PEKERJAAN : PEMINDAHAN COOLING TOWER AREA

LOKASI : PT. QUANTUM LABORATORIS INTERNASIONAL


: PANDAAN - PASURUAN
PROGRESS : 60%
TIME SCHEDULE

NO URAIAN
BOBOT Jan-22 Feb-22
% 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
I PEKERJAAN PERSIAPAN

1 Pengukuran / Bowplank 0,829 0,414 0,41


2 Listrik dan air kerja 1,159 0,12 0,7 0,348
II PEKERJAAN BONGKARAN
1 Bongkar Badukan beton existing 0,745 0,447 0,3
2 Bongkar atap spandek 0,983 0,59 0,393
3 Bongkar kolom UNP 100 doble 0,331 0,331
4 Bongkar kuda2 CNP 120 0,166 0,166
5 Bongkar gording CNP 120 0,414 0,414
III PEKERJAAN PASANG KEMBALI
1 Pasang atap spandek 2,388
2 Pasang kuda2 CNP 120 0,331
3 Pasang gording CNP 120 0,828
IV PEKERJAAN SIPIL
1 Galian Pondasi foot plate 50x50x20 0,097 0,097
2 Urugan kembali pondasi 0,048 0,048
3 Sloof beton 20x15 0,743 0,37 0,37
4 Dinding beton T=20 5,208 1,04 1,562 2,083 0,521
5 Lantai beton T=20 3,824 1,912 1,912
6 Pasangan keramik 20x20 2,185 RENCANA
7 Plester + Aci 0,872
REALISASI
8 Pedestal 25x25 1,614 0,646 0,97
9 Pasangan angkur 1,987 1,987
V PEKERJAAN BAJA
1 Kolom atap UNP 100 doble 7,496
2 Kolom platform WF 150 3,148 3,148
3 Balok platform WF 150 9,813 3,93 4,906 0,981
4 Balok platform WF 100 10,495 3,673 3,673 3,15
5 Balok platform siku 5x5 0,911 0,911
6 Bordes 2 mm 6,755 2,03 4,728
7 Tangga monyet besi Φ1" 1,159
8 Relling platform besi Φ3/4" 10,031
VI PEKERJAAN FINISHING
1 Pekerjaan cat besi 1,407 1,407
VII PEKERJAAN LAIN-LAIN
1 Pekerjaan drain pipa Φ1" dan valve 0,179
2 Pembersihan akhir 0,993
VIII MEKANIKAL
1 Pemindahan COOLING TOWER & POMPA 10,099 2,02 2,02
2 Bongkar & Instalasi ulang pompa 12,764 2,55 3,957
PROGRESS RENCANA 0,829 1,043 1,254 1,500 1,669 2,344 3,039 3,346 3,397 3,698 3,757 4,123 4,138 4,203 4,219 5,798 5,772 4,174 4,053 3,978 3,812 3,812 3,686 3,636 3,535 3,445 2,298 2,298 2,170 2,042 1,915 1,021
KOMULATIF PROGRESS RENCANA 0,829 1,87 3,13 4,63 6,29 8,64 11,68 15,02 18,42 22,12 25,88 30,00 34,14 38,34 42,56 48,36 54,13 58,30 62,36 66,33 70,14 73,96 77,64 81,28 84,81 88,26 90,55 92,85 95,02 97,06 98,98 100,00
PROGRESS REALISASI 0,000 0,000 0,000 0,000 0,000 0,000 0,414 0,530 0,695 0,795 0,888 0,890 0,930 1,413 1,562 2,083 2,433 2,558 2,955 3,148 3,925 4,906 4,654 3,673 3,148 2,937 4,728 3,427 2,020 2,553 3,957 0,000
KOMULATIF PROGRESS REALISASI 0,000 0,00 0,00 0,00 0,00 0,00 0,41 0,94 1,64 2,43 3,32 4,21 5,14 6,56 8,12 10,20 12,63 15,19 18,15 21,30 25,22 30,13 34,78 38,45 41,60 44,54 49,27 52,69 54,71 57,27 61,22 61,22

DIBUAT OLEH DISETUJUI OLEH

RIZKY FERDIAN TOPAN ABRI SIGIT WARI SUSILO DAMARIS H


PENANGGUNG JAWAB TEKNIS PROJECT CONTROLLER PLAN DIRECTOR