Anda di halaman 1dari 73

Disetujui Oleh :

SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO


Koordinator Pengawas Lapangan

FRIYANTO DAUD,ST
NIP : 19821006 201001 1 003

Diperiksa Oleh :
KONSULTAN SUPERVISI
PT. Yodya Karya (Persero)

FAIZAL MAKMUR, ST
Chief Inspector / Quantity Engineer

Diajukan Oleh :
KONTRAKTOR PELAKSANA
PT. Karunia Jaya Sejati

CHRISTIAN IVAN LEWA, ST


General Superintendent

Gunawan
Santoso,S
T

KONTRAKTOR PT. Karunia Jaya Sejati


KONSULTAN SUPEPT. Yodya Karya (Persero)
PAKET Pelebaran Jalan Isimu-Paguyaman (Rigit Pavement) III
JENIS PEKERJAAN
NO. PAY ITEM
ESTIMASI VOLUME
LOKASI KERJA
NO. KONTRAK HK0203/PJNPG-PPK04/541
17 Pebruari 2014
tanggal minggu bulan bobot rencana
20 Feb' s/d 23 Feb' 2014 1 Februari 2014 -
24 Feb' s/d 02 Mar' 2014 2 Maret 2014 0.041
03 Mar' s/d 09 Mar' 2014 3 Maret 2014 0.084
10 Mar' s/d 16 Mar' 2014 4 Maret 2014 0.169
17 Mar' s/d 23 Mar' 2014 5 Maret 2014 1.635
24 Mar' s/d 30 Mar' 2014 6 Maret 2014 4.537
31 Mar' s/d 06 Apr' 2014 7 April 2014 7.652
07 Apr' s/d 13 Apr' 2014 8 April 2014 12.460
14 Apr' s/d 20 Apr' 2014 9 April 2014 18.523
21 Apr' s/d 27 Apr' 2014 10 April 2014 23.067
28 Apr' s/d 04 Mei 2014 11 Mei 2014 28.471
05 Mei s/d 11 Mei 2014 12 Mei 2014 33.874
12 Mei s/d 18 Mei 2014 13 Mei 2014 38.523
19 Mei s/d 25 Mei 2014 14 Mei 2014 43.172
26 Mei s/d 01 Jun' 2014 15 Juni 2014 47.820
20 Jun' s/d 08 Jun' 2014 16 Juni 2014 50.992
09 Jun' s/d 15 Jun' 2014 17 Juni 2014 54.164
16 Jun' s/d 22 Jun' 2014 18 Juni 2014 57.336
23 Jun' s/d 29 Jun' 2014 19 Juni 2014 60.507
30 Jun' s/d 06 Jul' 2014 20 Juli 2014 63.679
07 Jul' s/d 13 Jul' 2014 21 Juli 2014 66.851
14 Jul' s/d 20 Jul' 2014 22 Juli 2014 70.129
21 Jul' s/d 27 Jul' 2014 23 Juli 2014 73.010
28 Jul' s/d 03 Agt' 2014 24 Agustus 2014 75.890
04 Agt' s/d 10 Agt' 2014 25 Agustus 2014 78.771
11 Agt' s/d 17 Agt' 2014 26 Agustus 2014 81.651
18 Agt' s/d 24 Agt' 2014 27 Agustus 2014 84.531
25 Agt' s/d 31 Agt' 2014 28 Agustus 2014 87.412
01 Sep' s/d 07 Sep' 2014 29 September 2014 90.292
08 Sep' s/d 14 Sep' 2014 30 September 2014 92.012
15 Sep' s/d 21 Sep' 2014 31 September 2014 93.957
22 Sep' s/d 28 Sep' 2014 32 September 2014 95.900
29 Sep' s/d 05 Okt' 2014 33 Oktober 2014 97.844
06 Okt' s/d 12 Okt' 2014 34 Oktober 2014 98.179
13 Okt' s/d 19 Okt' 2014 35 Oktober 2014 99.106
20 Okt' s/d 26 Okt' 2014 36 Oktober 2014 99.961
27 Okt' s/d 02 Nov' 2014 37 November 2014 100.00
03 Nov'' s/d 09 Nov' 2014 38 November 2014
10 Nov'' s/d 16 Nov' 2014 39 November 2014

PT. KARUNIA JAYA SEJATI


RIGID PAVEMENT III
Fandi
Yoni
Hengki
Doni
Anto
Bass
Gunawan Santoso, ST. Bazz
tanggal bulan ke
1 Minggu 1 20 Feb' s/d 23 Feb' 2014 Februari 2014 1
2 Minggu 2 24 Feb' s/d 30 Mar' 2014 Maret 2014 2
2 Minggu 3 31 Mar' s/d 27 Apr' 2014 April 2014 3
2 Minggu 4 28 Apr' s/d 25 Mei 2014 Mei 2014 4
2 Minggu 5 26 Mei s/d 29 Jun' 2014 Juni 2014 5
2 Minggu 6 30 Jun' s/d 27 Jul' 2014 Juli 2014 6
3 Minggu 7 28 Jul' s/d 31 Agt' 2014 Agustus 2014 7
3 Minggu 8 01 Sep' s/d 28 Sep' 2014 September 2014 8
3 Minggu 9 29 Sep' s/d 26 Okt' 2014 Oktober 2014 9
3 Minggu 10 27 Okt' s/d 16 Nov' 2014 November 2014 10
4 Minggu 11
4 Minggu 12
4 Minggu 13
4 Minggu 14
5 Minggu 15
5 Minggu 16
5 Minggu 17
5 Minggu 18
5 Minggu 19
6 Minggu 20
6 Minggu 21
6 Minggu 22
6 Minggu 23
7 Minggu 24
7 Minggu 25
7 Minggu 26
7 Minggu 27
7 Minggu 28
8 Minggu 29
8 Minggu 30
8 Minggu 31
8 Minggu 32
9 Minggu 33
9 Minggu 34
9 Minggu 35
9 Minggu 36
10 Minggu 37
10 Minggu 38
10 Minggu 39

Exza GE-2
Exza AE-3
Exza GE-1
Greder AG-2
Vibro KSP-1
LC
K_350
bobot rencana/bulan
-
4.537
23.067
43.172
60.507
73.010
87.412
95.900
99.961
100.000
KEMENTERIAN PEKERJAAN UMUM
Direktorat Jenderal Bina Marga
Balai Pelaksanaan Jalan Nasional XI - Manado
Satuan Kerja Pelaksanaan Jalan nasional Prov Gorontalo PT. Karunia Jaya Sejati
Jl.Tinaloga Desa Permata Ke. Tilongkabila Kab.Bone Bolango Prov Gorontalo Telp. (0435)823900

Kontraktor : PT. Karunia Jaya Sejati

No. Kontrak : HK0203/PJNPG-PPK04/541

Tgl. Kontrak : 17 Pebruari 2014

Konsultan : PT. Yodya Karya (Persero)

Laporan Cuaca

Paket :
Pelebaran Jalan Isimu-Paguyaman (Rigit Pavement) III
Kontraktor : PT. Karunia Jaya Sejati
Kegiatan
No. Kontrak : HK0203/PJNPG-PPK04/541
Tanggal Kontrak : 17 Februari 2014
Nama Paket
Nilai Kontrak : Rp. 28.369.000.000,00
No. SPMK : 597 /SPMK/PJNPG-PPK04
Tanggal SPMK : 20 Februari 2014

Februari Maret
NO. Volume Harga Satuan BOBOT RENC. 20/02/14 24/02/14 03/03/14 10/03/14
URAIAN Sat Jumlah Harga (Rp)
DIVISI Kontrak (Rp) PEK. (%) REAL. s/d s/d s/d s/d
23/02/14 02/03/14 09/03/14 16/03/14
MG. 1 MG. 2 MG. 3 MG. 4
1 UMUM 72,520,237.50 0.28
RENC. 0.041 0.041 0.041
1.2 Mobilisasi 1.00 LS 60,180,000.00 60,180,000.00 0.23
REAL. - 0.041 0.041 0.041
RENC. 0.001
1.8 Manajemen Keselamatan Lalu Lintas 1.00 LS 12,340,237.50 12,340,237.50 0.05
REAL. - - - -

3 PEKERJAAN TANAH 2,123,980,168.01 8.24


RENC.
3.1(1a) Galian Biasa 32,838.83 M3 47,421.10 1,557,253,441.31 6.04
REAL. - - - -
RENC.
3.1(1a) Galian Cadas Muda 69.82 53,296.66 3,721,172.80 0.01
REAL. - - - -
Galian Perkerasan Beraspal Tanpa Cold RENC.
3.1 (7) 1,820.95 M3 62,654.37 114,090,475.05 0.44
Milling Machine REAL. - - - -
RENC.
3.2. (1) Timbunan Biasa 3,748.68 M 3
102,757.81 385,206,147.19 1.49
REAL. - - - -
RENC. 0.041
3.3 (1) Penyiapan Badan Jalan 11,567.50 M2 5,507.58 63,708,931.65 0.25
REAL. - - - 0.041

4 PELEBARAN PERKERASAN DAN BAHU JALAN 462,810,379.82 1.79


RENC.
4.2(2b) Lapis Pondasi Agregat Klas S 1,384.80 M3 334,207.38 462,810,379.82 1.79
REAL. - - - -
5 PERKERASAN BERBUTIR 21,151,215,826.92 82.01
RENC.
5.1(2) Lapis Pondasi Agregat Klas B 2,436.00 M3 392,761.56 956,767,160.16 3.71
REAL. - - - -
RENC.
5.3(1) Perkerasan Beton Semen 8,746.92 M3 1,960,373.00 17,147,225,801.16 66.49
REAL. - - - -
RENC.
5.3(3) Lapis Pondasi Bawah Beton Kurus 3,239.60 M3 940,617.01 3,047,222,865.60 11.82
REAL. - - - -

7 STRUKTUR 1,539,751,101.91 5.97


RENC.
7.9.1 Pasangan Batu 2,581.89 M3 596,365.88 1,539,751,101.91 5.97
REAL. - - - -

8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 421,224,494.64 1.63


RENC.
8.4(1) Marka Jalan Thermoplastic 1,458.72 M2 288,763.09 421,224,494.64 1.63
REAL. - - - -

10 PEKERJAAN PEMELIHARAAN RUTIN 18,500,000.00 0.07


Pemeliharaan Rutin Selokan, Saluran Air, RENC. 0.001 0.001
10.1(3) 1.00 LS 7,500,000.00 7,500,000.00 0.03
Galian dan Timbunan REAL. - - - 0.001
RENC. 0.001 0.001
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan 1.00 LS 5,000,000.00 5,000,000.00 0.02
REAL. - - - -
RENC. 0.001 0.001
10.1(5) Pemeliharaan Rutin Jembatan 1.00 LS 6,000,000.00 6,000,000.00 0.02
REAL. - - - -

A. Jumlah 25,790,002,208.80 100.00


Komulatif Progres Rencana Awal (%) - 0.042 0.086 0.734
B. Progres Rencana Percepatan (%) - 0.041 0.043 0.085
C. Kumulatif Progres Rencana Percepatan (%) - 0.041 0.084 0.169
D. Progres Realisasi (%) - 0.041 0.041 0.083
E. Kumulatif Progres Realisasi (%) - 0.041 0.082 0.164
F. Deviasi Progres Pekerjaan (%) - - -0.002 -0.005
JADWAL PELAKSANAAN PEKERJAAN
Kegiatan : PPK 04 (Limboto - Isimu - Paguyaman - Kwandang - Tolango - Paguyaman - Akses Bandara)

Nama Paket : Pelebaran Jalan Isimu - Paguyaman (Rigid Pavement) III

BULAN
Maret April Mei Juni Juli
17/03/14 24/03/14 31/03/14 07/04/14 14/04/14 21/04/14 28/04/14 05/05/14 12/05/14 19/05/14 26/05/14 02/06/14 09/06/14 16/06/14 23/06/14 30/06/14 07/07/14 14/07/14
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
23/03/14 30/03/14 06/04/14 13/04/14 20/04/14 27/04/14 04/05/14 11/05/14 18/05/14 25/05/14 01/06/14 08/06/14 15/06/14 22/06/14 29/06/14 06/07/14 13/07/14 20/07/14
MG. 5 MG. 6 MG. 7 MG. 8 MG. 9 MG. 10 MG. 11 MG. 12 MG. 13 MG. 14 MG. 15 MG. 16 MG. 17 MG. 18 MG. 19 MG. 20 MG. 21 MG. 22

0.041
0.041 - - - - - - - - - - - - - - - - -
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
0.001 0.001 0.001 0.001 - - - - - - - - - - - - - -

0.755 0.755 0.755 0.755 0.755 0.755 0.755 0.755


- 0.593 0.144 0.742 - - - - - - - - - - - - - -
0.007 0.007
- - - - - - - - - - - - - - - - - -
0.221 0.221
- - - - - - - - - - - - - - - - - -
0.107
- - 0.061 0.110 - - - - - - - - - - - - - -
0.041 0.041 0.041 0.041 0.041
0.041 0.013 0.025 0.002 - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - -
0.618 0.618 0.618 0.618 0.618 0.618
- 0.254 0.293 0.314 - - - - - - - - - - - - - -
2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770
- - 1.505 1.342 - - - - - - - - - - - - - -
1.477 1.477 1.477 1.477 1.477 1.477 1.477 1.477
- - 0.260 0.342 - - - - - - - - - - - - - -
Kurva Rencana Awal

0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398
- - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - -

0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 Kurva Realisasi
0.001 0.001 4.716%
0.001 0.001 0.001 0.001 0.001 0.001 0.001
0.001 0.001 0.001 0.001 - - - - - - - - - - - - - -
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
- - - - - - - - - - - - - - - - - -
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
- - - - - - - - - - - - - - - - - -

1.388 2.003 2.892 3.782 5.069 7.833 10.535 14.926 20.190 24.582 29.439 34.296 38.707 43.962 48.369 52.576 56.143 59.817
1.466 2.9018 3.116 4.807 6.063 4.545 5.403 5.403 4.649 4.649 4.649 3.172 3.172 3.172 3.172 3.172 3.172 3.278
1.635 4.537 7.652 12.460 18.523 23.067 28.471 33.874 38.523 43.172 47.820 50.992 54.164 57.336 60.507 63.679 66.851 70.129
0.084 0.862 2.291 2.854 - - - - - - - - - - - - - -
0.248 1.111 3.402 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256
-1.387 -3.426 -4.251 -6.204 -12.266 -16.811 -22.215 -27.618 -32.267 -36.916 -41.564 -44.736 -47.908 -51.080 -54.251 -57.423 -60.595 -63.873
Konsultan : PT. Yodya Karya (Persero)
No. Kontrak : HK.02.03/SATKER-P2JN/157/I/2014
Tanggal Kontrak : 30 Januari 2014
Nilai Kontrak : Rp.1.367.657.500,00
No. SPMK : HK.01.24/SATKER-P2JN/269/II/2014
Tanggal SPMK : 20 Februari 2014

Juli Agustus September Oktober November


21/07/14 28/07/14 04/08/14 11/08/14 18/08/14 25/08/14 01/09/14 08/09/14 15/09/14 22/09/14 29/09/14 06/10/14 13/10/14 20/10/14 27/10/14 03/11/14 10/11/14
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d KET.
27/07/14 03/08/14 10/08/14 17/08/14 24/08/14 31/08/14 07/09/14 14/09/14 21/09/14 28/09/14 05/10/14 12/10/14 19/10/14 26/10/14 02/11/14 09/11/14 16/11/14
MG. 23 MG. 24 MG. 25 MG. 26 MG. 27 MG. 28 MG. 29 MG. 30 MG. 31 MG. 32 MG. 33 MG. 34 MG. 35 MG. 36 MG. 37 MG. 38 MG. 39

0.035 0.035 100


- - - - - - - - - - - - - - - - -
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
- - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - -
0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107 0.107
- - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - -

0.225 0.449 0.449 0.449 0.225


- - - - - - - - - - - - - - - - -
50

- - - - - - - - - - - - - - - - -
2.770 2.770 2.770 2.770 2.770 2.770 2.770 1.385 1.385 1.385 1.385
- - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - -

0.817 0.817
- - - - - - - - - - - - - - - - -

0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
- - - - - - - - - - - - - - - - -
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
- - - - - - - - - - - - - - - - -
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
- - - - - - - - - - - - - - - - - 0

63.491 67.165 70.839 74.512 78.186 81.860 85.534 89.208 91.298 93.216 95.358 97.499 98.058 98.286 99.105 99.960 100.000
2.880 2.880 2.880 2.880 2.880 2.880 2.880 1.720 1.944 1.944 1.944 0.335 0.927 0.855 0.038 - -
73.010 75.890 78.771 81.651 84.531 87.412 90.292 92.012 93.957 95.900 97.844 98.179 99.106 99.961 100.00 - -
- - - - - - - - - - - - - - - - -
6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 6.256 - -
-66.754 -69.634 -72.515 -75.395 -78.275 -81.156 -84.036 -85.756 -87.700 -89.644 -91.588 -91.923 -92.850 -93.705 -93.743 0.000 0.000
KONTRAK
Minggu 8
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT
(%) 7

I UMUM
1.2 Mobilisasi Ls 1.00 0.233 -
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 -
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 -
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 -
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 -
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 -
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 -
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 -
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 -
TOTAL BOBOT 100.00
Target Bobot Minggu ke 8 12.45958953 %
Bobot Tercapai Minggu ke 8 - %

3.780
0.200
1.680 1.880
3.6 3.2

0.400
2.880 3.280

1.000
6.400 7.400 16.340
07 Apr' s/d 13 Apr' 2014
Minggu 8 Target Bobot = 12.4595895 %
Bulan April 2014
8 9 10 11 12 13

- - - - - -
- - - 0.014 - -

- - - - - -
- - - - - -
- - - - - 93.398
- - - - - -
- - - - - -

- - - - - -

- - - 656.175 92.220 -
- - - 66.150 118.425 18.900
- - - - - -

- - - - - -

- - - - - -

- - - - - -
- - - - - -
- - - - - -
TOTAL

- Ls
0.014 Ls

- M3
- M3
93.398 M3
- M3
- M2

- M3

748.395 M3
203.475 M3
- M3

- M2

- M2

- Ls
- Ls
- Ls
KARTU KONTROL AKTIVITAS ALAT BERAT

Jenis Alat : Exza


Nama Opr : Yoni
Kode Alat : AE-3

HM TOTAL JAM PERMINTAAN DIMENSI (M) STA


TANGGAL URAIAN PEKERJAAN VOLUME KERJA (M³) KETERANGAN
AWAL AKHIR PENGISIAN KERJA (LITER) PANJANG LEBAR TINGGI AWAL AKHIR
23 April 2014 - galian tanah jam 161.00 5.87 0.67 633.20 4+173 4+334 kanan
- galian tanpa Cold Milling Machine jam 161.00 2.24 0.08 28.85 4+173 4+334 kanan
- hampar batu sreen jam 161.00 5.87 0.10 94.51 4+173 4+334 kanan
24 April 2014 - galian tanah jam 20.00 4.4 0.31 27.28 4+153 4+173 kiri
- galian tanpa Cold Milling Machine jam 20.00 4.4 0.08 7.04 4+153 4+173 kiri
- hampar batu sreen jam 20.00 4.4 0.10 8.80 4+153 4+173 kiri
25 April 2014 - Hampar LPB jam 20.00 4.4 0.15 13.20 4+153 4+173 kanan
26 April 2014 -
27 April 2014 -
28 April 2014 - galian tanah jam 102.00 4.83 4.24 2,086.42 3+700 3+802 kiri
- galian tanah saluran jam 100.00 1.625 0.49 80.11 3+700 3+800 kiri
29 April 2014 - galian tanah jam 62.50 - 1+528 1+591 belum diukur
- galian tanpa Cold Milling Machine jam 62.50 2.25 0.08 11.25 1+528 1+591 kiri
- hampar batu sreen jam 62.50 3.79 0.10 23.69 1+528 1+591 belum diukur
- Hampar LPB jam 62.50 3.79 0.15 35.53 1+528 1+591 belum diukur
30 April 2014
01 Mei 2014

02 Mei 2014

03 Mei 2014
04 Mei 2014

05 Mei 2014

06 Mei 2014

TOTAL jam liter


KARTU KONTROL AKTIVITAS ALAT BERAT

Jenis Alat : Vibro


Nama Opr : Anto
Kode Alat : KSP-1

HM TOTAL JAM PERMINTAAN DIMENSI (M) STA


TANGGAL URAIAN PEKERJAAN VOLUME KERJA (M³) KETERANGAN
AWAL AKHIR PENGISIAN KERJA (LITER) PANJANG LEBAR TINGGI AWAL AKHIR
28 April 2014 - -
29 April 2014 - pemadatan batu sreen jam 181.00 4.4 0.10 79.64 4+153 4+334 kanan
30 April 2014 - pemadatan LPB jam 181.00 4.4 0.15 119.46 4+153 4+334 kanan
- pemadatan LPB jam 103.70 5.47 0.15 85.09 4+025 4+129 kiri
01 Mei 2014 - pemadatan LPB jam 113.00 4.15 0.15 70.34 3+447 3+560 kiri
- pemadatan LPB jam 103.00 8.5 0.15 131.33 2+700 2+803 kiri kanan
- perbaikan pemadatan LPB jam 103.00 8.5 0.15 131.33 2+700 2+803 kiri kanan
02 Mei 2014 - hampar dan perbaikan LPB jam 150.00 4 0.15 90.00 2+450 2+600 kiri
03 Mei 2014 - hampar dan perbaikan LPB 2829 2833 4 jam 65.00 8.5 0.15 82.88 2+850 2+915 kiri kanan
04 Mei 2014 - hampar LPB 2833 2835 2 jam 150.00 2.82 0.15 63.45 2+800 2+950 kiri
- hampar LPB jam 200.00 4 0.15 120.00 3+100 3+300 kiri
05 Mei 2014 - pemadatan batu sreen 2835 2837 2 jam 62.50 3.79 0.10 23.69 1+528 1+591 kiri
- pemadatan LPB jam 62.50 3.79 0.15 35.53 1+528 1+591 kiri
06 Mei 2014 - perbaikan pemadatan LPB 2837 2841 4 jam 109.00 8.5 0.15 138.98 4+225 4+334 kanan
07 Mei 2014 - pemadatan tanah dasar 2841 2843 2 jam 200.00 2 400.00 0+700 0+900 kanan
08 Mei 2014 - pemadatan tanah dasar 2843 2844 1 jam 150.00 2 300.00 1+650 1+800 kanan
09 Mei 2014 - penyiapan badan jalan 2844 2846 2 jam 350.00 2 700.00 0+000 0+350 kiri
- penyiapan badan jalan 500.00 3 1,500.00 0+350 0+850 kiri
10 Mei 2014 - jam - -
- jam - -
- - -
- - -
- - -
- - -
11 Mei 2014 - - -
- -
- -
TOTAL 17 jam liter
KARTU KONTROL AKTIVITAS ALAT BERAT

Jenis Alat : Greder


Nama Opr : Doni
Kode Alat : AG-2

HM TOTAL JAM PERMINTAAN DIMENSI (M) STA


TANGGAL URAIAN PEKERJAAN VOLUME KERJA (M³) KETERANGAN
AWAL AKHIR PENGISIAN KERJA (LITER) PANJANG LEBAR TINGGI AWAL AKHIR
29 April 2014 - -
30 April 2014
01 Mei 2014 - -
02 Mei 2014 - hampar LPB jam 113.00 4.15 0.15 70.34 3+447 3+560 kiri
- hampar LPB jam 103.00 8.5 0.15 131.33 2+700 2+803 kiri kanan
- hampar dan perbaikan LPB jam 103.00 8.5 0.15 131.33 2+700 2+803 kiri kanan
03 Mei 2014 - hampar dan perbaikan LPB jam 150.00 4 0.15 90.00 2+450 2+600 kiri
04 Mei 2014 - hampar dan perbaikan LPB 9777 9783 6 jam 65.00 8.5 0.15 82.88 2+850 2+915 kiri kanan
05 Mei 2014 - hampar LPB 150.00 2.82 0.15 63.45 2+800 2+950 kiri
- hampar LPB 9783 9788 5 jam 200.00 4 0.15 120.00 3+100 3+300 kiri
06 Mei 2014 - perbaikan LPB 9788 9789 1 jam 28.00 4 0.05 5.60 4+306 4+334 kanan
- penyiapan badan jalan 350.00 2 700.00 0+300 0+650 kiri
07 Mei 2014 - hampar dan perbaikan LPB 9789 9792 3 jam 104.00 4 0.10 41.60 4+230 4+334 kanan
- penyiapan badan jalan 300.00 2 600.00 0+350 0+650 kanan
08 Mei 2014 - penyiapan badan jalan 9792 9798 6 jam 200.00 2 400.00 0+700 0+900 kanan
09 Mei 2014 - penyiapan badan jalan 9798 9804 6 jam 150.00 2 300.00 1+650 1+800 kanan
10 Mei 2014 - perbaikan badan jalan 150.00 - 2+700 2+850 kiri

11 Mei 2014 - penyiapan badan jalan 9804 9808 4 jam 350.00 2 700.00 0+000 0+350 kiri
- penyiapan badan jalan 500.00 3 1,500.00 0+350 0+850 kiri
- - -
- - -
- - -
- - -
12 Mei 2014 - - -
- -
- -
TOTAL 31 jam liter -
KARTU KONTROL AKTIVITAS ALAT BERAT

Jenis Alat : Exza


Nama Opr : Hengki
Kode Alat : GE-1

HM TOTAL JAM PERMINTAAN DIMENSI (M) STA


TANGGAL URAIAN PEKERJAAN VOLUME KERJA (M³) KETERANGAN
AWAL AKHIR PENGISIAN KERJA (LITER) PANJANG LEBAR TINGGI AWAL AKHIR
01 Mei 2014 - galian tanah 9850 9859 9 jam 250.00 40.00 3.7 4.20 621.60 0+160 0+200
- galian batu 34.00 2.1 1.80 128.52 0+165 0+199
02 Mei 2014 - galian tanah 9859 9867 8 jam 25.00 3.8 3.40 323.00 0+199 0+224
- galian batu 10.00 2.4 2.30 55.20 0+214 0+224
03 Mei 2014 - galian tanah 9867 9871 4 jam 26.00 2.4 3.70 230.88 0+224 0+250
- galian batu 25.00 1.4 2.10 73.50 0+224 0+249
04 Mei 2014 - - -
05 Mei 2014 - ` - -
06 Mei 2014 - galian tanah 9871 9878 7 jam 48.00 1.9 2.00 182.40 0+750 0+798
- galian batu 48.00 1.3 1.20 74.88 0+750 0+798
- - -
- - -
07 Mei 2014 - galian tanah 9878 9887 9 jam 47.00 2.9 2.70 368.01 0+798 0+845
- galian batu ` 47.00 1.37 3.10 199.61 0+798 0+845
08 Mei 2014 - -
09 Mei 2014 - -
- -
10 Mei 2014 - -
- -
11 Mei 2014 - -
- -
- -
- -
11 Mei 2014 - -
- -
- -
TOTAL 37 jam 250 liter
KARTU KONTROL AKTIVITAS ALAT BERAT

Jenis Alat : Exza


Nama Opr : Fandi
Kode Alat : GE-2

HM TOTAL JAM PERMINTAAN DIMENSI (M) STA


TANGGAL URAIAN PEKERJAAN VOLUME KERJA (M³) KETERANGAN
AWAL AKHIR PENGISIAN KERJA (LITER) PANJANG LEBAR TINGGI AWAL AKHIR

TOTAL jam liter


KARTU KONTROL AKTIVITAS MOBIL DUMP TRUCK

Jenis Alat : Dump truck

STA HM TOTAL
TANGGAL NAMA SOPIR URAIAN PEKERJAAN PANJANG VOLUME JAM PERMINTAAN KET
AWAL AKHIR AWAL AKHIR PENGISIAN KERJA (LITER)
maxi buang tanah cuttingan 4+173 4+334 161 m 211.07
ulu buang tanah cuttingan 4+173 4+334 161 m 211.07
16 April 2014
sule buang tanah cuttingan 4+173 4+334 161 m 211.07
633.20 sesuai dengan volume cuttingan Yoni tanggal 16 April 2014
maxi buang tanah cuttingan 3+700 3+802 102 m 1,416.53
21 April 2014 ulu buang tanah cuttingan 3+700 3+802 102 m 750.00
2,166.53 sesuai dengan volume cuttingan dan gal. saluran Yoni tanggal 21 April 2014
DITRASVER KE REKENING NO. …………………………………………………..an, SULE

211.07
LAPORAN CUACA
PEKERJAAN : Pelebaran Jalan Isimu-Paguyaman (Rigit Pavement) III BULAN : April 2014
LOKASI : Desa Pulubala dan Tolotio
PENYEDIA JASA : PT. KARUNIA JAYA SEJATI
SUMBER DANA : APBN
TAHUN ANGGARAN : 2014

JAM
TGL.
01.00

02.00

03.00

04.00

05.00

06.00

07.00

08.00

09.00

10.00

11.00

12.00

13.00

14.00

15.00

16.00

17.00

18.00

19.00

20.00

21.00

22.00

23.00

24.00
1
2
3
4
5
6
7
8
9
10
11
12
13 Hari minggu
14
15
16
17
18
19
20 Hari minggu 0
21
22
23
24
25
26
27
28
29
30
31

Pulubala, April 2014


Di Setujui Oleh, Diperiksa Oleh, Dibuat Oleh :
Pihak Kegiatan Konsultan Supervisi, Kontraktor pelaksana
PENGAWAS LAPANGAN PT. Yodya Karya (Persero) PT. KARUNIA JAYA SEJATI

………………………….. ………………………….. Gunawan Santoso,ST


Pelaksana Lapangan
Keterangan
: Cerah

: Gerimis

: Hujan lebat
LAPORAN CUACA
PEKERJAAN : Pelebaran Jalan Isimu-Paguyaman (Rigit Pavement) III BULAN : Mei 2014
LOKASI : Desa Pulubala dan Tolotio
PENYEDIA JASA : PT. KARUNIA JAYA SEJATI
SUMBER DANA : APBN
TAHUN ANGGARAN : 2014

JAM
TGL.
01.00

02.00

03.00

04.00

05.00

06.00

07.00

08.00

09.00

10.00

11.00

12.00

13.00

14.00

15.00

16.00

17.00

18.00

19.00

20.00

21.00

22.00

23.00

24.00
1
2
3
4 Hari minggu
5
6
7
8
9
10
11 Hari minggu
12
13
14
15
16
17
18 Hari minggu
19
20
21
22
23
24
25 Hari minggu
26
27
28
29
30
31

Pulubala, Mei 2014


Di Setujui Oleh, Diperiksa Oleh, Dibuat Oleh :
Pihak Kegiatan Konsultan Supervisi, Kontraktor pelaksana
PENGAWAS LAPANGAN PT. Yodya Karya (Persero) PT. KARUNIA JAYA SEJATI

………………………….. ………………………….. Gunawan Santoso,ST


Pelaksana Lapangan
Keterangan
: Cerah

: Gerimis

: Hujan lebat
HITUNGAN VOLUME HARI-HA
14 Apr' s/d 20 Apr' 2014
Minggu 9

KODE NAMA
NO. TANGGAL JENIS PEKERJAAN
ALAT OPERATOR
14/04/14
15/04/14
galian tanah GE-2 Fandi
galian tanah saluran GE-2 Fandi
galian tanah GE-2 Fandi
16/04/14

galian tanah AE-3 Yoni


hampar batu sreen AE-3 Yoni

17/04/14 galian tanah AE-3 Yoni


hampar batu sreen AE-3 Yoni
galian tanah AE-3 Yoni

18/04/14 Pemadatan LPB KSP-1 Anto


Pemadatan LPB KSP-1 Anto
Hampar LPB AE-3 Yoni
galian tanah AE-3 Yoni

19/04/14 Hampar LPB AG-2 Doni


Pemadatan LPB KSP-1 Anto

galian tanah GE-2 Fandi

Hampar LPB AG-2 Doni


Pemadatan LPB KSP-1 Anto

Hampar dan perbaikan LPB AG-2 Doni


Pemadatan LPB KSP-1 Anto

20/04/14 Hampar dan perbaikan LPB AG-2 Doni

HITUNGAN VOLUME HARI-HAR


21 Apr' s/d 27 Apr' 2014
Minggu 10

KODE NAMA
NO. TANGGAL JENIS PEKERJAAN
ALAT OPERATOR
21/04/14 galian tanah saluran GE-2 Fandi
galian tanah saluran GE-2 Fandi

galian tanah AE-3 Yoni


galian tanah saluran AE-3 Yoni

Hampar dan perbaikan LPB AG-2 Doni

LC 0 Bass

22 April 2014 LC 0 Bass


23 April 2014
24 April 2014
25 April 2014 LC 0 Bass

HITUNGAN VOLUME HARI-HA


28 Apr' s/d 04 Mei 2014
Minggu 11

KODE NAMA
NO. HARI TANGGAL JENIS PEKERJAAN
ALAT OPERATOR
1 minggu 27/04/14

2 Senin 28/04/14 galian tanah AE-3 Yoni


LC 0 Bass

3 selesa 29/04/14 LC 0 Bazz

4 rabu 30/04/14 0 Bazz

5 kamis 01/05/14

6 jumat 02/05/14
7 sabtu 03/05/14
UNGAN VOLUME HARI-HARI 14 Apr' s/d 20 Apr' 2014Minggu 9

STA KUBIKASI HM
JENIS ALAT
AWAL AKHIR PANJANG LEBAR TINGGI VOLUME AWAL

Exza 3 + 085 s/d 3 + 145 60 3.3 3.245 642.51


Exza 3 + 145 s/d 3 + 202 57 1.5 0.65 55.58
Exza 3 + 228 s/d 3 + 305 77.5 4.75 3.93 1,446.73

Exza 4 + 153 s/d 4 + 173 20 4.4 0.3166667 27.87


Exza 4 + 153 s/d 4 + 173 20 4.4 0.1 8.80

Exza 4 + 153 s/d 4 + 173 20 4.4 0.3166667 27.87


Exza 4 + 153 s/d 4 + 173 20 4.4 0.1 8.80
Exza 4 + 153 s/d 4 + 173 20 5.3 0.3166667 33.57

Vibro 4 + 153 s/d 4 + 334 181 4.4 0.15 119.46


Vibro 4 + 025 s/d 4 + 129 103.7 5.4725 0.15 85.12
Exza 4 + 153 s/d 4 + 173 20 4.4 0.15 13.20
Exza 4 + 153 s/d 4 + 173 20 4.4 0.3166667 27.87

Greder 3 + 447 s/d 3 + 560 113 4.15 0.15 70.34


Vibro 3 + 447 s/d 3 + 560 113 4.15 0.15 70.34

Exza 3 + 360 s/d 3 + 425 65 4.58 4.145 1,233.97

Greder 2 + 700 s/d 2 + 803 103 8.5 0.15 131.33


Vibro 2 + 700 s/d 2 + 803 103 8.5 0.15 131.33

Greder 2 + 700 s/d 2 + 803 103 8.5 0.15 131.33


Vibro 4 + 025 s/d 4 + 129 103.7 10 0.15 155.55

Greder 2 + 450 s/d 2 + 600 150 4 0.05 30.00

UNGAN VOLUME HARI-HARI 21 Apr' s/d 27 Apr' 2014Minggu 10


STA KUBIKASI HM
JENIS ALAT
AWAL AKHIR PANJANG LEBAR TINGGI VOLUME AWAL
Exza 2 + 500 s/d 2 + 615 115 1.5 0.65 112.13
Exza s/d 0 0 0 -

Exza s/d 0 0 0 -
Exza s/d 0 0 0 -

Greder 2 + 850 s/d 2 + 915 65 8.5 0.1 55.25

LC 3 + 425 s/d 3 + 525 100 3.75 0.1 37.50

LC 3 + 525 s/d 3 + 675 150 3.75 0.1 56.25

LC 3 + 425 s/d 3 + 675 250 3.45 0.1 86.25

UNGAN VOLUME HARI-HARI 28 Apr' s/d 04 Mei 2014Minggu 11

STA KUBIKASI HM
JENIS ALAT
AWAL AKHIR PANJANG LEBAR TINGGI VOLUME AWAL

Exza s/d 0 1.5 0.65 -


LC 3 + 425 s/d 3 + 680 255 3.45 0.1 87.98

K_350 3 + 550 s/d 3 + 680 130 3.45 0.27 121.10


s/d

K_350 3 + 425 s/d 3 + 550 125 3.45 0.27 116.44


s/d

s/d
s/d
s/d

s/d
s/d
s/d
s/d
s/d
s/d
HM
BBM KETERANGAN
AKHIR

kiri
kiri
kiri

kanan
kanan

kanan
kanan
kiri

kanan
kanan
kiri
kiri

kiri
kiri

kiri

kiri kanan
kiri kanan

kiri kanan
kiri kanan

kiri kanan
HM
BBM KETERANGAN
AKHIR
kiri
besok diukur

6409
6409

kanan

kanan

kiri

HM
BBM KETERANGAN
AKHIR

kanan
kiri

kiri

kiri
07 Apr' s/d 13 Apr' 2014
KONTRAK
Minggu 8 Target Bobot = 12.4596 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan April 2014
(%) 7 8 9 10 11 12 13 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 - - - - 0.014 - - 0.014 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 - - - - - - - - M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 - - - - - - 93.398 93.398 M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - - - - - - - - M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 - - - - 656.175 92.220 - 748.395 M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 - - - - 66.150 118.425 18.900 203.475 M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 - - - - - - - - M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu ke 8 12.45958953 %
Bobot Tercapai Minggu ke 8 - %
14 Apr' s/d 20 Apr' 2014
KONTRAK
Minggu 9 Target Bobot = 18.5225386 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan April 2014
(%) 14 15 16 17 18 19 20 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.016 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 587.390 285.92 2,172.683 61.433 27.867 1,233.967 - 4,369.259 M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 30.180 15.12 - - - - - 45.300 M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - 3,062.50 - - - - - 3,062.500 M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 395.250 171.55 - - 13.200 201.668 30.000 811.668 M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 70.875 85.08 - - - - - 155.955 M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 - - - - - - - - M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu 9 18.52253856 %
Bobot Tercapai Minggu 9 - %
21 Apr' s/d 27 Apr' 2014
KONTRAK
Minggu 10 Target Bobot = 23.067376 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan April 2014
(%) 21 22 23 24 25 26 27 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.016 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 1,876.400 2,838.50 - - - - - 4,714.904 M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 - 11.25 - - - - - 11.250 M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - 1,200.00 - - - - - 1,200.000 M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 55.250 218.98 35.531 - - - - 309.763 M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 - - - - - - - - M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 37.500 56.250 - - 86.250 - - 180.000 M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu 10 23.067376 %
Bobot Tercapai Minggu 10 - %
28 Apr' s/d 04 Mei 2014
KONTRAK
Minggu 11 Target Bobot = 28.4708472 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan Mei 2014
(%) 28 29 30 1 2 3 4 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 0.005 0.005 0.005 0.005 0.005 - 0.005 0.030 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 - - - - - - - - M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 - - - - - - - - M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - - - - - - - - M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 - - - - - - - - M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 - - - - - - - - M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 - - - - - - - - M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu 11 28.47084719 %
Bobot Tercapai Minggu 11 - %
24 Feb' s/d 02 Mar' 2014
KONTRAK
Minggu 2 Target Bobot = 0.04083559 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan Maret 2014
(%) 7 8 9 10 11 12 13 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 - - - - 0.014 - - 0.014 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 - - - - - - - - M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 - - - - - - 93.398 93.398 M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - - - - - - - - M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 - - - - 656.175 92.220 - 748.395 M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 - - - - 66.150 118.425 18.900 203.475 M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 - - - - - - - - M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu ke 8 0.040835592 %
Bobot Tercapai Minggu ke 8 - %
14 Apr' s/d 20 Apr' 2014
KONTRAK
Minggu 9 Target Bobot = 18.5225386 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan April 2014
(%) 14 15 16 17 18 19 20 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.016 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 587.390 285.92 2,172.683 61.433 27.867 1,233.967 - 4,369.259 M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 30.180 15.12 - - - - - 45.300 M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - 3,062.50 - - - - - 3,062.500 M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 395.250 171.55 - - 13.200 201.668 30.000 811.668 M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 70.875 85.08 - - - - - 155.955 M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 - - - - - - - - M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu 9 18.52253856 %
Bobot Tercapai Minggu 9 - %
21 Apr' s/d 27 Apr' 2014
KONTRAK
Minggu 10 Target Bobot = 23.067376 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan April 2014
(%) 21 22 23 24 25 26 27 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.016 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 1,876.400 2,838.50 - - - - - 4,714.904 M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 - 11.25 - - - - - 11.250 M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - 1,200.00 - - - - - 1,200.000 M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 55.250 218.98 35.531 - - - - 309.763 M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 - - - - - - - - M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 37.500 56.250 - - 86.250 - - 180.000 M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu 10 23.067376 %
Bobot Tercapai Minggu 10 - %
28 Apr' s/d 04 Mei 2014
KONTRAK
Minggu 11 Target Bobot = 28.4708472 %
NO. URAIAN PEKERJAAN SATUAN
VOLUME BOBOT Bulan Mei 2014
(%) 28 29 30 1 2 3 4 TOTAL
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 - - - - - - - - Ls
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 0.005 0.005 0.005 0.005 0.005 - 0.005 0.030 Ls
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 - - - - - - - - M3
3.1(1b) Galian Cadas Muda M3 69.82 0.014 - - - - - - - - M3
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 - - - - - - - - M3
3.2(1) Timbunan Biasa M3 3,748.68 1.494 - - - - - - - - M3
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 - - - - - - - - M2
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 - - - - - - - - M3
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 - - - - - - - - M3
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 - - - - - - - - M3
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 - - - - - - - - M3
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 - - - - - - - - M2
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 - - - - - - - - M2
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 - - - - - - - - Ls
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 - - - - - - - - Ls
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 - - - - - - - - Ls
TOTAL BOBOT 100.00
Target Bobot Minggu 11 28.47084719 %
Bobot Tercapai Minggu 11 - %
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Februari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 1
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 20 Feb' s/d 23 Feb' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.000 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 - - - - - - - - -
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - - - - - - -
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - - - - - - -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - - - - - - - - -
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - - - - - - -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 - - - - - - - - -
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 0.000
REALISASI 0.000 0.000
DEVIASI ( + / - ) 0.000 0.000

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Maret 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 2
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 24 Feb' s/d 02 Mar' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.041 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 - - - 0.175 17.500 0.041 0.175 17.500 0.041
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - - - - - - -
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - - - - - - -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - - - - - - - - -
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - - - - - - -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 - - - - - - - - -
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 0.041
REALISASI 0.000 0.041
DEVIASI ( + / - ) 0.000 0.000

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Maret 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 3
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 03 Mar' s/d 09 Mar' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.082 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.175 17.500 0.041 0.175 17.500 0.041 0.350 35.000 0.082
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - - - - - - -
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - - - - - - -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - - - - - - - - -
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - - - - - - -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 - - - - - - - - -
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.041 0.084
REALISASI 0.041 0.082
DEVIASI ( + / - ) 0.000 -0.002

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Maret 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 4
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 10 Mar' s/d 16 Mar' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.164 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.350 35.000 0.082 0.175 17.500 0.041 0.525 52.500 0.123
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - - - - - - -
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - - - - - - -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - - - 1,927.920 16.667 0.041 1,927.920 16.667 0.041
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - - - - - - -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 - - - 0.028 2.800 0.001 0.028 2.800 0.001
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.084 0.169
REALISASI 0.082 0.164
DEVIASI ( + / - ) -0.002 -0.005

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Maret 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 5
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 17 Mar' s/d 23 Mar' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.248 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.525 52.500 0.123 0.175 17.500 0.041 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - 0.030 3.000 0.001 0.030 3.000 0.001
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - - - - - - -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 1,927.920 16.667 0.041 1,905.000 16.469 0.041 3,832.920 33.135 0.082
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - - - - - - -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.028 2.800 0.001 0.028 2.800 0.001 0.056 5.600 0.002
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.169 1.635
REALISASI 0.164 0.248
DEVIASI ( + / - ) -0.005 -1.387

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Maret 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 6
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 24 Mar' s/d 30 Mar' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 1.111 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.030 3.000 0.001 0.030 3.000 0.001 0.060 6.000 0.003
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - 3,226.600 9.826 0.593 3,226.600 9.826 0.593
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 3,832.920 33.135 0.082 625.000 5.403 0.013 4,457.920 38.538 0.095
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - 166.500 6.835 0.254 166.500 6.835 0.254
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.056 5.600 0.002 0.028 2.800 0.001 0.084 8.400 0.002
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 1.635 4.537
REALISASI 0.248 1.111
DEVIASI ( + / - ) -1.387 -3.426

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : April 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 7
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 31 Mar' s/d 06 Apr' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 3.402 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.060 6.000 0.003 0.030 3.000 0.001 0.090 9.000 0.004
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 3,226.600 9.826 0.593 782.700 2.383 0.144 4,009.300 12.209 0.737
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - 154.200 4.113 0.061 154.200 4.113 0.061
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 4,457.920 38.538 0.095 1,181.500 10.214 0.025 5,639.420 48.752 0.120
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 166.500 6.835 0.254 192.500 7.902 0.293 359.000 14.737 0.547
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - 198.000 2.264 1.505 198.000 2.264 1.505
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - 71.250 2.199 0.260 71.250 2.199 0.260
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.084 8.400 0.002 0.028 2.800 0.001 0.112 11.200 0.003
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 4.537 7.652
REALISASI 1.111 3.402
DEVIASI ( + / - ) -3.426 -4.251

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : April 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 8
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 07 Apr' s/d 13 Apr' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 6.256 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.090 9.000 0.004 0.030 3.000 0.001 0.120 12.000 0.006
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 4,009.300 12.209 0.737 4,036.540 12.292 0.742 8,045.840 24.501 1.479
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 154.200 4.113 0.061 276.500 7.376 0.110 430.700 11.489 0.172
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 5,639.420 48.752 0.120 75.000 0.648 0.002 5,714.420 49.401 0.122
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 359.000 14.737 0.547 206.500 8.477 0.314 565.500 23.214 0.861
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 198.000 2.264 1.505 176.500 2.018 1.342 374.500 4.282 2.847
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 71.250 2.199 0.260 93.800 2.895 0.342 165.050 5.095 0.602
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.112 11.200 0.003 0.028 2.800 0.001 0.140 14.000 0.004
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 7.652 12.460
REALISASI 3.402 6.256
DEVIASI ( + / - ) -4.251 -6.204

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : April 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 9
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 14 Apr' s/d 20 Apr' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 9.371 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.120 12.000 0.006 0.030 3.000 0.001 0.150 15.000 0.007
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 8,045.840 24.501 1.479 4,177.76 12.722 0.768 12,223.600 37.223 2.248
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 430.700 11.489 0.172 409.30 10.919 0.163 840.000 22.408 0.335
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 5,714.420 49.401 0.122 2,653.200 22.937 0.057 8,367.620 72.337 0.179
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1,920.00 1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 565.500 23.214 0.861 169.50 6.958 0.258 735.000 30.172 1.119
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 374.500 4.282 2.847 211.40 2.417 1.607 585.900 6.698 4.454
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 165.050 5.095 0.602 71.20 2.198 0.260 236.250 7.293 0.862
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.140 14.000 0.004 0.028 2.800 0.001 0.168 16.800 0.005
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 12.460 18.523
REALISASI 6.256 9.371
DEVIASI ( + / - ) -6.204 -9.152

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : April 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 10
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 21 Apr' s/d 27 Apr' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 16.838 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.150 15.000 0.007 0.030 3.000 0.001 0.180 18.000 0.009
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 12,223.600 37.223 2.248 2,250.00 6.852 0.414 14,473.600 44.075 2.661
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 840.000 22.408 0.335 - - - 840.000 22.408 0.335
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 8,367.620 72.337 0.179 2,235.30 19.324 0.048 10,602.920 91.661 0.226
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1,920.00 1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 735.000 30.172 1.119 307.50 12.623 0.468 1,042.500 42.796 1.588
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 585.900 6.698 4.454 567.000 6.482 4.310 1,152.900 13.181 8.764
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 236.250 7.293 0.862 610.000 18.829 2.225 846.250 26.122 3.086
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.168 16.800 0.005 0.028 2.800 0.001 0.196 19.600 0.006
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 18.523 23.067
REALISASI 9.371 16.838
DEVIASI ( + / - ) -9.152 -6.230

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Mei 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 11
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 28 Apr' s/d 04 Mei 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 16.839 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.180 18.000 0.009 - - - 0.180 18.000 0.009
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 14,473.600 44.075 2.661 - - - 14,473.600 44.075 2.661
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 840.000 22.408 0.335 - - - 840.000 22.408 0.335
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 10,602.920 91.661 0.226 - - - 10,602.920 91.661 0.226
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 1,042.500 42.796 1.588 - - - 1,042.500 42.796 1.588
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 1,152.900 13.181 8.764 - - - 1,152.900 13.181 8.764
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 846.250 26.122 3.086 - - - 846.250 26.122 3.086
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.196 19.600 0.006 0.028 2.800 0.001 0.224 22.400 0.007
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 23.067 28.471
REALISASI 16.838 16.839
DEVIASI ( + / - ) -6.230 -11.632

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Mei 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 12
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 05 Mei s/d 11 Mei 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 17.019 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.180 18.000 0.009 0.030 3.000 0.001 0.210 21.000 0.010
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 14,473.600 44.075 2.661 291.000 0.886 0.054 14,764.600 44.961 2.715
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 840.000 22.408 0.335 - - - 840.000 22.408 0.335
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 10,602.920 91.661 0.226 230.000 1.988 0.005 10,832.920 93.650 0.231
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1,920.00 1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 1,042.500 42.796 1.588 - - - 1,042.500 42.796 1.588
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 1,152.900 13.181 8.764 - - - 1,152.900 13.181 8.764
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 846.250 26.122 3.086 - - - 846.250 26.122 3.086
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - 52.000 2.014 0.120 52.000 2.014 0.120
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.224 22.400 0.007 0.028 2.800 0.001 0.252 25.200 0.007
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - 0.001 0.100 0.000 0.001 0.100 0.000
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 28.471 33.874
REALISASI 16.839 17.019
DEVIASI ( + / - ) -11.632 -16.855

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN BULANAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Februari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 BULAN KE : 1
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 20 Feb' s/d 23 Feb' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.000 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 - - - - - - - - -
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - - - - - - -
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - - - - - - -
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - - - - - - - - -
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - - - - - - -
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 - - - - - - - - -
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 0.000
REALISASI 0.000 0.000
DEVIASI ( + / - ) 0.000 0.000

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN BULANAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Maret 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 BULAN KE : 2
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 24 Feb' s/d 30 Mar' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 1.111 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 - - - 0.700 70.000 0.163 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 - - - 0.060 6.000 0.003 0.060 6.000 0.003
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - - - 3,226.600 9.826 0.593 3,226.600 9.826 0.593
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - - - - - - -
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - - - 4,457.920 38.538 0.095 4,457.920 38.538 0.095
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - - - 166.500 6.835 0.254 166.500 6.835 0.254
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - - - - - - -
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - - - - - - -
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 - - - 0.084 8.400 0.002 0.084 8.400 0.002
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 4.537
REALISASI 0.000 1.111
DEVIASI ( + / - ) 0.000 -3.426

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN BULANAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : April 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 BULAN KE : 3
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 31 Mar' s/d 27 Apr' 2014
Konsultan : PT. Yodya Karya (Persero) BOBOT : 16.838 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D BULAN LALU BULAN INI S/D BULAN INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.700 70.000 0.163 - - - 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.060 6.000 0.003 0.120 12.000 0.006 0.180 18.000 0.009
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 3,226.600 9.826 0.593 11,247.000 34.249 2.068 14,473.600 44.075 2.661
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - - - - - - - - -
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - - - - - - - - -
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - - - 840.000 22.408 0.335 840.000 22.408 0.335
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 4,457.920 38.538 0.095 6,145.000 53.123 0.131 10,602.920 91.661 0.226
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - - - - - - - - -
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 166.500 6.835 0.254 876.000 35.961 1.334 1,042.500 42.796 1.588
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - - - 1,152.900 13.181 8.764 1,152.900 13.181 8.764
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - - - 846.250 26.122 3.086 846.250 26.122 3.086
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - - - - - - - - -
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - - - - - - - - -
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.084 8.400 0.002 0.112 11.200 0.003 0.196 19.600 0.006
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 - - - - - - - - -
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 - - - - - - - - -
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 23.067
REALISASI 1.111 16.838
DEVIASI ( + / - ) 1.111 -6.230

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero) PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN HARIAN

- : Pembangunan Jalan
- : Pelebaran Jalan Isimu - Paguyaman (Rigid Pavement) III
- : HK.02,03/PJNPG-PPK04/541/2014
- : Rp 28,369,000,000.00
- : Kecamatan Pulubala
- : PT. YODYA KARYA (PERSERO)
- : PT. KARUNIA JAYA SEJATI
- : 2014

Minggu Ke : 8 Jam : s/d Cuaca :


Tanggal : 12 April 2014 Jam : s/d Cuaca :
Hari : Jam : s/d Cuaca :

R E A L I S A S I
No. Mata Lokasi Jam Kerja Jumlah Produksi Produksi Sisa
JENIS PEKERJAAN
Pemby. Pekerjaan Mulai Selesai Jam Hari ini s/d Hari Ini Produksi

1.2 Mobilisasi 8:00 17:00 8 - - 1.00


1.8 Manajemen Keselamatan Lalu Lintas 8:00 17:00 8 0.002 0.07 0.93
3.1 (1a) Galian Biasa 8:00 17:00 8 - 4,009.30 28,829.53 volume
3.1(1a) Galian Cadas Muda 8:00 17:00 8 - 25.17 44.66 1.00
3.1 (7) Galian Perkerasan Tanpa Cold Miling Machine 8:00 17:00 8 - 93.40 1,727.55 1.00
3.2. (1) Timbunan Biasa 8:00 17:00 8 - - 32,838.83
KECAMATAN PULUBALA
3.3 (1) Penyiapan Badan Jalan 8:00 17:00 8 - 5,382.92 6,184.58 69.82
4.2(2b) Lapis Pondasi Agregat Kelas S 8:00 17:00 8 - - 1,820.95
5.1(2) Lapis Pondasi Kelas B 8:00 17:00 8 - 967.40 1,468.61 3,748.68
5.3(1) Perkerasan Beton Semen 8:00 17:00 8 100.00 166.15 8,580.77 11,567.50
5.3(3) Lapis Pondasi Bawah Beton Kurus 8:00 17:00 8 - 93.75 3,145.85 1,384.80
7.9.1 Pasangan Batu 8:00 17:00 8 - 170.045 2,436.00
8.4(1) Marka Jalan bukan Thermoplastic 8:00 17:00 8 - 137.325 8,746.92
10.1(3) Pemeliharaan Rutin Selokan, Saluran Air, Galian dan Timbunan 8:00 17:00 8 - 3,239.60
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan 8:00 17:00 8 - 2,581.89
10.1(5) Pemeliharaan Rutin Jembatan 8:00 17:00 8 - 1,458.72
1.00
1.00
1.00

SEMEN
PASIR
disetujui oleh, diperiksa oleh, dibuat oleh, AGRE.KASAR
Direksi Pekerjaan Konsultan Supervisi PT. Karunia Jaya Sejati AGRE.HALUS
SIRTU
BESI

………………………….. ……………………………… …………………………..


LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Pebruari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 1
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 20 s/d 23 Pebruari
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.000 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 0.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 0.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 0.000
REALISASI 0.000 0.000
DEVIASI ( + / - ) 0.000 0.000

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI
KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero)
PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Pebruari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 2
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 24 Pebr. s/d 2 Maret
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.041 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.000 0.000 0.000 0.175 17.500 0.041 0.175 17.500 0.041
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.000 0.041
REALISASI 0.000 0.041 0.041
DEVIASI ( + / - ) 0.000 0.000

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI
KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero)
PT. Karunia Jaya Sejati
FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST
NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Pebruari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 3
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 3 s/d 9 Maret
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.082 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.175 17.500 0.041 0.175 17.500 0.041 0.350 35.000 0.082
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.000 0.000 0.000 0.028 2.800 0.001 0.028 2.800 0.001
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.041 0.084
REALISASI 0.041 0.042 0.082
DEVIASI ( + / - ) 0.000 -0.001

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI
KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero)
PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Pebruari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 4
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 10 s/d 16 Maret
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.167 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.350 35.000 0.082 0.175 17.500 0.041 0.525 52.500 0.123
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.000 0.000 0.000 0.030 3.000 0.001 0.030 3.000 0.001
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 - 0.000 0.000 1,927.92 16.667 0.041 1,927.92 16.667 0.041
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.028 2.800 0.001 0.028 2.800 0.001 0.056 5.600 0.002
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.072 18,500,000.000
TOTAL BOBOT 100.00 25,790,002,208.80
RENCANA 0.084 0.169
REALISASI 0.082 0.084 0.167
DEVIASI ( + / - ) -0.001 -0.002

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI
KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero)
PT. Karunia Jaya Sejati

FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST


NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
LAPORAN MINGGUAN

Kontraktor : PT. Karunia Jaya Sejati BULAN : Pebruari 2014


No. Kontrak : HK0203/PJNPG-PPK04/541 MINGGU KE : 5
Tgl. Kontrak : 17 Pebruari 2014 TANGGAL : 17 s/d 23 Maret
Konsultan : PT. Yodya Karya (Persero) BOBOT : 0.252 %

REALISASI PEKERJAAN
KONTRAK HARGA SATUAN JUMLAH HARGA
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
NO. URAIAN PEKERJAAN SATUAN
BOBOT PRESTASI BOBOT PRESTASI BOBOT PRESTASI BOBOT
VOLUME ( Rp ) ( Rp ) VOLUME VOLUME VOLUME
(%) % % % % % %
I UMUM
1.2 Mobilisasi Ls 1.00 0.233 60,180,000.00 60,180,000.000 0.525 52.500 0.123 0.175 17.500 0.041 0.700 70.000 0.163
1.8 Manajemen Keselamatan Lalu Lintas Ls 1.00 0.048 12,340,237.50 12,340,237.500 0.030 3.000 0.001 0.030 3.000 0.001 0.060 6.000 0.003
0.281 72,520,237.500
III PEKERJAAN TANAH
3.1(1a) Galian Biasa M3 32,838.83 6.038 47,421.100 1,557,253,441.313 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.1(1b) Galian Cadas Muda M3 69.82 0.014 53,296.660 3,721,172.801 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.1(7) Gal. Perk. Tanpa Cold Milling Machine M3 1,820.95 0.442 62,654.370 114,090,475.052 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.2(1) Timbunan Biasa M3 3,748.68 1.494 102,757.810 385,206,147.191 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
3.2(3) Penyiapan Badan Jalan M2 11,567.50 0.247 5,507.580 63,708,931.650 1,927.92 16.667 0.041 1,927.92 16.667 0.041 3,855.83 33.333 0.082
8.236 2,123,980,168.007
IV PELEBARAN PERKERASAN DAN BAHU JALAN
4.2(2b) Lapis Pondasi Agregat Kelas S M3 1,384.80 1.795 334,207.380 462,810,379.824 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
1.795 462,810,379.824
V PERKERASAN BERBUTIR
5.1(2) Lapis Pondasi Agregat Kelas B M3 2,436.00 3.710 392,761.560 956,767,160.160 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
5.3(1) Perkerasan Beton Semen M3 8,746.92 66.488 1,960,373.000 17,147,225,801.160 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
5.3(3) Lapis Pondasi Bawah Beton Kurus M3 3,239.60 11.816 940,617.010 3,047,222,865.596 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
82.013 21,151,215,826.916
BAB. VII STRUKTUR
7.9.(1) Pasangan Batu M2 2,581.89 5.970 596,365.880 1,539,751,101.913 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
5.970 1,539,751,101.913
BAB. VIII PENGEMB. KONDISI PEKERJAAN MINOR
8.4.(1) Marka Jalan Termoplastik M2 1,458.72 1.633 288,763.090 421,224,494.645 - 0.000 0.000 - 0.000 0.000 - 0.000 0.000
1.633 421,224,494.645
X PEKERJAAN PEMELIHARAAN RUTIN
10.1(3) Pemel. Rutin Selokan, Sal. Air, Galian & Timb. Ls 1.00 0.029 7,500,000.000 7,500,000.000 0.056 5.600 0.002 0.001 0.081 0.000 0.057 5.681 0.003
10.1(4) Pemel. Rutin Perlengkapan Jalan Ls 1.00 0.019 5,000,000.000 5,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10.1(5) Pemel. Rutin Jembatan Ls 1.00 0.023 6,000,000.000 6,000,000.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
0.072 18,500,000.000

TOTAL BOBOT 100.00 25,790,002,208.80


RENCANA 0.169 1.635
REALISASI 0.164 0.083 0.252
DEVIASI ( + / - ) -0.005 -1.383

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


SATKER PELAKSANAAN JALAN NASIONAL PROV. GORONTALO KONSULTAN SUPERVISI
KONTRAKTOR PELAKSANA
Koordinator Pengawas Lapangan PT. Yodya Karya (Persero)
PT. Karunia Jaya Sejati
FRIYANTO DAUD,ST FAIZAL MAKMUR, ST CHRISTIAN IVAN LEWA, ST
NIP : 19821006 201001 1 003 Chief Inspector / Quantity Engineer General Superintendent
JADWAL PELAKSANAAN PEKERJAAN
Kontraktor : PT. Karunia Jaya Sejati Kegiatan : PPK 04 (Limboto - Isimu - Paguyaman - Kwandang - Tolango - Paguyaman - Akses Bandara) Konsultan : PT. Yodya Karya (Persero)
No. Kontrak : HK0203/PJNPG-PPK04/541 No. Kontrak : HK.02.03/SATKER-P2JN/157/I/2014
Tanggal Kontrak : 17 Februari 2014 Nama Paket : Pelebaran Jalan Isimu - Paguyaman (Rigid Pavement) III Tanggal Kontrak : 30 Januari 2014
Nilai Kontrak : Rp. 28.369.000.000,00 Nilai Kontrak : Rp.1.367.657.500,00
No. SPMK : 597 /SPMK/PJNPG-PPK04 No. SPMK : HK.01.24/SATKER-P2JN/269/II/2014
Tanggal SPMK : 20 Februari 2014 Tanggal SPMK : 20 Februari 2014
No. Addendum : HK0203/PJNPG-PPK04/1668
Tanggal Addendum : 30 Juni 2014

BULAN
Februari Maret April Mei Juni Juli Agustus September Oktober November
Volume Harga Satuan BOBOT 20/02/14 24/02/14 03/03/14 10/03/14 17/03/14 24/03/14 31/03/14 07/04/14 14/04/14 21/04/14 28/04/14 05/05/14 12/05/14 19/05/14 26/05/14 02/06/14 09/06/14 16/06/14 23/06/14 CCO 30/06/14 07/07/14 14/07/14 21/07/14 28/07/14 04/08/14 11/08/14 18/08/14 25/08/14 01/09/14 08/09/14 15/09/14 22/09/14 29/09/14 06/10/14 13/10/14 20/10/14 27/10/14 03/11/14 10/11/14
NO. DIVISI URAIAN Sat Jumlah Harga (Rp)
Kontrak (Rp) PEK. (%) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d Vol Harga Jumlah Bobot Bobot Bobot s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d KET.
23/02/14 02/03/14 09/03/14 16/03/14 23/03/14 30/03/14 06/04/14 13/04/14 20/04/14 27/04/14 04/05/14 11/05/14 18/05/14 25/05/14 01/06/14 08/06/14 15/06/14 22/06/14 29/06/14 Satuan Real Sisa 06/07/14 13/07/14 20/07/14 27/07/14 03/08/14 10/08/14 17/08/14 24/08/14 31/08/14 07/09/14 14/09/14 21/09/14 28/09/14 05/10/14 12/10/14 19/10/14 26/10/14 02/11/14 09/11/14 16/11/14
MG. 1 MG. 2 MG. 3 MG. 4 MG. 5 MG. 6 MG. 7 MG. 8 MG. 9 MG. 10 MG. 11 MG. 12 MG. 13 MG. 14 MG. 15 MG. 16 MG. 17 MG. 18 MG. 19 MG. 20 MG. 21 MG. 22 MG. 23 MG. 24 MG. 25 MG. 26 MG. 27 MG. 28 MG. 29 MG. 30 MG. 31 MG. 32 MG. 33 MG. 34 MG. 35 MG. 36 MG. 37 MG. 38 MG. 39
1 UMUM 72,520,237.50 0.28 72,520,237.50
1.2 Mobilisasi 1.00 LS 60,180,000.00 60,180,000.00 0.23 0.041 0.041 0.041 0.041 1.000 60,180,000.00 60,180,000.00 0.233 0.160 0.073 0.035 0.038 100
1.8 Manajemen Keselamatan Lalu Lintas 1.00 LS 12,340,237.50 12,340,237.50 0.05 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 1.000 12,340,237.50 12,340,237.50 0.048 0.020 0.028 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
-
3 PEKERJAAN TANAH 2,123,980,168.01 8.24 1,585,784,967.20
3.1(1a) Galian Biasa 32,838.83 M3 47,421.10 1,557,253,441.31 6.04 0.755 0.755 0.755 0.755 0.755 0.755 0.755 0.755 19,035.48 47,421.10 902,683,400.63 3.500 2.250 1.250 0.208 0.208 0.208 0.208 0.208 0.208 CCO
3.1(1a) Galian Cadas Muda 69.82 53,296.66 3,721,172.80 0.01 0.007 0.007 69.82 53,296.66 3,721,172.80 0.014 0.010 0.004 0.004
Galian Perkerasan Beraspal Tanpa Cold Milling
3.1 (7) 1,820.95 M3 62,654.37 114,090,475.05 0.44 291.41 62,654.37
Machine 0.221 0.221 18,258,109.96 0.071 0.070 0.001 0.001
3.2. (1) Timbunan Biasa 3,748.68 M3 102,757.81 385,206,147.19 1.49 4,309.88 102,757.81 442,873,830.16 1.717 0.260 1.457 0.243 0.243 0.243 0.243 0.243 0.243
Timbunan Pilihan 172,863.00 894.00 172,863.00 154,539,522.00 0.599 0.000 0.599 0.150 0.150 0.150 0.150
3.3 (1) Penyiapan Badan Jalan 11,567.50 M2 5,507.58 63,708,931.65 0.25 0.041 0.041 0.041 0.041 0.041 0.041 11,567.50 5,507.58 63,708,931.65 0.247 0.240 0.007 0.007
Kurva Rencana Awal -
4 PELEBARAN PERKERASAN DAN BAHU JALAN 462,810,379.82 1.79 465,216,672.96
4.2(2b) Lapis Pondasi Agregat Klas S 1,384.80 M3 334,207.38 462,810,379.82 1.79 1,392.00 334,207.38 465,216,672.96 1.804 0.000 1.804 0.361 0.361 0.361 0.361 0.361
-
5 PERKERASAN BERBUTIR 21,151,215,826.92 82.01 21,151,215,826.92
5.1(2) Lapis Pondasi Agregat Klas B 2,436.00 M3 392,761.56 956,767,160.16 3.71 0.618 0.618 0.618 0.618 0.618 0.618 2,436.00 392,761.56 956,767,160.16 3.710 2.880 0.830 0.104 0.104 0.104 0.104 0.104 0.104 0.104 0.104
5.3(1) Perkerasan Beton Semen 8,746.92 M3 1,960,373.00 17,147,225,801.16 66.49 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 2.770 8,746.92 1,960,373.00 17,147,225,801.16 66.488 19.820 46.668 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899 3.88899
5.3(3) Lapis Pondasi Bawah Beton Kurus 3,239.60 M3 940,617.01 3,047,222,865.60 11.82 1.477 1.477 1.477 1.477 1.477 1.477 1.477 1.477 3,239.60 940,617.01 3,047,222,865.60 11.816 4.5 7.316 0.732 0.732 0.732 0.732 0.732 0.732 0.732 0.732 0.732 0.732
-
PERKERASAN ASPAL 30,169,661.32
6.1.1a Lapis Resap Pengikat - Aspal Cair 84.00 13,888.95 1,166,671.76 0.005 0.005 0.002 0.002
50
6.1.2.a Lapis Perekat - Aspal Cair 15.75 13,761.00 216,735.75 0.001 0.001 0.000 0.000
6.3..5a Laston Lapis Aus (AC-WC) 9.01 491,139.26 4,425,164.75 0.017 0.017 0.009 0.009
6.3.6a Laston Lapis Antara (AC-BC) 13.65 479,351.25 6,543,144.56 0.025 0.025 0.013 0.013
6.3.8a Aspal Keras 1.36 12,644,250.00 17,196,180.00 0.067 0.067 0.033 0.033
6.3.9 Aditif Anti Pengelupasan 1.82 55,000.00 100,100.00 0.000 0.000 0.000 0.000
6.3.10b Bahan Pengisi Filler Tambahan Semen 461.65 1,130.00 521,664.50 0.002 0.002 0.001 0.001

7 STRUKTUR 1,539,751,101.91 5.97 1,823,461,684.80


7.1.5 Beton Mutu Tinggi fc'20Mpa (K250) 1,637,182.36 98.50 1,637,182.36 161,262,462.50 0.625 0.625 0.21 0.21 0.21
7.3.1 Baja Tulangan U24 polos 14,137.00 10,524.92 14,137.00 148,790,794.04 0.577 0.577 0.19 0.19 0.19
7.9.1 Pasangan Batu 2,581.89 M3 596,365.88 1,539,751,101.91 5.97 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 0.398 2,537.72 596,365.88 1,513,408,428.26 5.868 2.370 3.498 0.583 0.583 0.583 0.583 0.583 0.583
-
8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 421,224,494.64 1.63 643,133,154.05
8.4(1) Marka Jalan Thermoplastic 1,458.72 M2 288,763.09 421,224,494.64 1.63 2,227.20 288,763.09 643,133,154.05 2.494 2.494 0.831 0.831 0.831
-
10 PEKERJAAN PEMELIHARAAN RUTIN 18,500,000.00 0.07 18,500,000.00
Pemeliharaan Rutin Selokan, Saluran Air, Galian
10.1(3) dan Timbunan
1.00 LS 7,500,000.00 7,500,000.00 0.03 7,500,000.00
0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 1.000 7,500,000.00 0.029 0.010 0.019 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
10.1(4) Pemeliharaan Rutin Perlengkapan Jalan 1.00 LS 5,000,000.00 5,000,000.00 0.02 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 1.000 5,000,000.00 5,000,000.00 0.019 0.010 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
10.1(5) Pemeliharaan Rutin Jembatan 1.00 LS 6,000,000.00 6,000,000.00 0.02 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 1.000 6,000,000.00 6,000,000.00 0.023 0.023 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
0
A. Jumlah 25,790,002,208.80 100.00 25,790,002,204.75 100.000 32.600 67.400
2.280 6.313 6.313 5.913 5.913 1.881 0.840 4.729 4.625 4.625 3.893 3.893 0.004 0.424 5.144 5.085 5.120 0.403 0.001 0.001
Komulatif Progres Rencana Awal (%) - 0.042 0.086 0.734 1.388 2.003 2.892 3.782 5.069 7.833 10.535 14.926 20.190 24.582 29.439 34.296 38.707 43.962 48.369 32.600 34.880 41.193 47.507 53.419 59.332 61.213 62.052 66.781 71.406 76.030 79.924 83.817 83.821 84.245 89.389 94.474 99.594 99.997 99.999 100.000
B. Progres Rencana Percepatan (%) - 0.041 0.043 0.085 1.466 2.9018 3.116 4.807 6.063 4.545 5.403 5.403 4.649 4.649 4.649 3.172 3.172 3.172 3.172
C. Kumulatif Progres Rencana Percepatan (%) - 0.041 0.084 0.169 1.635 4.537 7.652 12.460 18.523 23.067 28.471 33.874 38.523 43.172 47.820 50.992 54.164 57.336 60.507
D. Progres Realisasi (%)
E. Kumulatif Progres Realisasi (%)
F. Deviasi Progres Pekerjaan (%)

PPK 04 KONSULTAN SUPERVISI KONTRAKTOR PELAKSANA


PJN GORONTALO PT. YODYA KARYA (PERSERO) PT. KARUNIA JAYA SEJATI

YUDHIR UMAR, ST. MMT Ir. BERNADUS BG. MANGIN CHRISTIAN IVAN LEWA, ST
NIP. 110 054 094 SITE ENGINEER GENERAL SUPERINTENDENT