ID Task Task Name Duration Start Finish 21 Nov '21 28 Nov '21 05 Dec '21 12 Dec '21 19 Dec '21 26 Dec '21
Mode T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 PEKERJAAN PERKUATAN DAN PEMASANGAN KEMBALI ACP 32 days 25/11/2021 26/12/2021
2 Pemasangan dan Pembentangan Jaring Hiu 1 day 26/11/2021 26/11/2021
3 Pembongkaran ACP (16 Keping) 4 days 25/11/2021 28/11/2021
4 Pemasangan Hollow Baja disiku ACP 4 days 29/11/2021 02/12/2021
5 Perbaikan Rangka ACP 7 days 13/12/2021 19/12/2021
6 Pemasangan Kembali ACP 7 days 20/12/2021 26/12/2021
7 PEKERJAAN PERBAIKAN DAN PENEBALAN KOLOM 12 days 01/12/2021 12/12/2021
8 Perbaikan Retakan dan Penebalan Kolom (LT5 - RF1) 4 days 01/12/2021 04/12/2021
9 Pemasangan Chemical angkur Jarak 60cm d10 ( LT5-RF1) 4 days 05/12/2021 08/12/2021
10 Pemasangan Hollow Baja dikolom 6 days 07/12/2021 12/12/2021
Project: DATA CENTER KUNING Split Inactive Task Duration-only Finish-only Progress
Date: 27 NOVEMBER 2021 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress