1.

SALURAN = 547M3 SALURAN


2.CASTIN = 136M3 KANSTEEN
3.TROTOAR = 264M3 TROTOAR
4.TUTUP SALURAN = 91M3 TUTUP SALURAN
5.BAK CONTROL = 82M3 BAK KONTROL
6.PONDASI PJU = 13M3 PONDASI PJU
TOTAL KEBUTUHAN BETON = 1133M3 RIGID
KEBUTUHAN MATERIAL BASE A
1.SEMEN = 6780 SAK BASE B
2.PASIR = 452 M3 LANTAI KERJA JLN
3.KORAL =678 M3
28,382 4.BESI = 3942 BTG (D10 )
SEMEN
BISA DI SELESAIKAN SAMPE 3BULAN 7 HARI PASIR
1130M3/10M3 = 113HARI KORAL
113HARI /30 HARI = 3 BULAN 7 HARI BESI

Kebutuhan material jalan kita


1.Bes B = 4104m3
2.Bes A = 2736m3
3.Lantai kerja jalan = 684m3
4.Rijit beton = 2736m3
547 M³
136 M³
264 M³
1133
91 M³
82 M³
13 M³
2736 M³
4104 M³
2736 M³
648 M³
4517 M³