SCHEDULE PEMASANGAN DAN PERKUATAN ACP

ID Task Task Name Duration Start Finish 21 Nov '21 28 Nov '21 05 Dec '21 12 Dec '21 19 Dec '21 26 Dec '21
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 PEKERJAAN PERKUATAN DAN PEMASANGAN KEMBALI ACP 32 days 25/11/2021 26/12/2021
2 Pemasangan dan Pembentangan Jaring Hiu 1 day 26/11/2021 26/11/2021
3 Pembongkaran ACP (16 Keping) 4 days 25/11/2021 28/11/2021
4 Pemasangan Hollow Baja disiku ACP 4 days 29/11/2021 02/12/2021
5 Perbaikan Rangka ACP 7 days 13/12/2021 19/12/2021
6 Pemasangan Kembali ACP 7 days 20/12/2021 26/12/2021
7 PEKERJAAN PERBAIKAN DAN PENEBALAN KOLOM 12 days 01/12/2021 12/12/2021
8 Perbaikan Retakan dan Penebalan Kolom (LT5 - RF1) 4 days 01/12/2021 04/12/2021
9 Pemasangan Chemical angkur Jarak 60cm d10 ( LT5-RF1) 4 days 05/12/2021 08/12/2021
10 Pemasangan Hollow Baja dikolom 6 days 07/12/2021 12/12/2021

Task Project Summary Manual Task Start-only Deadline

Project: DATA CENTER KUNING Split Inactive Task Duration-only Finish-only Progress
Date: 27 NOVEMBER 2021 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone