Canal Truss C.75.75, Reng U 0.45mm m 813.16 148,128.61 120,452,795.80
2
2 Penutup Atap Bitumen Gelombang setara onduline m 813.16 145,702.70 118,480,132.06
3 Nok atap Bitumen Gelombang setara onduline m' 95.78 184,952.90 17,714,788.76
4 Lisplank Superplank, lebar 20 cm, t= 9mm m' 171.27 61,553.25 10,542,225.13
2
5 Atap zincalume 0,35 mm (atap void) m 74.67 136,818.00 10,216,473.70
6 Kanopi depan, Rangka utama Baja WF 75.150.7.5+Aksesori (base plate
Kg 386.12 45,314.50 17,496,834.74
7mm+angkur baut dia. 12 mm)
7 Penutup atap kanopi depan, zincalume 0,35 mm, rangka besi hollow 2
m 61.10 520,000.00 31,772,000.00
40.40.1
8 Talang air PVC m' 18.20 24,375.00 443,625.00
2
9 Lisplank kanopi, ACP Pvdf 0,3 mm, rangka besi hollow 40.40.1 m 20.94 831,957.50 17,424,517.88
10 Penutup tiang depan 4 bh, ACP Pvdf 0,3 mm, rangka besi hollow 40.40.1 2
m 20.25 831,957.50 16,844,144.33
2
11 Kanopi selasar, Atap zincalume 0,35 mm, rangka besi hollow 40.40.1 m 26.97 520,000.00 14,024,400.00
JUMLAH HARGA PEKERJAAN ATAP 375,411,937.40
H PEKERJAAN KUSEN PINTU DAN JENDELA
1 Kusen Pintu, Jendela dan Ventilasi Alumunium 3" warna cokelat m 1,018.31 162,254.95 165,225,838.13
2
2 Daun Pintu DK1 dan DK6, kaca tempered t:12 mm, polos m 6.40 1,194,775.45 7,646,562.88
3 Floor hinge, setara Dorma bh 4.00 1,980,000.00 7,920,000.00
4 Patch Fitting set set 4.00 1,035,000.00 4,140,000.00
5 Cylinder lock pintu kaca bh 2.00 780,000.00 1,560,000.00
6 Pull Handle P: 120 cm, Stainless steel psg 4.00 619,850.00 2,479,400.00
2
7 Daun pintu multipleks 18 mm, lapis HPL woodgrain (2 rangkap) m 70.01 665,028.34 46,555,309.14
2
8 Daun pintu toilet, bingkai profil alumunium+alumunium spandrel m 20.20 400,000.00 8,080,000.00
2
9 Daun Jendela dan ventilasi rangka profil alumunium m 64.05 337,085.10 21,591,109.66
2
10 Pek. Kaca t:5 mm, polos m 183.79 269,125.45 49,461,974.38
11 Engsel Pintu, ex. DEKSON atau setara bh 217.00 65,320.20 14,174,483.40
12 Kunci Pintu silinderTanam, ex. SES atau setara bh 34.00 250,189.50 8,506,443.00
13 Pull handle pintu P1, P2 & P3 psg 59.00 176,000.00 10,384,000.00
14 Engsel Jendela/cesement bh 166.00 71,590.75 11,884,064.50
15 Rambuncis/kunci jendela bh 83.00 31,250.00 2,593,750.00
JUMLAH HARGA PEKERJAAN KUSEN PINTU DAN JENDELA 362,202,935.09
I PEKERJAAN PLAFON
2
1 Rangka Plafon hollow galvalume 20.40 mm m 1,113.36 145,854.50 162,388,566.12
2
2 Plafon gypsumboard 9 mm m 1,113.36 67,779.14 75,462,583.31
2
3 Lis profil plafon, gypsumboard strip 5 cm m 88.48 67,779.14 5,997,396.54
JUMLAH HARGA PEKERJAAN PLAFON 243,848,545.97
J PEKERJAAN PENGECATAN
1 Plamur dan Pengecatan Dinding Dalam/Interior m2 2,351.98 25,990.03 61,127,916.40
2
2 Pengecatan Dinding Luar/Eksterior m 870.45 33,058.30 28,775,580.71
2
3 Pengecatan Plafon m 1,113.36 38,987.30 43,406,900.33
2
4 Pengecatan lisplank m 34.25 38,987.30 1,335,470.97
2
5 Waterproof dak beton m 12.00 26,185.50 314,226.00
JUMLAH HARGA PEKERJAAN PENGECATAN 134,960,094.41
K PEKERJAAN PLUMBING & SANITAIR
1 Pipa Disposal cair PVC dia.3" AW, ex. Maspion atau setara m' 165.44 87,936.81 14,548,265.02
2 Pipa Suplai Air Bersih PVC dia. 3/4" AW, ex. Maspion atau setara m' 47.50 30,326.51 1,440,508.99
3 Pipa Distribusi Air Bersih PVC dia.1/2" AW, ex. Maspion atau setara m' 260.70 26,367.50 6,874,005.95
4 Pipa Disposal Padat PVC dia.3" AW, ex. Maspion atau setara m' 119.90 87,936.81 10,543,622.92
5 Kloset Duduk, American standard atau setara bh 20.00 3,847,266.50 76,945,330.00
6 Jet washer bh 20.00 280,000.00 5,600,000.00
7 Sink/bak cuci piring, stainless steel kualitas sedang bh 3.00 300,000.00 900,000.00
8 Kran Air 1/2", ex onda atau setara bh 22.00 90,848.18 1,998,659.85
9 Kran Air 1/2" sink/bak cuci piring , ex onda atau setara bh 3.00 90,000.00 270,000.00
10 Floor Drain, stainless steel dia. 3" bh 22.00 89,952.50 1,978,955.00
11 Reservoir/tandon air bahan fiber kapasitas 1200 liter bh 2.00 1,690,000.00 3,380,000.00
12 Washtafel setara Toto bh 15.00 1,795,695.00 26,935,425.00
13 Septictank 1,2 x 2.85 m bh 2.00 5,599,148.97 11,198,297.95
14 Mesin pompa air sumur dangkal, setara shimizu PS-130 Bit bh 1.00 910,000.00 910,000.00
JUMLAH HARGA PEKERJAAN PLUMBING & SANITAIR 163,523,070.67
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN SAT VOL
(Rp.) (Rp.)
1 2 3 4 5 6
L PEKERJAAN ELEKTRIKAL
1 Penambahan daya listrik 1300 VA ke 5.500 VA ls 1.00 5,111,250.00 5,111,250.00
2 MCB 20A ex. Schneider bh 3.00 227,700.00 683,100.00
2
3 Instalasi Penerangan Kabel 3x2,5 mm + PVC 20 mm titik 126.00 322,668.50 40,656,231.00
2
4 Instalasi Stop kontak 3x2,5 mm + PVC 20 mm titik 86.00 345,658.50 29,726,631.00
5 Fitting Lampu Downlight diameter 4" bh 126.00 54,600.00 6,879,600.00
6 Lampu PLC 13 watt, ex. PHILIPS bh 102.00 43,200.00 4,406,400.00
7 Lampu PLC 8 watt, ex. PHILIPS bh 24.00 36,000.00 864,000.00
8 Stop Kontak, ex. Broco bh 55.00 51,350.00 2,824,250.00
9 Stop Kontak AC, ex. Panasonic bh 31.00 66,950.00 2,075,450.00
10 Saklar Ganda, ex.Broco bh 20.00 38,350.00 767,000.00
11 Saklar Tunggal, ex.Broco bh 40.00 22,100.00 884,000.00
12 Outlet MATV + Penyambungan bh 2.00 188,350.00 376,700.00
13 Exhaust fan toilet, ex. Panasonic FV15TGU1W bh 8.00 338,000.00 2,704,000.00
JUMLAH HARGA PEKERJAAN ELEKTRIKAL 97,958,612.00
M PEKERJAAN LANDSCAPE
1 Perkerasan area luar, Paving block model bata t=6 cm K300 2
m 85.60 124,897.71 10,691,243.72
2 Huruf timbul t:30 cm, acrylic 5mm (depan), plat galvanis fin. Duco
bh 13.00 562,500.00 7,312,500.00
(belakang) + lampu LED strip (sign PUSKESMAS MOTI)
3 Huruf timbul t:20 cm, acrylic 5mm (depan), plat galvanis fin. Duco
bh 8.00 375,000.00 3,000,000.00
(belakang) + lampu LED strip (sign UGD 24 JAM)
4
Logo Puskesmas, acrylic 5mm (depan), plat galvanis fin. Duco (belakang) bh 1.00 5,500,000.00 5,500,000.00
JUMLAH HARGA PEKERJAAN LANDSCAPE 26,503,743.72
N PEKERJAAN INTERIOR
Railing tangga, tiang besi dan handrail besi hollow stainless 40.60.1,2,
1 m 14.65 750,000.00 10,987,500.00
teralisbesi hollow stainless 20.40.1
2
2 Pemasangan Wallpaper Dinding Polos Embose Bahan Vinyl (Rg. Kapus) m 60.80 111,586.32 6,783,912.39
2
3 Meja counter (Rg. Pendaftaran dan Rg. Farmasi) m 15.60 583,820.83 9,104,685.92
JUMLAH HARGA PEKERJAAN INTERIOR 26,876,098.30
ANALISA HARGA SATUAN PEKERJAAN
Peraturan Menteri PUPERA No. 28/PRT/M/2016

A.2.3.1 SATUAN PEKERJAAN GALIAN

TM.04.a.1 Galian tanah kedalaman 0 - 2 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A. TENAGA
Pekerja L.01 OH 0.7500 95,000.00 71,250.00
Mandor L.04 OH 0.0250 165,000.00 4,125.00
JUMLAH TENAGA KERJA 75,375.00
B. BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah ( A + B + C ) 75,375.00
E Overheead & Profit 10% x D 7,537.50

F Harga Satuan Pekerjaan 82,912.50

A.2.3.1.9 Pengurugan kembali 1m3 galian tanah

No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A. TENAGA
Pekerja L.01 Oh 0.5000 95,000.00 47,500.00
Mandor L.04 Oh 0.0500 165,000.00 8,250.00
JUMLAH TENAGA KERJA 55,750.00
B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT -
D. Jumlah ( A + B + C ) 55,750.00
E. Overheead & Profit 10% 5,575.00
F. Harga Satuan Pekerjaan dengan Tanah Urug 55,750.00

A.2.3.1.11 Pengurukan 1 m3 dengan pasir dan tanah timbunan

No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A. TENAGA
Pekerja L.01 Oh 0.3000 95,000.00 28,500.00
Mandor L.04 Oh 0.0100 165,000.00 1,650.00
JUMLAH TENAGA KERJA 30,150.00
B. BAHAN
3
Pasir Urug m 1.2000 126,000.00 151,200.00
3
Tanah Timbunan m 1.2000 100,000.00 120,000.00
JUMLAH HARGA BAHAN 271,200.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. Jumlah ( A + B + C ) Pasir Urug 181,350.00
Jumlah ( A + B + C ) Tanah Urug 150,150.00
E. Overheead & Profit 10%
F. Harga Satuan Pekerjaan dengan Pasir Urug 199,485.00
Harga Satuan Pekerjaan dengan Tanah Timbunan 165,165.00
TM.04.c Pemadatan Tanah di Lokasi Pekerjaan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1422 95,000.00 13,509.00
Mandor L.04 OH 0.0142 165,000.00 2,343.00
JUMLAH TENAGA KERJA 15,852.00
B. BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
Roller Vibro E.49 jam 0.0178 283,600.00 5,048.08
Water Tank Truck E.50 jam 0.0078 85,600.00 667.68
JUMLAH HARGA ALAT 667.68
D Jumlah ( A + B + C ) 16,519.68
E Overheead & Profit 10% x D 1,651.97
F Harga Satuan Pekerjaan 18,171.65

