AKTUAL PEKERJAAN
NO DESKRIPSI VOLUME SATUAN
1 GALIAN 38.128 M3
2 LC 31.48 M3
3 BETON K-450 13.96425 M3
4 BESI BETON 2502.962381 KG
5 BEKISTING 140.208 M2
6 JASA PENGECORAN 0
7 ANCHOR M20 192 Pcs
8 Grouting 2.352 M3
56 Pcs
0.686 M3
DKC1
NO DESKRIPSI VOLUME SATUAN
1 GALIAN 26.928 M3
2 LC 24.48 M3
3 BETON K-450 10.438 M3
4 BESI BETON 1772.932 KG
5 BEKISTING 99.314 M2
6 JASA PENGECORAN
7 ANCHOR M20 136 Pcs
8 Grouting 1.666 M3
DKC2
NO DESKRIPSI VOLUME SATUAN
1 GALIAN 11.2 M3
2 LC 7 M3
3 BETON K-450 3.52625 M3
4 BESI BETON 730.0307 KG
5 BEKISTING 40.894 M2
6 JASA PENGECORAN
7 ANCHOR M20 56 Pcs
8 GRROUTING 0.686 M3
GALIAN TANAH
SITE P L T TITIK VOLUME
DKC1 1.2 1.2 0.55 34 26.928
DKC2 1 1 0.8 14 11.2
K-450
SITE P L T TITIK VOLUME VOLUME TOTAL
DKC1 POO 0.8 0.8 0.25 34 5.44
10.438
COLOUM 0.35 0.35 1.2 34 4.998
DKC2 POO 0.8 0.8 0.25 14 2.24
3.52625
COLOUM 0.35 0.35 0.75 14 1.28625
LC
SITE P L T TITIK VOLUME
DKC1 1.2 1.2 0.5 34 24.48
DKC2 1 1 0.5 14 7
BEKISTING
SITE P L TITIK VOLUME TOTAL VOLUME
POO 0.8 0.25 68 13.6
0.818 0.25 68 13.906
DKC1 99.314
COLOUM 0.35 1.2 68 28.56
0.53 1.2 68 43.248
POO 0.8 0.25 28 5.6
0.818 0.25 28 5.726
DKC2 40.894
COLOUM 0.35 1.2 28 11.76
0.53 1.2 28 17.808
GROUTING
SITE P L T JUMLAH TITIK VOLUME
DKC1 0.35 0.35 0.4 34 1.666
DKC2 0.35 0.35 0.4 14 0.686
PEMBESIAN DKC1
D JUMLAH TULANGAN PANJANG TULANGAN VOLUME
MENERUS 16 4 1.38 8.711885
SENGKANG 16 8 0.92 0.006165 11.61585
FOOTING 16 12 1.68 31.81732
PEMBESIAN DKC2
D JUMLAH TULANGAN PANJANG TULANGAN VOLUME
MENERUS 16 4 1.38 8.711885
SENGKANG 16 8 0.92 0.006165 11.61585
FOOTING 16 12 1.68 31.81732
34 1772.9316864
14 730.0306944
14 27816.2906112