Kontraktor :
Konsultan :
:
Lokasi :
Pekerjaan : LANTAI KERJA
Mutu Rencana : FC 10
Σ 38.76 Σ 2.69
= 1.16 Mpa
= 11.57 Mpa
= 21.60 Mpa
= 1.83 Mpa
= 19.47 Mpa
= 25.44 Mpa
= 5.49 Mpa
= 19.07 Mpa