A.3.2.1 SATUAN PEKERJAAN PONDASI

A.3.2.1.2 Pemasangan pondasi batu belah, campuran 1 SP : 4 PP

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 1.5000 95,000.00 142,500.00
Tukang batu L.02 Oh 0.7500 135,000.00 101,250.00
Kepala tukang L.03 Oh 0.0750 150,000.00 11,250.00
Mandor L.04 Oh 0.0750 165,000.00 12,375.00
JUMLAH TENAGA KERJA 267,375.00
B BAHAN
Batu gunung 15/20 m3 1.2000 157,500.00 189,000.00
Semen PC kg 163.0000 1,322.50 215,567.50
Pasir Pasang m3 0.5200 300,000.00 156,000.00
JUMLAH HARGA BAHAN 560,567.50

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 827,942.50
E. Overheead & Profit 10% x D 82,794.25
F. Harga Satuan Pekerjaan 910,736.75

A.3.2.1.9 Pemasangan 1m3 Batu Kosong (anstamping)

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja Oh 0.7800 95,000.00 74,100.00
Tukang batu Oh 0.3900 135,000.00 52,650.00
Kepala tukang Oh 0.0390 150,000.00 5,850.00
Mandor Oh 0.0390 165,000.00 6,435.00
JUMLAH TENAGA KERJA 139,035.00
B BAHAN
Batu gunung m3 1.2000 157,500.00 189,000.00
3
Pasir Pasang m 0.4320 300,000.00 129,600.00
JUMLAH HARGA BAHAN 318,600.00
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 457,635.00
E. Overheead & Profit 10% x D 45,763.50
F. Harga Satuan Pekerjaan 503,398.50
A.4.1.1 SATUAN PEKERJAAN BETON
CATATAN
Bobot isi pasir = 1,400 kg/m3 jadi 1 kg Rp.Rp 168.79
Bobot isi kerikil = 1,350 kg/m3 jadi 1 kg Rp.Rp 276.85
Bulking faktor pasir = 20.00 %
A.4.1.1.4 Membuat 1 m3 lantai kerja Beton mutu f' c = 7,4 Mpa (k100), slump ( 12 ± 2 ) cm, w/c = 0,87

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 1.200 95,000.00 114,000.00
Tukang batu L.02 Oh 0.120 135,000.00 16,200.00
Kepala tukang L.03 Oh 0.020 150,000.00 3,000.00
Mandor L.04 Oh 0.060 165,000.00 9,900.00
JUMLAH TENAGA KERJA 143,100.00
B BAHAN
Semen PC kg 230.000 1,322.50 304,175.00
Pasir beton kg 893.000 168.79 150,725.64
Krikil (max. 30 mm ) kg 1,027.00 276.85 284,326.85
Air ltr 200.000 150.00 30,000.00
JUMLAH HARGA BAHAN 769,227.49
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 912,327.49
E. Overheead & Profit 10% x D 91,232.75
F. Harga Satuan Pekerjaan 1,003,560.24

A.4.1.1.8 Membuat 1 m3 beton mutu f' c = 21,7 Mpa ( K 250 ), slump ( 12 ± 2 ) cm, w/c = 0,56

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 1.650 95,000.00 156,750.00
Tukang batu L.02 Oh 0.275 135,000.00 37,125.00
Kepala tukang L.03 Oh 0.028 150,000.00 4,200.00
Mandor L.04 Oh 0.083 165,000.00 13,695.00
JUMLAH TENAGA KERJA 211,770.00
B BAHAN
Semen PC kg 384.00 1,322.50 507,840.00
Pasir beton kg 692.00 168.79 116,799.71
Krikil (max. 30 mm ) kg 1,039.00 276.85 287,649.07
Air ltr 215.00 150.00 32,250.00
JUMLAH HARGA BAHAN 944,538.79
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 1,156,308.79
E. Overheead & Profit 10% x D 115,630.88
F. Harga Satuan Pekerjaan 1,271,939.67

A.4.1.1.17 Pembesian 10 Kg dengan besi polos atau besi ulir

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.070 95,000.00 6,650.00
Tukang besi L.02 Oh 0.070 135,000.00 9,450.00
Kepala tukang L.03 Oh 0.007 150,000.00 1,050.00
Mandor L.04 Oh 0.004 165,000.00 660.00
JUMLAH TENAGA KERJA 17,810.00
B BAHAN
Besi beton polos kg 10.500 13,125.00 137,812.50
Kawat beton kg 0.150 26,250.00 3,937.50
JUMLAH HARGA BAHAN 141,750.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 159,560.00
E. Overheead & Profit 10% x D 15,956.00
F. Harga Satuan Pekerjaan Per 10 Kg 175,516.00
Per 1 Kg 17,551.60
A.4.1.1.19.a Pemasangan 1 m2 Wiremesh (1 lapis)

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0250 95,000.00 2,375.00
Tukang besi L.02 Oh 0.0250 135,000.00 3,375.00
Kepala tukang L.03 Oh 0.0250 150,000.00 3,750.00
Mandor L.04 Oh 0.0010 165,000.00 165.00
JUMLAH TENAGA KERJA 9,665.00
B BAHAN
Wiremesh lbr 0.0970 569,800.00 55,271.60
Kawat beton kg 0.3000 33,150.00 9,945.00
JUMLAH HARGA BAHAN 65,216.60
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 74,881.60
E. Overheead & Profit 10% x D 7,488.16
F. Harga Satuan Pekerjaan 82,369.77

A.4.1.1.20 Memasang 1 m2 bekisting untuk pondasi

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.5200 95,000.00 49,400.00
Tukang kayu L.02 Oh 0.2600 135,000.00 35,100.00
Kepala tukang L.03 Oh 0.0260 150,000.00 3,900.00
Mandor L.04 Oh 0.0260 165,000.00 4,290.00
JUMLAH TENAGA KERJA 92,690.00
B BAHAN
Kayu kls.III (2x pakai) m3 0.0200 3,850,000.00 77,000.00
Paku 5 cm - 10 cm kg 0.3000 26,250.00 7,875.00
Minyak bekesting ltr 0.1000 16,200.00 1,620.00
JUMLAH HARGA BAHAN 86,495.00
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 179,185.00
E. Overheead & Profit 10% x D 17,918.50
F. Harga Satuan Pekerjaan 197,103.50

2
A.4.1.1.21 Memasang 1 m bekisting untuk sloof

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.5200 95,000.00 49,400.00
Tukang kayu L.02 Oh 0.2600 135,000.00 35,100.00
Kepala tukang L.03 Oh 0.0260 150,000.00 3,900.00
Mandor L.04 Oh 0.0260 165,000.00 4,290.00
JUMLAH TENAGA KERJA 92,690.00
B BAHAN
3
Kayu kls.III (2x pakai) m 0.0225 3,850,000.00 86,625.00
Paku 5 cm - 10 cm kg 0.3000 26,250.00 7,875.00
Minyak bekesting ltr 0.1000 16,200.00 1,620.00
JUMLAH HARGA BAHAN 96,120.00
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 188,810.00
E. Overheead & Profit 10% x D 18,881.00
F. Harga Satuan Pekerjaan 207,691.00
A.4.1.1.22 Memasang 1 m2 bekisting untuk kolom

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.6600 95,000.00 62,700.00
Tukang kayu L.02 Oh 0.3300 135,000.00 44,550.00
Kepala tukang L.03 Oh 0.0330 150,000.00 4,950.00
Mandor L.04 Oh 0.0330 165,000.00 5,445.00
JUMLAH TENAGA KERJA 117,645.00
B BAHAN
Kayu kls.III (2x pakai) m3 0.0200 3,850,000.00 77,000.00
Paku 5 cm - 10 cm kg 0.4000 26,250.00 10,500.00
Minyak bekesting ltr 0.2000 16,200.00 3,240.00
3
Balok kayu Kls.II (2x pakai) m 0.0075 5,500,000.00 41,250.00
Plywood, tebal 9 mm (2x pakai) lbr 0.1750 143,000.00 25,025.00
Dolken kayu Ø8 - 10 cm - pjg 4 m (2x pakai) btg 1.0000 26,250.00 26,250.00
JUMLAH HARGA BAHAN 183,265.00
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 300,910.00
E. Overheead & Profit 10% x D 30,091.00
F. Harga Satuan Pekerjaan 331,001.00

A.4.1.1.23 Memasang 1 m2 bekisting untuk balok

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.6600 95,000.00 62,700.00
Tukang kayu L.02 Oh 0.3300 135,000.00 44,550.00
Kepala tukang L.03 Oh 0.0330 150,000.00 4,950.00
Mandor L.04 Oh 0.0330 165,000.00 5,445.00
JUMLAH TENAGA KERJA 117,645.00
B BAHAN
Kayu kls.III (2x pakai) m3 0.0200 3,850,000.00 77,000.00
Paku 5 cm - 10 cm kg 0.4000 26,250.00 10,500.00
Minyak bekesting ltr 0.2000 16,200.00 3,240.00
Balok kayu Kls.II (2x pakai) m3 0.0090 5,500,000.00 49,500.00
Plywood, tebal 9 mm (2x pakai) lbr 0.1750 143,000.00 25,025.00
Dolken kayu Ø8 - 10 cm - pjg 4 m (2x pakai) btg 1.0000 26,250.00 26,250.00
JUMLAH HARGA BAHAN 191,515.00
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 309,160.00
E. Overheead & Profit 10% x D 30,916.00
F. Harga Satuan Pekerjaan 340,076.00

A.4.1.1.24 Memasang 1 m2 bekisting untuk lantai

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.6600 95,000.00 62,700.00
Tukang kayu L.02 Oh 0.3300 135,000.00 44,550.00
Kepala tukang L.03 Oh 0.0330 150,000.00 4,950.00
Mandor L.04 Oh 0.0330 165,000.00 5,445.00
JUMLAH TENAGA KERJA 117,645.00
B BAHAN
Kayu kls.III (2x pakai) m3 0.0200 3,850,000.00 77,000.00
Paku 5 cm - 10 cm kg 0.4000 26,250.00 10,500.00
Minyak bekesting ltr 0.2000 16,200.00 3,240.00
3
Balok kayu Kls.II (2x pakai) m 0.0075 5,500,000.00 41,250.00
Plywood, tebal 9 mm (2x pakai) lbr 0.1750 143,000.00 25,025.00
Dolken kayu Ø8 - 10 cm - pjg 4 m (2x pakai) btg 3.0000 26,250.00 78,750.00
JUMLAH HARGA BAHAN 235,765.00
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 353,410.00
E. Overheead & Profit 10% x D 35,341.00
F. Harga Satuan Pekerjaan 388,751.00
- 1 M2 Pekerjaan Floordecking

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.2000 95,000.00 19,000.00
Tukang kayu L.02 Oh 0.3000 135,000.00 40,500.00
Kepala tukang L.03 Oh 0.0300 150,000.00 4,500.00
Mandor L.04 Oh 0.0250 165,000.00 4,125.00
JUMLAH TENAGA KERJA 68,125.00
B BAHAN
Floor decking m2 1.0000 143,000.00 143,000.00
JUMLAH HARGA BAHAN 143,000.00
C PERALATAN
JUMLAH HARGA PERALATAN
D. Jumlah ( A + B + C ) 211,125.00
E. Overheead & Profit 10% x D 21,112.50
F. Harga Satuan Pekerjaan 232,237.50

A.4.2.1 SATUAN PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.11. Pemasangan 1 m kusen alluminium

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0430 95,000.00 4,085.00
Tukang alumunium / kaca L.02 Oh 0.0430 135,000.00 5,805.00
Kepala tukang L.03 Oh 0.0043 150,000.00 645.00
Mandor L.04 Oh 0.0021 165,000.00 346.50
JUMLAH TENAGA KERJA 10,881.50
B BAHAN
Profil alluminium m 1.1000 119,000.00 130,900.00
Skrup fisher bh 2.0000 2,500.00 5,000.00
Sealant tube 0.0600 12,050.00 723.00
JUMLAH HARGA BAHAN 136,623.00
C PERALATAN
-
JUMLAH HARGA PERALATAN -
D. Jumlah ( A + B + C ) 147,504.50
E. Overheead & Profit 10% x D 14,750.45
F. Harga Satuan Pekerjaan 162,254.95

A.4.2.1.13. Pemasangan 1 m2 rangka kaca alluminium

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0850 95,000.00 8,075.00
Tukang alumunium / kaca L.02 Oh 0.0850 135,000.00 11,475.00
Kepala tukang L.03 Oh 0.0090 150,000.00 1,350.00
Mandor L.04 Oh 0.0050 165,000.00 825.00
JUMLAH TENAGA KERJA 21,725.00
B BAHAN
Pintu/jendela alluminium m 4.4000 31,625.00 139,150.00
Profil kaca m 4.5000 31,625.00 142,312.50
Sealant tube 0.2700 12,050.00 3,253.50
JUMLAH HARGA BAHAN 284,716.00
C PERALATAN
-
JUMLAH HARGA PERALATAN -
D. Jumlah ( A + B + C ) 306,441.00
E. Overheead & Profit 10% x D 30,644.10
F. Harga Satuan Pekerjaan 337,085.10
A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60x60 cm, plafond

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.3500 95,000.00 33,250.00
Tukang besi L.02 Oh 0.3500 135,000.00 47,250.00
Kepala tukang L.03 Oh 0.0350 150,000.00 5,250.00
Mandor L.04 Oh 0.0180 165,000.00 2,970.00
JUMLAH TENAGA KERJA 88,720.00
B BAHAN
Rangka metal hollow 20.40.2 mm m 4.0000 8,775.00 35,100.00
Aksesoris (perkuatan, las dll) Ls 100% x rangka 8,775.00 8,775.00
JUMLAH HARGA BAHAN 43,875.00
C PERALATAN
-
JUMLAH HARGA PERALATAN -
D. Jumlah ( A + B + C ) 132,595.00
E. Overheead & Profit 10% x D 13,259.50
F. Harga Satuan Pekerjaan 145,854.50

2
A.4.2.1.22 Pemasangan 1 m atap pelana rangka atap baja canai dingin profil C75

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.2600 95,000.00 24,700.00
Tukang besi L.02 Oh 0.0200 135,000.00 2,700.00
Kepala tukang L.03 Oh 0.2250 150,000.00 33,750.00
Mandor L.04 Oh 0.0125 165,000.00 2,062.50
JUMLAH TENAGA KERJA 63,212.50
B BAHAN
Baja ringan canai dingin C75 kg 3.0650 22,575.00 69,192.38
JUMLAH HARGA BAHAN 69,192.38
C PERALATAN
Peralatan % 10.000 2,257.50 2,257.50
JUMLAH HARGA PERALATAN 2,257.50
D. Jumlah ( A + B + C ) 134,662.38
E. Overheead & Profit 10% x D 13,466.24
F. Harga Satuan Pekerjaan 148,128.61

A.4.4.1 SATUAN PEKERJAAN DINDING

2
A.4.4.1.7 Pemasangan 1m dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :2PP

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.3000 95,000.00 28,500.00
Tukang batu L.02 Oh 0.1000 135,000.00 13,500.00
Kepala tukang L.03 Oh 0.0100 150,000.00 1,500.00
Mandor L.04 Oh 0.0150 165,000.00 2,475.00
JUMLAH TENAGA KERJA 45,975.00
B BAHAN
Bata merah buah 70.0000 630.00 44,100.00
Semen portland kg 18.9500 1,058.00 20,049.10
3
Pasir pasang m 0.0380 300,000.00 11,400.00
JUMLAH HARGA BAHAN 75,549.10
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 121,524.10
E. Overheead & Profit 10% x D 12,152.41
F. Harga Satuan Pekerjaan 133,676.51
A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.3000 95,000.00 28,500.00
Tukang batu L.02 Oh 0.1000 135,000.00 13,500.00
Kepala tukang L.03 Oh 0.0100 150,000.00 1,500.00
Mandor L.04 Oh 0.0150 165,000.00 2,475.00
JUMLAH TENAGA KERJA 45,975.00
B BAHAN
Bata merah buah 70.0000 630.00 44,100.00
Semen portland kg 11.5000 1,058.00 12,167.00
3
Pasir pasang m 0.0430 300,000.00 12,900.00
JUMLAH HARGA BAHAN 69,167.00
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 115,142.00
E. Overheead & Profit 10% x D 11,514.20
F. Harga Satuan Pekerjaan 126,656.20

A.4.4.2 SATUAN PEKERJAAN PLESTERAN


2
A.4.4.2.4 Pemasangan 1 m plesteran 1 SP : 4 PP tebal 15 mm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.3000 95,000.00 28,500.00
Tukang batu L.02 Oh 0.1500 135,000.00 20,250.00
Kepala tukang L.03 Oh 0.0150 150,000.00 2,250.00
Mandor L.04 Oh 0.0150 165,000.00 2,475.00
JUMLAH TENAGA KERJA 53,475.00
B BAHAN
Semen portland kg 6.2400 1,058.00 6,601.92
3
Pasir pasang m 0.0240 300,000.00 7,200.00
JUMLAH HARGA BAHAN 13,801.92
C PERALATAN

JUMLAH HARGA PERALATAN


D. Jumlah ( A + B + C ) 67,276.92
E. Overheead & Profit 10% x D 6,727.69
F. Harga Satuan Pekerjaan 74,004.61

2
A.4.4.2.27 Pemasangan 1 m acian

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.2000 95,000.00 19,000.00
Tukang batu L.02 Oh 0.1000 135,000.00 13,500.00
Kepala tukang L.03 Oh 0.0100 150,000.00 1,500.00
Mandor L.04 Oh 0.0100 165,000.00 1,650.00
JUMLAH TENAGA KERJA 35,650.00
B BAHAN
Semen portland kg 3.2500 1,058.00 3,438.50
JUMLAH HARGA BAHAN 3,438.50
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 39,088.50
E. Overheead & Profit 10% x D 3,908.85
F. Harga Satuan Pekerjaan 42,997.35
A.4.4.3 SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
2
- Pemasangan 1m lantai granit ukuran 60 cm x 60 cm, motif

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

TENAGA
A
Pekerja L.01 Oh 0.5000 95,000.00 47,500.00
Tukang batu L.02 Oh 0.2500 135,000.00 33,750.00
Kepala tukang L.03 Oh 0.0250 150,000.00 3,750.00
Mandor L.04 Oh 0.0025 165,000.00 412.50
JUMLAH TENAGA KERJA 85,412.50
B BAHAN
Granit tile 60 x 60 cm Bh 2.7917 114,000.00 318,250.00
Semen portland Kg 10.4000 1,058.00 11,003.20
Semen warna Kg 0.6200 2,500.00 1,550.00
Pasir pasang m3 0.0450 300,000.00 13,500.00
JUMLAH HARGA BAHAN 344,303.20
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 429,715.70
E. Overheead & Profit 10% x D 42,971.57
F. Harga Satuan Pekerjaan 472,687.27

- Pemasangan 1 m2 dinding keramik 30 cm x 60 cm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

TENAGA
A
Pekerja L.01 Oh 0.9000 95,000.00 85,500.00
Tukang batu L.02 Oh 0.4500 135,000.00 60,750.00
Kepala tukang L.03 Oh 0.0450 150,000.00 6,750.00
Mandor L.04 Oh 0.0038 165,000.00 618.75
JUMLAH TENAGA KERJA 153,618.75
B BAHAN
Keramik bh 5.5778 28,452.33 158,700.00
Semen portland zak 9.3000 1,058.00 9,839.40
Pasir pasang m3 0.0180 300,000.00 5,400.00
Semen warna Kg 1.9400 2,500.00 4,850.00
JUMLAH HARGA BAHAN 178,789.40
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 332,408.15
E. Overheead & Profit 10% x D 33,240.82
F. Harga Satuan Pekerjaan 365,648.97

A.4.4.3.4 Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

TENAGA
A
Pekerja L.01 Oh 0.5000 95,000.00 47,500.00
Tukang batu L.02 Oh 0.2500 135,000.00 33,750.00
Kepala tukang L.03 Oh 0.0250 150,000.00 3,750.00
Mandor L.04 Oh 0.0250 165,000.00 4,125.00
JUMLAH TENAGA KERJA 89,125.00
B BAHAN
Keramik uk. 30 x 30 bh 11.1111 10,833.33 120,370.37
Semen portland kg 9.8000 1,058.00 10,368.40
3
Pasir pasang m 0.0450 300,000.00 13,500.00
JUMLAH HARGA BAHAN 144,238.77
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 233,363.77
E. Overheead & Profit 10% x D 23,336.38
F. Harga Satuan Pekerjaan 256,700.15
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.7 Pemasangan 1m2 langit-langit gysumboard ukuran (120x240x9)mm, tebal 3,5 mm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.1000 95,000.00 9,500.00
Tukang kayu L.02 Oh 0.0500 135,000.00 6,750.00
Kepala tukang L.03 Oh 0.0050 150,000.00 750.00
Mandor L.04 Oh 0.0050 165,000.00 825.00
JUMLAH TENAGA KERJA 17,825.00
B BAHAN
Gypsumboard lbr 0.3640 100,100.00 36,436.40
sekrup kg 0.1100 12,100.00 1,331.00
grouting dempul kg 0.1000 40,250.00 4,025.00
lakban jaring m 1.0000 2,000.00 2,000.00
JUMLAH HARGA BAHAN 43,792.40
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 61,617.40
E. Overheead & Profit 10% x D 6,161.74
F. Harga Satuan Pekerjaan 67,779.14

A.4.5.2 SATUAN PEKERJAAN PENUTUP ATAP

A.4.1.1.20 Pemasangan 1 m2 Atap Bitumen Gelombang memanjang monolayer


No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.1400 95,000.00 13,300.00
Tukang batu L.02 Oh 0.0700 135,000.00 9,450.00
Kepala tukang L.03 Oh 0.0070 150,000.00 1,050.00
Mandor L.04 Oh 0.0070 165,000.00 1,155.00
JUMLAH TENAGA KERJA 24,955.00
B BAHAN
Bitumen Bergelombang Monolayer 3
Lbr 0.6380 141,000.00 89,958.00
mm - Duro 235
Screw drill Bh 11.6960 1,500.00 17,544.00
JUMLAH HARGA BAHAN 107,502.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 132,457.00
E. Overheead & Profit 10% x D 13,245.70
F. Harga Satuan Pekerjaan 145,702.70

A.4.1.1.21 Pemasangan 1 m Nok Atap Bitumen Gelombang memanjang monolayer


No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.0840 95,000.00 7,980.00
Tukang batu L.02 Oh 0.1250 135,000.00 16,875.00
Kepala tukang L.03 Oh 0.0130 150,000.00 1,950.00
Mandor L.04 Oh 0.0040 165,000.00 660.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Nok/Ridge Onduline Lbr 1.4740 85,000.00 125,290.00
Screw drill Bh 10.2560 1,500.00 15,384.00
JUMLAH HARGA BAHAN 140,674.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 168,139.00
E. Overheead & Profit 10% x D 16,813.90
F. Harga Satuan Pekerjaan 184,952.90
A.4.5.2.41 Pemasangan 1m2 atap zincalume

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.1500 95,000.00 14,250.00
Tukang batu L.02 Oh 0.2500 135,000.00 33,750.00
Kepala tukang L.03 Oh 0.0800 150,000.00 12,000.00
Mandor L.04 Oh 0.0060 165,000.00 990.00
JUMLAH TENAGA KERJA 60,990.00
B BAHAN
atap zincalume lbr 1.0500 59,800.00 62,790.00
Self drilling screw kg 0.0200 30,000.00 600.00
JUMLAH HARGA BAHAN 63,390.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 124,380.00
E. Overheead & Profit 10% x D 12,438.00
F. Harga Satuan Pekerjaan 136,818.00

A.4.5.2.42 Pemasangan 1m' nok atap zincalume

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0840 95,000.00 7,980.00
Tukang kayu L.02 Oh 0.1250 135,000.00 16,875.00
Kepala tukang L.03 Oh 0.0130 150,000.00 1,950.00
Mandor L.04 Oh 0.0040 165,000.00 660.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Nok zincalume lbr 1.2000 31,200.00 37,440.00
Screw drill kg 0.0400 30,000.00 1,200.00
JUMLAH HARGA BAHAN 38,640.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 66,105.00
E. Overheead & Profit 10% x D 6,610.50
F. Harga Satuan Pekerjaan 72,715.50

An.Ter-08 Pemasangan 1m' lisplank superplank

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0500 95,000.00 4,750.00
Tukang besi L.02 Oh 0.0100 135,000.00 1,350.00
Kepala tukang L.03 Oh 0.1000 150,000.00 15,000.00
Mandor L.04 Oh 0.0050 165,000.00 825.00
JUMLAH TENAGA KERJA 21,925.00
B BAHAN
Kanal C 75 m' 1.1000 22,575.00 24,832.50
Papan lisplank lbr 0.3000 23,000.00 6,900.00
Assesories, perkuatan las, dll % 10.0000 2,300.00 2,300.00
JUMLAH HARGA BAHAN 34,032.50
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 55,957.50
E. Overheead & Profit 10% x D 5,595.75
F. Harga Satuan Pekerjaan 61,553.25
A.4.6.2 SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.1 Pemasangan 1 buah kunci tanam, 2x putar

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0600 95,000.00 5,700.00
Tukang kayu L.02 Oh 0.6000 135,000.00 81,000.00
Kepala tukang L.03 Oh 0.0600 150,000.00 9,000.00
Mandor L.04 Oh 0.0030 165,000.00 495.00
JUMLAH TENAGA KERJA 96,195.00
B BAHAN
Kunci tanam 2x putar bh 1.0000 131,250.00 131,250.00
JUMLAH HARGA BAHAN 131,250.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 227,445.00
E. Overheead & Profit 10% x D 22,744.50
F. Harga Satuan Pekerjaan 250,189.50

A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm, polos

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0150 95,000.00 1,425.00
Tukang kayu L.02 Oh 0.1500 135,000.00 20,250.00
Kepala tukang L.03 Oh 0.0150 150,000.00 2,250.00
Mandor L.04 Oh 0.0008 165,000.00 132.00
JUMLAH TENAGA KERJA 24,057.00
B BAHAN
Kaca tebal 5 mm m2 1.1000 200,000.00 220,000.00
Sealant Kg 0.0500 12,050.00 602.50
JUMLAH HARGA BAHAN 220,602.50
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 244,659.50
E. Overheead & Profit 10% x D 24,465.95
F. Harga Satuan Pekerjaan 269,125.45

A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm, rayben

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0150 95,000.00 1,425.00
Tukang kayu L.02 Oh 0.1500 135,000.00 20,250.00
Kepala tukang L.03 Oh 0.0150 150,000.00 2,250.00
Mandor L.04 Oh 0.0008 165,000.00 132.00
JUMLAH TENAGA KERJA 24,057.00
B BAHAN
Kaca tebal 5 mm m2 1.1000 220,000.00 242,000.00
Sealant Kg 0.0500 12,050.00 602.50
JUMLAH HARGA BAHAN 242,602.50
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 266,659.50
E. Overheead & Profit 10% x D 26,665.95
F. Harga Satuan Pekerjaan 293,325.45
A.4.6.2.17.a Pemasangan 1 m2 kaca tebal 8 mm, rayban

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0150 95,000.00 1,425.00
Tukang kayu L.02 Oh 0.1500 135,000.00 20,250.00
Kepala tukang L.03 Oh 0.0150 150,000.00 2,250.00
Mandor L.04 Oh 0.0008 165,000.00 132.00
JUMLAH TENAGA KERJA 24,057.00
B BAHAN
Kaca tebal 8 mm m2 1.1000 262,509.00 288,759.90
Sealant Kg 0.0500 12,050.00 602.50
JUMLAH HARGA BAHAN 289,362.40
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 313,419.40
E. Overheead & Profit 10% x D 31,341.94
F. Harga Satuan Pekerjaan 344,761.34

- Pemasangan 1 m2 kaca tempered tebal 12 mm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0150 95,000.00 1,425.00
Tukang kayu L.02 Oh 0.1500 135,000.00 20,250.00
Kepala tukang L.03 Oh 0.0150 150,000.00 2,250.00
Mandor L.04 Oh 0.0008 165,000.00 132.00
JUMLAH TENAGA KERJA 24,057.00
B BAHAN
Kaca tempered tebal 12 mm m2 1.1000 965,000.00 1,061,500.00
Sealant Kg 0.0500 12,050.00 602.50
JUMLAH HARGA BAHAN 1,062,102.50
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 1,086,159.50
E. Overheead & Profit 10% x D 108,615.95
F. Harga Satuan Pekerjaan 1,194,775.45

- 1 m2 Pemasangan Atap kaca

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.5000 95,000.00 47,500.00
Tukang kayu L.02 Oh 1.0000 135,000.00 135,000.00
Kepala tukang L.03 Oh 0.0500 150,000.00 7,500.00
Mandor L.04 Oh 0.0050 165,000.00 825.00
JUMLAH TENAGA KERJA 190,825.00
B BAHAN
karet bantal kaca/rubber m2 0.2000 123,750.00 24,750.00
silicone & lem kuning kg 0.5000 12,050.00 6,025.00
Kaca Tempered 10 mm polos m2 1.1000 777,500.00 855,250.00
JUMLAH HARGA BAHAN 886,025.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 1,076,850.00
E. Overheead & Profit 10% x D 107,685.00
F. Harga Satuan Pekerjaan 1,184,535.00
A.4.6.2.5 Pemasangan 1 buah engsel pintu

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0150 95,000.00
Tukang kayu L.02 Oh 0.1500 135,000.00 20,250.00
Kepala tukang L.03 Oh 0.0150 150,000.00 2,250.00
Mandor L.04 Oh 0.0008 165,000.00 132.00
JUMLAH TENAGA KERJA 22,632.00
B BAHAN
Engsel pintu bh 1.0000 36,750.00 36,750.00
JUMLAH HARGA BAHAN 36,750.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 59,382.00
E. Overheead & Profit 10% x D 5,938.20
F. Harga Satuan Pekerjaan 65,320.20

An.Ter-13 Pemasangan 1 buah engsel jendela casement

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0100 95,000.00
Tukang kayu L.02 Oh 0.1000 135,000.00 13,500.00
Kepala tukang L.03 Oh 0.0100 150,000.00 1,500.00
Mandor L.04 Oh 0.0005 165,000.00 82.50
JUMLAH TENAGA KERJA 15,082.50
B BAHAN
Engsel casement bh 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 65,082.50
E. Overheead & Profit 10% x D 6,508.25
F. Harga Satuan Pekerjaan 71,590.75

A.4.7.1 SATUAN PEKERJAAN PENGECATAN


A.4.7.1.10.b Pengecatan 1 m2 bidang tembok baru ( 1 lapis plamur, 1 lapis cat dasar, dan 2 lapis cat penutup )

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

TENAGA
A
Pekerja L.01 Oh 0.0280 95,000.00 2,660.00
Tukang cat L.02 Oh 0.0420 135,000.00 5,670.00
Kepala tukang L.03 Oh 0.0042 150,000.00 630.00
Mandor L.04 Oh 0.0030 165,000.00 495.00
JUMLAH TENAGA KERJA 9,455.00
B BAHAN
Plamur Skimcoat kg 0.0500 14,586.00 729.30
Cat dasar kg 0.1200 27,650.00 3,318.00
Cat penutup Interior kg 0.1800 56,250.00 10,125.00
Cat penutup Exterior kg 0.1800 96,000.00 17,280.00
JUMLAH HARGA BAHAN INTERIOR 14,172.30
JUMLAH HARGA BAHAN EKSTERIOR 20,598.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) Interior 23,627.30
D. Jumlah ( A + B + C ) Eksterior 30,053.00
E. Overheead & Profit Interior 10% x D 2,362.73
E. Overheead & Profit Eksterior 10% x D 3,005.30
F. Harga Satuan Pekerjaan Interior 25,990.03
F. Harga Satuan Pekerjaan Eksterior 33,058.30
A.4.7.1.10.b Pengecatan 1 m2 waterproofing ( 2 lapis cat )

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0200 95,000.00 1,900.00
Tukang cat L.02 Oh 0.0630 135,000.00 8,505.00
Kepala tukang L.03 Oh 0.0063 150,000.00 945.00
Mandor L.04 Oh 0.0030 165,000.00 495.00
JUMLAH TENAGA KERJA 11,845.00
B BAHAN
cat waterproofing kg 0.2600 46,000.0000 11,960.00
JUMLAH HARGA BAHAN 11,960.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 23,805.00
E. Overheead & Profit 10% x D 2,380.50
F. Harga Satuan Pekerjaan 26,185.50

A.4.7.1.10.b Pengecatan 1 m2 plafond (2 lapis cat)

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0200 95,000.00 1,900.00
Tukang cat L.02 Oh 0.0630 135,000.00 8,505.00
Kepala tukang L.03 Oh 0.0063 150,000.00 945.00
Mandor L.04 Oh 0.0030 165,000.00 495.00
JUMLAH TENAGA KERJA 11,845.00
B BAHAN
Cat Dasar/sealer kg 0.1200 27,650.00 3,318.00
Cat Penutup kg 0.2600 78,000.00 20,280.00
JUMLAH HARGA BAHAN 23,598.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 35,443.00
E. Overheead & Profit 10% x D 3,544.30
F. Harga Satuan Pekerjaan 38,987.30

A.5.1.1 SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1 Pemasangan 1 buah closet duduk/monoblock

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 1.0000 95,000.00 95,000.00
Tukang batu L.02 Oh 1.5000 135,000.00 202,500.00
Kepala tukang L.03 Oh 0.1500 150,000.00 22,500.00
Mandor L.04 Oh 0.1600 165,000.00 26,400.00
JUMLAH TENAGA KERJA 346,400.00
B BAHAN
Kloset duduk unit 1.0000 2,972,750.0 2,972,750.00
Perlengkapan Ls 6% x kloset 178,365.0 178,365.00
JUMLAH HARGA BAHAN 3,151,115.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 3,497,515.00
E. Overheead & Profit 10% x D 349,751.50
F. Harga Satuan Pekerjaan 3,847,266.50
A.5.1.1.5 Pemasangan 1 buah washtafel keramik / lavatory
No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 1.2000 95,000.00 114,000.00
Tukang kayu L.02 Oh 1.4500 135,000.00 195,750.00
Kepala tukang L.03 Oh 0.1500 150,000.00 22,500.00
Mandor L.04 Oh 0.0600 165,000.00 9,900.00
JUMLAH TENAGA KERJA 342,150.00
B BAHAN
Lavatory unit 1.2000 977,500.00 1,173,000.00
Perlengkapan % 12.0000 117,300.00 117,300.00
JUMLAH HARGA BAHAN 1,290,300.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 1,632,450.00
E. Overheead & Profit 10% x D 163,245.00
F. Harga Satuan Pekerjaan 1,795,695.00

A.5.1.1.14 Pemasangan 1 buah floor drain

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0100 95,000.00 950.00
Tukang kayu L.02 Oh 0.1000 135,000.00 13,500.00
Kepala tukang L.03 Oh 0.0100 150,000.00 1,500.00
Mandor L.04 Oh 0.0050 165,000.00 825.00
JUMLAH TENAGA KERJA 16,775.00
B BAHAN
Floor drain unit 1.0000 65,000.00 65,000.00
JUMLAH HARGA BAHAN 65,000.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 81,775.00
E. Overheead & Profit 10% x D 8,177.50
F. Harga Satuan Pekerjaan 89,952.50

A.5.1.1.19 Pemasangan 1 buah kran dia. 1/2" atau 3/4"

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.0100 95,000.00 950.00
Tukang kayu L.02 Oh 0.4000 135,000.00 54,000.00
Kepala tukang L.03 Oh 0.0400 150,000.00 6,000.00
Mandor L.04 Oh 0.0050 165,000.00 825.00
JUMLAH TENAGA KERJA 61,775.00
B BAHAN
Kran air bh 1.0000 20,658.00 20,658.00
Sealtape bh 0.0250 6,250.00 156.25
JUMLAH HARGA BAHAN 20,814.25
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 82,589.25
E. Overheead & Profit 10% x D 8,258.93
F. Harga Satuan Pekerjaan 90,848.18
A.5.1.1.25 Pemasangan 1 m' pipa PVC tipe AW Ø1/2"

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.0360 95,000.00 3,420.00
Tukang pipa L.02 Oh 0.0600 135,000.00 8,100.00
Kepala tukang L.03 Oh 0.0060 150,000.00 900.00
Mandor L.04 Oh 0.0020 165,000.00 330.00
JUMLAH TENAGA KERJA 12,750.00
B BAHAN
Pipa PVC 1/2" m 1.2000 7,239.00 8,686.80
Perlengkapan % 35.0000 2,533.65 2,533.65
JUMLAH HARGA BAHAN 11,220.45
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 23,970.45
E. Overheead & Profit 10% x D 2,397.05
F. Harga Satuan Pekerjaan 26,367.50

A.5.1.1.26 Pemasangan 1 m' pipa PVC tipe AW Ø3/4"

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.0360 95,000.00 3,420.00
Tukang pipa L.02 Oh 0.0600 135,000.00 8,100.00
Kepala tukang L.03 Oh 0.0060 150,000.00 900.00
Mandor L.04 Oh 0.0020 165,000.00 330.00
JUMLAH TENAGA KERJA 12,750.00
B BAHAN
Pipa PVC 3/4" m 1.2000 9,561.00 11,473.20
Perlengkapan % 35.0000 3,346.35 3,346.35
JUMLAH HARGA BAHAN 14,819.55
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 27,569.55
E. Overheead & Profit 10% x D 2,756.96
F. Harga Satuan Pekerjaan 30,326.51

A.5.1.1.31 Pemasangan 1 m' pipa PVC tipe AW Ø3"


No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.0810 95,000.00 7,695.00
Tukang pipa L.02 Oh 0.1350 135,000.00 18,225.00
Kepala tukang L.03 Oh 0.0135 150,000.00 2,025.00
Mandor L.04 Oh 0.0040 165,000.00 660.00
JUMLAH TENAGA KERJA 28,605.00
B BAHAN
Pipa PVC 3" m 1.2000 33,121.00 39,745.20
Perlengkapan % 35.0000 11,592.35 11,592.35
JUMLAH HARGA BAHAN 51,337.55
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 79,942.55
E. Overheead & Profit 10% x D 7,994.26
F. Harga Satuan Pekerjaan 87,936.81
SATUAN PEKERJAAN ELEKTRIKAL
An.Ter-13 Pemasangan 1 titik instalasi penerangan

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Tukang listrik L.02 Oh 0.5000 160,000.00 80,000.00
Kepala tukang L.03 Oh 0.2000 185,000.00 37,000.00
JUMLAH TENAGA KERJA 117,000.00
B BAHAN
Kabel NYM (3x2,5) mm m' 10.0000 12,000.00 120,000.00
Klem kabel No.10 bh 4.0000 3,100.00 12,400.00
Pipa Instalasi listrik bh 1.0000 10,855.00 10,855.00
Inbow dos bh 1.0000 6,800.00 6,800.00
Las dop bh 4.0000 1,695.00 6,780.00
Isolasi bh 1.0000 14,500.00 14,500.00
T-Dos 5/8" bh 1.0000 4,800.00 4,800.00
Alat bantu ls 0.1000 2,000.00 200.00
JUMLAH HARGA BAHAN 176,335.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 293,335.00
E. Overheead & Profit 10% x D 29,333.50
F. Harga Satuan Pekerjaan 322,668.50

An.Ter-14 Pemasangan 1 titik instalasi stop kontak

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Tukang listrik L.02 Oh 0.5000 160,000.00 80,000.00
Kepala tukang L.03 Oh 0.2000 185,000.00 37,000.00
JUMLAH TENAGA KERJA 117,000.00
B BAHAN
Kabel NYM (3x2,5) mm m' 12.0000 12,000.00 144,000.00
Klem kabel No.10 bh 3.0000 3,100.00 9,300.00
Pipa Instalasi listrik bh 1.0000 10,855.00 10,855.00
Inbow dos bh 1.0000 6,800.00 6,800.00
Las dop bh 4.0000 1,695.00 6,780.00
Isolasi bh 1.0000 14,500.00 14,500.00
T-Dos 5/8" bh 1.0000 4,800.00 4,800.00
Alat bantu ls 0.1000 2,000.00 200.00
JUMLAH HARGA BAHAN 197,235.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 314,235.00
E. Overheead & Profit 10% x D 31,423.50
F. Harga Satuan Pekerjaan 345,658.50

2
A.4.4.3.66 Pemasangan 1m Paving bolck 6 cm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.2500 76,800.00 19,200.00
Tukang batu L.02 Oh 0.5000 118,200.00 59,100.00
Kepala tukang L.03 Oh 0.0500 141,800.00 7,090.00
Mandor L.04 Oh 0.0013 141,800.00 184.34
JUMLAH TENAGA KERJA 85,574.34
B BAHAN
Paving blok t= 6 cm m2 1.0100 11,603.00 11,719.03
3
Pasir pasang m 0.0500 325,000.00 16,250.00
JUMLAH HARGA BAHAN 27,969.03
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 113,543.37
E. Overheead & Profit 10% x D 11,354.34
F. Harga Satuan Pekerjaan 124,897.71
A..4.4.3.60 Pemasangan 1m2 Wallpaper L: 50 cm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.3500 95,000.00 33,250.00
Tukang cat L.02 Oh 0.1750 135,000.00 23,625.00
Kepala tukang L.03 Oh 0.0170 150,000.00 2,550.00
Mandor L.04 Oh 0.0200 165,000.00 3,300.00
JUMLAH TENAGA KERJA 62,725.00
B BAHAN
wallpaper m 2.2000 9,473.68 20,842.11
lem kg 0.2500 71,500.00 17,875.00
JUMLAH HARGA BAHAN 38,717.11
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 101,442.11
E. Overheead & Profit 10% x D 10,144.21
F. Harga Satuan Pekerjaan 111,586.32

A.4.2.1.25. Pemasangan 1 m2 Dinding ACP, rangka besi hollow 1x40.40.1,2mm

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.4800 95,000.00 45,600.00
Tukang Alumunium L.02 Oh 0.7000 135,000.00 94,500.00
Kepala tukang L.03 Oh 0.0700 150,000.00 10,500.00
Mandor L.04 Oh 0.0583 165,000.00 9,625.00
JUMLAH TENAGA KERJA 160,225.00
B BAHAN
Dinding Alumunium Composite Panel
M2 1.0000 297,000.00 297,000.00
(ACP) PVDF 0,3 ex. seven
Waste 10% 29,700.00 29,700.00
Bracket besi siku 40.40.2,8 M1 3.0000 13,433.33 40,300.00
Stiffener M1 1.0000 40,000.00 40,000.00
Rangka Hollow galfanis 40.40.1,2 mm M1 6.0000 23,183.33 139,100.00
Sealant netral, lakban, sekrup dan spon ati Ls 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 596,100.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 756,325.00
E. Overheead & Profit 10% x D 75,632.50
F. Harga Satuan Pekerjaan 831,957.50

A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel hitam

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.7000 95,000.00 66,500.00
Tukang kayu L.02 Oh 0.3500 135,000.00 47,250.00
Kepala tukang L.03 Oh 0.0350 150,000.00 5,250.00
Mandor L.04 Oh 0.0350 165,000.00 5,775.00
JUMLAH TENAGA KERJA 124,775.00
B BAHAN
Batu tempel m2 1.1000 126,360.00 138,996.00
Semen Portland kg 11.7500 1,322.50 15,539.38
Pasir pasang m3 0.0350 300,000.00 10,500.00
Cat clear batu alam m2 0.1200 95,700.00 11,484.00
JUMLAH HARGA BAHAN 176,519.38
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 301,294.38
E. Overheead & Profit 10% x D 30,129.44
F. Harga Satuan Pekerjaan 331,423.81
- Pek. 1 m2 Daun pintu multipleks lapis HPL woodgrain 2 rangkap

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.5000 95,000.00 47,500.00
Tukang kayu L.02 Oh 0.2500 135,000.00 33,750.00
Kepala tukang L.03 Oh 0.0250 150,000.00 3,750.00
Mandor L.04 Oh 0.0025 165,000.00 412.50
JUMLAH TENAGA KERJA 85,412.50
B BAHAN
Multipleks 18 mm m2 2.2000 122,278.96 269,013.71
HPL Motif m2 2.2000 82,975.01 182,545.01
Edging/Tepi Pvc L:42 Mm m 4.0000 9,750.00 39,000.00
Lem kuning kg 0.4000 71,500.00 28,600.00
JUMLAH HARGA BAHAN 519,158.72
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 604,571.22
E. Overheead & Profit 10% x D 60,457.12
F. Harga Satuan Pekerjaan 665,028.34

- Pek. 1 m2 Dinding multipleks lapis HPL woodgrain, 1x rangkap

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.8000 95,000.00 76,000.00
Tukang kayu L.02 Oh 0.4000 135,000.00 54,000.00
Kepala tukang L.03 Oh 0.0400 150,000.00 6,000.00
Mandor L.04 Oh 0.0040 165,000.00 660.00
JUMLAH TENAGA KERJA 136,660.00
B BAHAN
Multipleks 18 mm m2 1.1000 122,278.96 134,506.85
HPL Motif m2 1.1000 82,975.01 91,272.51
Edging/Tepi Pvc L:42 Mm m 2.0000 9,750.00 19,500.00
Lem kuning kg 0.2000 71,500.00 14,300.00
JUMLAH HARGA BAHAN 259,579.36
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 396,239.36
E. Overheead & Profit 10% x D 39,623.94
F. Harga Satuan Pekerjaan 435,863.30

- Pek. 1 m2 Perabot multipleks lapis HPL woodgrain, 2x rangkap

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.8000 95,000.00 76,000.00
Tukang kayu L.02 Oh 0.4000 135,000.00 54,000.00
Kepala tukang L.03 Oh 0.0400 150,000.00 6,000.00
Mandor L.04 Oh 0.0040 165,000.00 660.00
JUMLAH TENAGA KERJA 136,660.00
B BAHAN
Multipleks 18 mm m2 2.2000 122,278.96 269,013.71
HPL Motif m2 1.1000 82,975.01 91,272.51
Edging/Tepi Pvc L:42 Mm m 2.0000 9,750.00 19,500.00
Lem kuning kg 0.2000 71,500.00 14,300.00
JUMLAH HARGA BAHAN 394,086.21
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 530,746.21
E. Overheead & Profit 10% x D 53,074.62
F. Harga Satuan Pekerjaan 583,820.83
- 1 M2 DINDING PARTISI

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.2000 95,000.00 19,000.00
Tukang kayu L.02 Oh 0.5000 135,000.00 67,500.00
Kepala tukang L.03 Oh 0.0500 150,000.00 7,500.00
Mandor L.04 Oh 0.0100 165,000.00 1,650.00
JUMLAH TENAGA KERJA 95,650.00
B BAHAN
Panel Gypsumboard (doubel) m2 2.2000 34,756.94 76,465.28
Metal stud galvalume m 2.5000 11,068.75 27,671.88
Metal stud galvalume U runner m 1.0000 14,720.00 14,720.00
JUMLAH HARGA BAHAN 118,857.15
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 214,507.15
E. Overheead & Profit 10% x D 21,450.72
F. Harga Satuan Pekerjaan 235,957.87

- 1 unit Septictank (1.2x2.8x2)

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 2.0000 95,000.00 190,000.00
Tukang kayu L.02 Oh 1.0000 135,000.00 135,000.00
Kepala tukang L.03 Oh 1.0000 150,000.00 150,000.00
Mandor L.04 Oh 0.5000 165,000.00 82,500.00
JUMLAH TENAGA KERJA 557,500.00
B BAHAN
Galian tanah m3 6.7200 82,912.50 557,172.00
Pasangan bata m2 16.0000 126,656.20 2,026,499.20
Pembesian plat lantai m3 59.6736 17,551.60 1,047,367.16
Pengecoran plat lantai kg 0.4032 1,271,939.67 512,846.07
Bekisting plat lantai m2 1.0000 388,751.00 388,751.00
JUMLAH HARGA BAHAN 4,532,635.43
C PERALATAN

JUMLAH HARGA PERALATAN -


D. Jumlah ( A + B + C ) 5,090,135.43
E. Overheead & Profit 10% x D 509,013.54
F. Harga Satuan Pekerjaan 5,599,148.97

A.4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja IWF

No. Uraian Kode Satuan Koefesien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 Oh 0.0600 95,000.00 5,700.00
Tukang las konstruksi L.02 Oh 0.0600 135,000.00 8,100.00
Kepala tukang L.03 Oh 0.0060 150,000.00 900.00
Mandor L.04 Oh 0.0030 165,000.00 495.00
JUMLAH TENAGA KERJA 15,195.00
B BAHAN
Besi baja IWF kg 1.1500 20,800.00 23,920.00
JUMLAH HARGA BAHAN 23,920.00
C PERALATAN
Peralatan % 10.000 2,080.00 2,080.00
JUMLAH HARGA PERALATAN 2,080.00
D. Jumlah ( A + B + C ) 41,195.00
E. Overheead & Profit 10% x D 4,119.50
F. Harga Satuan Pekerjaan 45,314.50
PERINCIAN MATA PEMBAYARAN SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI UNTUK PEKERJAAN GEDUNG

SATUAN KUANTIT HARGA TOTAL HARGA


NO URAIAN PEKERJAAN KET.
UKURAN AS SATUAN (Rp.) (Rp.)
1 Penyiapan RK3K terdiri atas:
Pembuatan dokumen Rencana Keselamatan Memperhatikan
a
Konstruksi jumlah dan jenis
Set 1 750,000.00 750,000.00
b Pembuatan prosedur dan instruksi kerja pekerjaan yang
c Penyiapan formulir dikerjakan
Jumlah 750,000.00
2 Sosialisasi dan Promosi K3 terdiri atas:
Memperhatikan
perkiraan jumlah
a Induksi K3 (safety Induction) Org 20 8,500.00 170,000.00
pekerja, tamu, dan
staf
Memperhatikan
perkiraan jumlah
b Pengarahan K3 (safety briefing) : Org 20 20,000.00 400,000.00
pekerja dan risiko K3
pekerjaan
c Pelatihan K3;
Memperhatikan
perkiraan jumlah
1 Bekerja di ketinggian Org 2 10,000.00 20,000.00
pekerja serta jumlah
dan jenis pekerjaan
Memperhatikan
perkiraan jumlah
2 Penggunaan bahan kimia (MSDS) Org 0 - -
pekerja serta jumlah
dan jenis pekerjaan
Memperhatikan
perkiraan jumlah
d Simulasi K3 Org 0 - -
pekerja dan risiko K3
pekerjaan
Memperhatikan
e Spanduk (Banner) Lbr 1 250,000.00 250,000.00 lokasi pekerjaan dan
waktu pekerjaan
Memperhatikan
f Poster Lbr 1 50,000.00 50,000.00 lokasi pekerjaan dan
waktu pekerjaan
Memperhatikan risiko
g Papan Informasi K3 Bh 1 150,000.00 150,000.00
K3 pekerjaan
Jumlah 1,040,000.00
3 Alat Pelindung Kerja dan Alat pelidung Diri
a Alat Pelindung Kerja dan Alat pelidung Diri
1 Jaring pengaman (safety net) Ls 0 - - sesuai kebutuhan
2 Tali keselamatan (safety line) Ls 0 - - sesuai kebutuhan
3 Pagar pengaman (Guard railing) Ls 0 - - sesuai kebutuhan
4 Pembatas area (Restricted area) Ls 0 - - sesuai kebutuhan
Jumlah -
b Alat Pelindung Diri terdiri atas:
Memperhatikan
1 Topi pelindung (safety helmet) Bh 15 96,000.00 1,440,000.00 perkiraan jumlah
pekerja tamu dan staf
2 Pelindung mata (Goggles, Spectacles) Psg 5 25,000.00 125,000.00 sesuai kebutuhan
3 Tameng muka (Face shield) Bh 0 55,000.00 - sesuai kebutuhan
4 Pelindung pernafasan dan Mulut (Masker) Bh 10 10,000.00 100,000.00 sesuai kebutuhan
5 Sarung tangan (Safety gloves) Psg 10 20,000.00 200,000.00 sesuai kebutuhan
Memperhatikan
6 Sepatu keselamatan (Safety shoes) Psg 5 300,000.00 1,500,000.00 perkiraan jumlah
pekerja tamu dan staf
7 Penunjang seluruh tubuh (Full body Harness) Bh 2 230,000.00 460,000.00 Sesuai kebutuhan
8 Rompi keselamatan (Safety vest) Bh 10 45,000.00 450,000.00 Sesuai kebutuhan
9 Celemek (Apron/Coveralls) Bh 5 35,000.00 175,000.00 Sesuai kebutuhan
10 Pelindung jatuh (Fall Arrester) Bh 2 450,000.00 900,000.00 Sesuai kebutuhan
Jumlah 5,350,000.00
SATUAN KUANTIT HARGA TOTAL HARGA
NO URAIAN PEKERJAAN KET.
UKURAN AS SATUAN (Rp.) (Rp.)
4 Asuransi dan Perijinan terdiri atas :
a Asuransi Ls 1 - -
Jumlah -
5 Personil K3 Konstruksi terdiri atas :
Memperhatikan
a Ahli K3 Konstruksi OB 0 6,000,000.00 - perkiraan jumlah
pekerja dan risiko K3
pekerjaan. Biaya
dimasukkan ke
b Petugas K3 Konstruksi OB 2 1,500,000.00 3,000,000.00 dalam biaya personel
manajerial.
Jumlah 3,000,000.00
6 Fasilitas sarana dan prasarana kesehatan;
a Peralatan P3K (kotak P3K, Obat luka, Perban, dll Ls 1 250,000.00 250,000.00 Sesuai kebutuhan
b Peralatan pengasapan (Fogging) Bh 0 - - Sesuai kebutuhan
Jumlah 250,000.00
7 Rambu-rambu yang diperlukan :
a Rambu petunjuk Bh 3 75,000.00 225,000.00 Sesuai kebutuhan
b Rambu larangan Bh 2 75,000.00 150,000.00 Sesuai kebutuhan
c Rambu Peringatan Bh 0 - - Sesuai kebutuhan
d Rambu Kewajiban Bh 0 - - Sesuai kebutuhan
e Rambu Informasi Bh 0 - - Sesuai kebutuhan
Sesuai kebutuhan
memperhatikan jenis
f Jalur evakuasi (Escape route) Ls 1 - -
pekerjaan dan risiko
K3 pekerjaan
Jumlah 375,000.00
8 Konsultasi dengan ahli terkait Keselamatan Konstruksi :
Sesuai kebutuhan
memperhatikan jenis
a Ahli K3 Konstruksi OJ 0 - - pekerjaan dan waktu
pelaksanaan
pekerjaan
Jumlah -
9 Lain-lain terkait pengendalian risiko Keselamatan Konstruksi :
Sesuai kebutuhan
memperhatikan jenis
a Alat Pemadam Api Ringan (APAR) Bh 0 - -
pekerjaan dan risiko
K3 pekerjaan
Sesuai kebutuhan
memperhatikan jenis
b Bendera K3 Bh 1 50,000.00 50,000.00
pekerjaan dan risiko
K3 pekerjaan
Memperhatikan
c Program Inspeksi Ls 0 - - perkiraan jumlah
pekerja
Sesuai kebutuhan
memperhatikan
e Pelaporan dan penyelidikan insiden Ls 0 - -
waktu pelaksanaan
pekerjaan
Sesuai kebutuhan
memperhatikan
f Pembuatan Kartu Identitas Pekerja (KIP) Lbr 0 - -
waktu pelaksanaan
pekerjaan
Jumlah 50,000.00
Total Jumlah 10,815,000.00 Dimasukkan ke RAB
HARGA
NO JENIS BARANG SAT.
ZONA 1
I BAHAN DASAR BANGUNAN KEC. BANTAENG
A BAHAN DASAR. KEC. BISSAPPU
KEC. EREMERASA
KEC. PA'JUKUKANG
1 BATU KALI
UTUH M3 Rp 202,000
BATU PECAH 5-7 CM M3 Rp 397,800
BATU PECAH 3-5 CM (MANUAL) M3 Rp 345,000
BATU PECAH 3-5 CM (CRUSHER) M3 Rp 345,000
BATU PECAH 2-3 CM (CRUSHER) M3 Rp 373,750
2 BATU GUNUNG M3 Rp 157,500
3 TIMBUNAN PILIHAN M3 Rp 190,000
4 TANAH TIMBUNAN BIASA M3 Rp 100,000
5 TANAH TIMBUNAN HUMUS M3 Rp 172,500
6 PASIR URUG/TIMBUNAN M3 Rp 126,000
7 PASIR PASANGAN M3 Rp 300,000
8 KERIKIL SUNGAI M3 Rp 195,000
9 SIRTU M3 Rp 199,500
10 KAPUR PASANGAN ZAK Rp 89,700
11 SEMEN PORTLAND 40 Kg ZAK Rp 52,900
12 BATU MERAH BH Rp 630
13 BATA RINGAN ex. Citicon M3 Rp 732,850
14 PAVING BLOCK T. 6 CM, MODEL BATA M2 Rp 11,603
15 PAVING BLOCK T. 8 CM M2 Rp 117,000
16 PLASTIK BENING ALAS BETON M2 Rp 10,400
17 GORONG-GORONG DIA.60 CM BH Rp 143,000
18 GORONG-GORONG DIA.80 CM BH Rp 175,500
19 GORONG-GORONG DIA.100 CM BH Rp 273,000
20 GORONG-GORONG DIA.60,TUL 12 MM BH Rp 481,000
21 GORONG-GORONG DIA 80, TUL 12 MM BH Rp 611,000
22 GORONG-GORONG DIA 100,TUL 12 MM BH Rp 741,000
23 KANSTIN BETON Uk. 25 X 15 X 40 Cm BH Rp 15,000
B BAHAN KAYU
1 KAYU KELAS 1
BALOK GERGAJI SWALMIL M3 Rp 14,850,000
PAPAN GERGAJI SWALMIL M3 Rp 18,400,000
BALOK GERGAJI CHANSOW M3 Rp 14,300,000
PAPAN GERGAJI CHANSOW M3 Rp 16,250,000
2 KAYUKELAS 2
BALOK M3 Rp 5,500,000
PAPAN M3 Rp 5,500,000
3 KAYU KELAS 3
BALOK M3 Rp 3,850,000
PAPAN M3 Rp 3,850,000
4 BAMBU BTG Rp 26,250
5 KAYU KELAS 4 M3 Rp 3,600,000
C BAHAN LANTAI
1 TEGEL MOZAIK 30X30 CM DOS Rp 113,100
2 TEGEL KERAMIK
PUTIH 10 X 20 CM DOS Rp 93,600
WARNA 10 X 20 CM DOS Rp 100,100
PUTIH 20 X 20 CM DOS Rp 65,000
WARNA 20 X 20 CM DOS Rp 80,600
PUTIH 20 X 25 CM DOS Rp 65,000
WARNA 20 X 25 CM DOS Rp 80,600
PUTIH 30 X 30 CM DOS Rp 65,000
MOTIF 30 X 30 CM DOS Rp 68,250
PUTIH 40 X 40 CM DOS Rp 70,980
WARNA 40 X 40 CM DOS Rp 84,500
WARNA 60 X 60 CM DOS Rp 234,000
3 GRANIT ESSENZA 30 X 30 DOS Rp 442,000
4 GRANIT ESSENZA 40 X 40 CM DOS Rp 481,000
5 GRANIT ESSENZA 60 X 60 CM, DOS Rp 546,000
6 GRANIT LANTAI GARUDA, MAGIOR GREY DOS Rp 289,800
7 GRANIT LANTAI 60x60 CM SETARA INDOGRESS DOS Rp 456,000
8 GRANIT DINDING 30 X 60 CM, KUALITAS SEDANG DOS Rp 158,700
9 BATU ALAM/BATU CANDI HITAM UK. 15x30 CM M2 Rp 126,360
10 KARPET RUMPUT SINTETIS M2 Rp 280,000
11 MEDIA TANAM PUPUK, TANAH SUBUR KRG Rp 25,300
HARGA
NO JENIS BARANG SAT.
ZONA 1
12 RUMPUT GAJAH MINI (AXONOPUS COMPRESSUS'DWARF') M2 Rp 28,750
D BAHAN KACA
1 KACA BENING 3 MM M2 Rp 156,000
2 KACA BENING 5 MM M2 Rp 200,000
3 KACA BENING 8 MM M2 Rp 232,500
4 KACA BURAM 2 MM M2 Rp 195,000
5 KACA BURAM 3MM M2 Rp 260,000
6 KACA BURAM 5 MM M2 Rp 325,000
7 KACA RYBEN 3 MM M2 Rp 195,000
8 KACA RYBEN 5 MM, HIJAU M2 Rp 220,000
9 KACA PANASAP/TINT GLASS 8 MM, BIRU M2 Rp 262,509
9 KACA TEMPERED 10 MM ASAHIMAS POLOS M2 Rp 777,500
10 KACA TEMPERED 12 MM ASAHIMAS POLOS M2 Rp 965,000
11 GLASS BLOCK BH Rp 32,500
12 KACA NAKO (RANGKA NAKO + TERALI BESI DAUN Rp 22,100
13 LOSTER ANGIN 15/25 BH Rp 26,250
14 LOSTER ANGIN 15/30 BH Rp 22,100
15 LOSTER KARAWANG BH Rp 22,100
16 KARET BANTALAN KACA/RUBBER M2 Rp 123,750
E BAHAN BESI DAN BAJA
1 BESI BETON KG Rp 13,125
2 BESI BETON ULIR KG Rp 16,800
3 PAKU 2-3 CM KG Rp 26,250
4 PAKU 4 CM KG Rp 26,250
5 PAKU 5-10 CM -
6 PAKU ASBES KG Rp 42,000
7 PAKU SENG/ PAKU PAYUNG KG Rp 40,000
8 PAKU SEKRUP 3 MM KG Rp 132,600
9 PAKU SEKRUP 4 MM KG Rp 227,500
10 PAKU PAYUNG BERULIR KG Rp 45,000
11 PAKU SIRAP KG Rp 63,000
12 PAKU BETON PUTIH
1 INCH DOS Rp 19,500
1 1/2 INCH DOS Rp 19,500
1 1/4 INCH DOS Rp 19,500
2 INCH DOS Rp 19,500
3 INCH DOS Rp 26,000
4 INCH DOS Rp 26,000
13 PAKU BETON HITAM
1 INCH DOS Rp 10,500
1 1/4 INCH DOS Rp 10,500
1 1/2 INCH DOS Rp 10,500
2 INCH DOS Rp 10,500
3 INCH DOS Rp 63,000
4 INCH DOS Rp 63,000
14 KAWAT BETON KG Rp 26,250
15 RANG NYAMUK
BIASA M2 Rp 31,500
ALMA M2 Rp 57,750
STAINLESS M2 Rp 157,500
16 RANG AYAKAN KECIL
PVC M2 Rp 21,000
BESI M2 Rp 59,800
17 KAWAT DURI 10 KG ROLL Rp 247,000
18 KAWAT HARMONIKA 3 CM M2 Rp 59,800
19 BESI PLAT 2 MM, 1,2MX2,4M LBR Rp 773,500
20 BESI PLAT 3 MM, 1,2M X 2,4M LBR Rp 1,007,500
21 BESI STREP 3X30MM- 6 M BTG Rp 123,500
22 BESI STREP 4X40 MM, 6 M BTG Rp 156,000
23 BESI STREP 5X30, 6 M BTG Rp 175,500
24 BESI STEP 5X50, 6 M BTG Rp 253,500
25 BESI STREP 6X50, 6M BTG Rp 338,000
26 BESI SIKU 30,30.3 -6 BTG Rp 104,000
27 BESI SIKU 40,40,4 -6 BTG Rp 80,600
28 BESI SIKU 50,50,5 -6 BTG Rp 266,500
29 BESI SIKU 60,60,6 -6 BTG Rp 468,000
30 BESI SIKU 70,70,7 -6 BTG Rp 507,000
31 BESI SIKU 40,40,3 -6 M BTG Rp 78,000
32 BESI SIKU 50,50,4 -6M BTG Rp 132,600
HARGA
NO JENIS BARANG SAT.
ZONA 1
33 BESI BAJA H BEAM 125X125X6,5X9 CM KG Rp 22,100
34 BESI BAJA H BEAM 150X150X7X10 CM KG Rp 20,800
35 BESI BAJA KANAL UNP "U" 6,5X42X5X6M' BTG Rp 370,500
36 BESI BAJA KANAL UNP "U" 70X40X5X6 M' BTG Rp 435,500
37 BESI HOLLOW 40X60. t = 1mm (hitam) 6M Rp 188,500
38 BESI HOLLOW 40X40. t = 1mm (hitam) 6M Rp 130,000
39 besi hollow 20x40 t = 1mm (hitam 6M Rp 104,000
40 besi hollow 20x20 t = 1mm (hitam 6M Rp 71,500
41 BESI HOLLOW 40X60. t = 1mm (GALVANIS) 6M Rp 217,100
42 BESI HOLLOW 40X40. t = 1mm (GALVANIS) 6M Rp 139,100
43 BESI HOLLOW 20X40. t = 1mm (GALVANIS) 6M Rp 113,100
44 BESI HOLLOW 20X20. t = 1mm (GALVANIS) 6M Rp 80,600
45 BAJA TRALIS M2 Rp 577,500
46 KAWAT BRONJONG (PABRIKAN) M3 Rp 467,250
47 BAUT BAJA KG Rp 33,800
48 BESI GALVANISIR KG Rp 33,800
49 PAKU JEMBATAN KG Rp 35,100
50 BESI TEMPA M2 Rp 351,000
51 RANGKA ATAP BAJA RINGAN M2 Rp 85,000
52 BAJA RINGAN (CNP) 75X0,75 M Rp 22,575
53 KUSEN ALUMUNIUM 3", COKELAT M Rp 119,000
53 KUSEN ALUMUNIUM 4", POWDER COATING WARNA PUTIH M Rp 133,200
54 BINGKAI PINTU PROFIL ALUMUNIUM M Rp 169,400
55 BINGKAI JENDELA PROFIL ALUMUNIUM M Rp 126,500
56 SEALANT / LEM KACA TUBE Rp 12,050
57 Reng Galvalum 35 X 40 Mm - 6M BATANG Rp 43,000
58 Floordeck/Bondek galvanis T=0,75, L= 1 m M2 Rp 143,000
59 WIREMESH M10 2,1 x 5,4 m LEMBAR Rp 968,000
60 WIREMESH M8 2,1 x 5,4 m LEMBAR Rp 569,800
61 BESI BAJA IWF 150.75.7.5 KG Rp 20,800
F BAHAN PIPA
I PIPA PVC AW
1 DIAMETER 1/2 METER Rp 7,239
2 DIAMETER 3/4 METER Rp 9,561
3 DIAMETER 1 METER Rp 15,365
4 DIAMETER 1 1/4 METER Rp 18,438
5 DIAMETER 1 1/2 METER Rp 20,965
6 DIAMETER 2 METER Rp 24,072
7 DIAMETER 2 1/2 METER Rp 26,224
8 DIAMETER 3 METER Rp 33,121
9 DIAMATER 4 METER Rp 41,844
10 DIAMETER 6 METER Rp 99,000
11 DIAMETER 8 METER Rp 170,727
12 DIAMETER 10 METER Rp 261,826
13 DIAMETER 12 METER Rp 375,598
BAHAN PLAFON DAN PARTISI 𝜃
1 ETERNIT 100 X 100 X0,2 LBR Rp 35,000
2 TRIPLEKS
122X 244 X 0,2 CM LBR Rp 50,700
122X 244 X 0,3 CM LBR Rp 68,900
122X 244 X 0,6 CM LBR Rp 100,100
122X 244 X 0,9 CM LBR Rp 143,000
122X 244 X 1,8 CM LBR Rp 364,000
3 TRIPLEKS MELAMIN
122X 244 X 0,2 CM LBR Rp 130,000
122X 266 X 0,3 CM LBR Rp 149,500
4 ACUSTIC 40 X 60 LBR Rp 58,500
5 TEAKWOOD
122X 244 X 0,3 CM LBR Rp 149,500
80 X 244 X 0,3 CM LBR Rp 78,000
6 HARD BOARD 122X244 CM 18 MM LBR Rp 325,000
7 ASBES PLAT HARFLEX 200 X100 CM LBR Rp 117,000
8 GIPSUM BOARD
240 X 120 X 0,3 CM LBR Rp 91,000
240 X 120 X 0,4 CM LBR Rp 93,600
240 X 120 X 0,9 CM LBR Rp 100,100
9 LIST PROFIL KAYU
2 X 3 CM BTG/4M Rp 13,000
3 X 3 CM BTG/4M Rp 14,300
HARGA
NO JENIS BARANG SAT.
ZONA 1
4 X 4 CM BTG/4M Rp 20,800
4X 5 CM BTG/4M Rp 35,100
LIST PROFIL GYPSUM
7 ̸ 7 M' Rp 28,600
7 ̸ 10 M' Rp 23,400
7 ̸ 16 M' Rp 26,000
13 ̸ 15 M' Rp 28,600
LIST PVC
58 X 32 MM BTG/2M' Rp 33,800
32 X 32 MM BTG/2M' Rp 27,300
26 X 30 MM BTG/2M' Rp 22,100
10 LAMBRISERING BTG/2M' Rp 351,000
11 PLAFON DAN PARTISI PVC
TEBAL 1 CM LBR Rp 286,000
TEBAL 0,8 CM LBR Rp 234,000
LIST SAMPING 4M Rp 130,000
LIST SAMBUNGAN 4M Rp 130,000
12 GRC t= 0,6 MM(1,20 X 2,40) LBR Rp 195,000
13 KALSIBOARD
0,35 MM X 1,2 X 2,4 LBR Rp 91,000
6 MM X 1,24 X 2,4 LBR Rp 188,500
9 MM X 1,24 X 2,4 LBR Rp 240,500
KALSIBOARD POLOS (0,8MM X 0,3 X 3) LBR Rp 97,500
KALSIBOARD POLOS (0,8MM X 0,2 X 3) LBR Rp 69,000
KALSIPLANK JATI (0,8 MM X O,3 X 3) LBR Rp 100,750
BAJA RINGAN 4 METER
2X4X0,25 BTG Rp 23,400
4X4X0,30 BTG Rp 29,900
2X4X0,25 BTG Rp 27,300
4X4X0,30 BTG Rp 35,100
Metal stud galvalume profil 75x50x8 t: 0,4, panjang 4 m Btg Rp 44,275
Metal stud galvalume U runner 76x35x35 t: 0,4, panjang 2,5 m Btg Rp 36,800
H BAHAN ATAP
1 GENTENG
TANAH LIAT BH Rp 5,200
BETON BH Rp 14,300
KERAMIK BH Rp 16,900
ASBES PLAT HARFLEX 200 X100 CM LBR Rp 65,000
HARFLEX (115X85X0,5) LBR Rp 58,500
2 ASBES GELOMBANG KAKI Rp 14,300
3 SIRAP LBR Rp 145,600
4 SENG GELOMBANG
BWG 34" BJLS 0,20 MM KAKI Rp 10,400
BWG 32" BJLS 0,30 MM KAKI Rp 15,600
BWG 28" BJLS 0,35 MM KAKI Rp 16,900
5 SENG PLAT BJLS GALVANIS
BJLS 0,4 MM 1,219 X 1 M M' Rp 188,500
BJLS 0,5 MM 1,219 X 1 M M' Rp 96,233
BJLS 0,6 MM 1,219 X 1 M M' Rp 110,670
BJLS 0,7 MM 1,219 X 1 M M' Rp 127,260
6 POLYCARBONATE M2 Rp 136,500
7 ATAP FIBER M2 Rp 52,000
8 BITUMEN BERGELOMBANG MONOLAYER 3mm - DURO 235 Lembar Rp 141,000
9 NOK/RIDGE EX. ONDULINE Lembar Rp 85,000
10 NOK BUBUNGAN
GENTENG BETON BH Rp 36,400
GENTENG ASBES BH Rp 44,200
GENTENG KERAMIK BH Rp 59,800
NOK ZINCALUM BH Rp 62,400
11 KARET PELAPIS GENTENG 55 CM X 30 M ROLL Rp 513,500
12 LIST PLANK SEJENIS WOOD PLANK
POLOS 4M Rp 66,300
MOTIF
0,2M X 4 M BTG Rp 100,100
0,3M X 4 M BTG Rp 132,600
13 ATAP ZINCALUME T = 0,30 mm M2 Rp 59,800
I BAHAN PENGGANTUNG
1 KUNCI TANAM
UNION 1 X SLAG BH Rp 120,750
HARGA
NO JENIS BARANG SAT.
ZONA 1
UNION 2 X SLAG BH Rp 157,500
YALE 1 X SLAG BH Rp 105,000
YALE 2 X SLAG BH Rp 131,250
KUDA TERBANG BH Rp 100,100
2 PENGGANTUNG
HAK ANGIN KECIL BH Rp 22,100
HAK ANGIN BESAR BH Rp 35,100
GRENDEL KECIL BH Rp 10,500
GRENDEL BESAR BH Rp 36,750
ENGSEL PINTU PSG Rp 36,750
ENGSEL JENDELA PSG Rp 10,500
EXPANYOLET BH Rp 91,000
3 DOOR CLOSER BH Rp 246,750
4 DOOR STOPPER BH Rp 84,000
5 ENGSEL CASEMENT 10" BH Rp 50,000
6 RAMBUNCIS/KUNCI JENDELA BH Rp 31,250
7 FLOOR HINGE, EX DORMA BH Rp 1,980,000
8 PATCH FITTING SET SET Rp 1,035,000
9 PATCH + LOCK CYLINDER EX. DORMA BH Rp 780,000
10 PULL HANDLE P: 120 CM, STAINLESS STELL PSG Rp 619,850
11 PULL HANDLE P: 30 CM, STAINLESS STELL PSG Rp 176,000

