1 Standby Piket
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Sabtu
TANGGAL : 01-Juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Minggu
TANGGAL : 02-Juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Senin
TANGGAL : 03-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Selasa
TANGGAL : 04-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Rabu
TANGGAL : 05-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Kamis
TANGGAL : 06-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Jumat
TANGGAL : 07-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Sabtu
TANGGAL : 08-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN
NO KONTRAK/SPK : 29/SPPPP/STADION MANAHAN/ADHI-PENTA/II/2019
NAMA PROYEK : PROYEK RENOVASI DAN PENGEMBANGAN STADION MANAHAN SURAKARTA
LOKASI : SOLO
PAKET PEKERJAAN : PEKERJAAN PENGADAAN DAN PEMASANGAN FOP LIGHTING
1 Standby Piket 1 1
CUACA
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
PEKERJA 15
16
NO POSISI QTY UNIT Location 17
18
19
1 Project Manager' 0 Orng Manahan
20
21
2 Drafter 0 Orng Manahan
22
23
3 Supervisor 0 Orng Manahan
24
LEGEND
4 Admin 0 Orng Manahan
CERAH
5 HSE 1 Orng Manahan
PERMASALAHAN PROJECT
TANGGAL:
NO
HARI : Minggu
TANGGAL : 09-juni-19
BEKERJA
WAKTU KONDISI
YA TIDAK
06.00
07.00
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
01.00
02.00
03.00
04.00
05.00
BERAWAN HUJAN
PERMASALAHAN PROJECT
URAIAN PEKERJAAN
......................................
PEKERJAAN
NAMA PEKERJAAN
NAMA PEKERJAAN