ANALISIS HARGA SATUAN

I. PASANGAN BATU
A. BAHAN BANGUNAN
Batu belah 1.200 180,000 216,000
Pasir pasang 0.520 185,000 96,200
Semen 202.000 1,300 262,600
Jumlah = 574,800

B. UPAH KERJA
Pekerja 1.5000 90,000 135,000
Tukang batu 0.7500 100,000 75,000
Mandor 0.0750 120,000 9,000
Kepala tukang 0.0750 150,000 11,250
Jumlah = 230,250

Total / m3 = 805,050

2. PLESTERAN DAN ACIAN


A. BAHAN BANGUNAN
Semen 3.936 1,300 5,117
Pasir pasang 0.028 185,000 5,180
Jumlah = 10,297

B. UPAH KERJA
Pekerja 0.300 90,000 27,000
Tukang batu 0.150 100,000 15,000
Mandor 0.015 120,000 1,800
Kepala tukang 0.015 150,000 2,250
Jumlah = 46,050

Total / m2 = 56,347
Saluran Dalam 223.50 145.275 805,000 116,946,375.00
Saluran Jalan 70.00 1,120.00 78,400
Tembok Tebing 51.00 1,300.00 66,300
Jalan 145.00