J BAHAN SANITER
1 SAMB. PDAM UNIT Rp 2,600,000
2 CLOSET DUDUK KIA (LENGKAP) SET Rp 3,005,860
3 CLOSET DUDUK AMERICAN STANDAR KUALITAS SEDANG (LENGKAP) SET Rp 2,972,750
4 CLOSET DUDUK TOTO SET Rp 3,223,500
5 CLOSET JONGKOK BH Rp 420,000
6 WASTAFEL KUALITAS SEDANG + AKSESORI BH Rp 977,500
7 WASTAFEL TOTO tipe LW 247 CJ (LENGKAP) BH Rp 2,450,000
8 SINK CUCI PIRING LOGAM 1 MATA BH Rp 313,766
9 POMPA TANGAN TERPASANG BH Rp 664,950
10 URINIOR SEJENISN TT BH Rp 3,692,260
11 BSK MANDI FIBER BH Rp 469,040
12 TANGKI AIR FIBER 1000 LITER BH Rp 1,250,000
13 TANGKI AIR FIBER 500 LITER BH Rp 850,000
14 RESORVOIR FIBER 3 M3 BH Rp -
15 KERAN WASTAFHEL STAINLESS BH Rp 124,410
16 KERAN URINOIR BH Rp 178,750
17 FLOORDRAIN KUALITAS SEDANG BH Rp 65,000
18 FLOORDRAIN PLASTIK BH Rp 41,500
19 SOAP HOLDER BH Rp 74,360
20 KITCHEN SET M' Rp 1,644,500
21 KRAN AIR 1/2 BH Rp 20,658
22 KUSEN PINTU FIBER + DAUN PINTU UNIT Rp 472,500
BAHAN FINISHING
1 CAT DASAR/ALKALI KG Rp 27,650
2 CAT TEMBOK SEJENIS VINILEX KG Rp 56,250
3 CAT TEMBOK SEJENIS NIPPON PAINT SPOTLESS INTERIOR KG Rp 81,250
4 CAT TEMBOK SEJENIS MOWILEX EXTERIOR KG Rp 96,000
5 CAT PLAFON ACRYLIC EMULSION KG Rp 78,000
6 CAT KAYU (GLOTEX) KG Rp 67,850
7 CAT ATAP (NO DROP) KG Rp 69,000
8 CAT BESI (AVIAN) KG Rp 68,250
9 CAT CLEAR NATURAL BATU ALAM, EX. PROPAN STONE CARE KG Rp 95,700
10 LEM PEREKAT KG Rp 71,500
11 HPL MOTIF LBR Rp 247,000
12 EDGING/TEPI PVC L:42 MM M Rp 9,750
13 PARKET M2 Rp 613,600
14 PLINT PARKET M Rp 293,800
15 PLAMUR TEMBOK ZAK Rp 71,500
16 CAT DASAR (MENI KAYU) KG Rp 49,450
17 CAT JEMBATAN KG Rp 99,750
18 MINYAK CAT LTR Rp 49,400
19 MINYAK FLUX LTR Rp 13,000
20 PELUMAS LTR Rp 39,000
21 WALLPAPER DINDING BAHAN VINYL L:53cm, KUALITAS IMPORT ROL Rp 90,000
22 SOLAR LTR Rp 7,085
23 BENSIN LTR Rp 8,385
HARGA
NO JENIS BARANG SAT.
ZONA 1
24 POLITUR KG Rp 78,750
25 DEMPUL KAYU KG Rp 40,250
26 KERTAS GOSOK (AMPLAS) LBR Rp 11,500
27 RESIDU LTR/KG Rp 52,500
28 OKAR KG Rp 55,200
29 SPRITUS LTR Rp 26,000
30 ASPAL CAIR KG Rp 17,420
31 ASPAL BUTON TON Rp 17,550,000
II BAHAN INSTALASI LISTRIK
1 PENG.SAMB LISTRIK KWH 1300 UNIT Rp 4,500,000
2 BOX PANEL PVC ISI 4 MCB BH Rp 67,600
3 MCB 20A ex. Schneider BH Rp 227,700
4 MCB 4A BH Rp 80,600
5 KABEL NYM 2 X 2,5 MM2 M Rp 18,200
6 KABEL NYM 3 X 2,5 MM2 M Rp 12,000
7 KABEL TELEPHONE 4X0,5 M Rp 7,800
8 ISOLASI BH Rp 9,100
9 SAKLAR TUNGGAL BH Rp 22,100
10 SAKLAR GANDA BH Rp 38,350
11 STOP KONTAK BH Rp 51,350
12 STOP KONTAK AC BH Rp 66,950
13 OUTLET TV BH Rp 38,350
14 OUTLET TELEPHONE BH Rp 48,750
15 DOWNLIGHT / PLC 13 WATT BH Rp 54,600
16 FITTING PLAFON + LAMPU BH Rp 10,000
17 LAMPU PLC 23 WATT BH Rp 43,200
18 LAMPU PLC 8 WATT BH Rp 36,000
19 LAMPU TL 2 X 18 WATT GRILLE SET Rp 301,600
20 LAMPU TL 2 X 36 WATT GRILLE SET Rp 490,100
21 Panasonic FV15TGU1W Exhaust Fan BH Rp 338,000
22 AC Split 1/2 pk ex. LG Dual Cool Eco T06EV4 SET Rp 4,100,000
23 AC Split 3/4 pk ex. LG Dual Cool Eco T13EV4 SET Rp 5,700,000
24 AC Split 1 pk ex. LG Dual Cool Deluxe P10RIV3 SET Rp 7,300,000
III UPAH KERJA
1 ~PEKERJA HARI Rp 95,000
2 TUKANG
TUKANG KAYU HARI Rp 135,000
TUKANG BATU HARI Rp 135,000
TUKANG CAT HARI Rp 135,000
TUKANG LISTRIK HARI Rp 160,000
TUKANG PIPA HARI Rp 135,000
TUKANG BESI HARI Rp 135,000
TUKANG LAS HARI Rp 135,000
TUKANG LANDSCAPING HARI Rp 135,000
TUKANG PROFIL HARI Rp 160,000
3 KEPALA TUKANG
KEPALA TUKANG KAYU HARI Rp 150,000
KEPALA TUKANG BATU HARI Rp 150,000
KEPALA TUKANG CAT HARI Rp 150,000
KEPALA TUKANG LISTRIK HARI Rp 185,000
KEPALA TUKANG PIPA HARI Rp 150,000
KEPALA TUKANG BESI HARI Rp 150,000
KEPALA TUKANG LAS HARI Rp 150,000
KEPALA TUKANG LANDSCAPING HARI Rp 150,000
KEPALA TUKANG PROFIL HARI Rp 185,000
4 MANDOR HARI Rp 165,000
5 MASINIS HARI Rp 130,000
6 PEMBANTU MASINIS HARI Rp 114,400
7 PENJAGA GUDANG HARI Rp 117,000
8 PENJAGA MALAM HARI Rp 117,000

Anda mungkin juga menyukai