DATA TENAGA HARIAN SUBKON

DIVISI SAPPHIRE MANSION KARANGRAU


PERIODE : 30 SEPTEMBER - 06 OKTOBER 2022
HARI/TANGGAL
HARGA
NO NAMA SUBKON JABATAN 30-Sep 1-Oct 2-Oct 3-Oct 4-Oct 5-Oct 6-Oct JUMLAH TOTAL KETERANGAN
SATUAN
JUMAT SABTU MINGGU SENIN SELASA RABU KAMIS
TUKANG 8 8 OFF 8 8 8 8 Rp 85,000 48 Rp 4,080,000 RUKO A1, RUKO A2, A4-18
1 SUKIR
TENAGA 3 3 OFF 3 3 3 3 Rp 70,000 18 Rp 1,260,000 RUKO A1, RUKO A2, A4-18
TUKANG 6 6 OFF 6 6 6 6 Rp 85,000 36 Rp 3,060,000 A2-55, A1-8, A1-9
2 TARSAM
TENAGA 3 3 OFF 3 3 3 3 Rp 70,000 18 Rp 1,260,000 A2-55, A1-8, A1-9
TUKANG 1 1 OFF 1 1 1 1 Rp 85,000 6 Rp 510,000 A2-25,RUKO 3A, RUKO 4A
3 WARDIONO
TENAGA 1 1 OFF 1 1 1 1 Rp 70,000 6 Rp 420,000 A2-25,RUKO 3A, RUKO 4A
TUKANG 9 9 OFF 9 9 9 9 Rp 85,000 54 Rp 4,590,000 A5-34, A5-39,A5-48,A2-17,A2-18
4 TOMO
TENAGA 4 4 OFF 4 4 4 4 Rp 70,000 24 Rp 1,680,000 A5-34, A5-39,A5-48,A2-17,A2-18
TUKANG 1 1 OFF 1 1 1 1 Rp 85,000 6 Rp 510,000 A5-38,A5-47, A1-1, A3-11
5 SUKIRAN
TENAGA 1 1 OFF 1 1 1 1 Rp 70,000 6 Rp 420,000 A5-38,A5-47, A1-1, A3-11
TUKANG 0 0 OFF 0 0 0 0 Rp 85,000 0 Rp - A2-21,A4-20
6 ANDRI
TENAGA 0 0 OFF 0 0 0 0 Rp 70,000 0 Rp - A2-21,A4-20

Diketahui, Dibuat,

PRAMA BAGAS ANDREAN SANGAJI


Perencanaan QA
DAFTAR ABSEN HARIAN TENAGA KERJA
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU
TAHAP 1
PERIODE TANGGAL : 30 SEPTEMBER - 06 OKTOBER 2022
HARIAN KANTOR PERBAIKAN
HARI /TANGGAL JUMLAH
UPAH PER-HOK JUMLAH
NO NAMA JABATAN JUMAT SABTU MINGGU SENIN SELASA RABU KAMIS PEMBAYARAN POTONG SUBKON
(Rp) HOK
30 1 2 3 4 5 6 (Rp)
BLOK SUBKON
1 SARWO TUKANG 70,000 1 1 - 1 1 1 1 6.0 420,000
2 SITO TUKANG 70,000 1 1 - 1 1 1 1 6.0 420,000

NOTA : Terlampir
840,000
JUMLAH TOTAL PEMBAYARAN Rp 840,000
Jumlah Dibulatkan

Purwokerto, 06 Oktober 2022


Disetujui Diperiksa oleh, Diabsen oleh,

IBNU PURWANTO PRAMA BAGAS ANDREAN SANGAJI


BM Jabagsel PERENCANAAN PELAKSANA
KET :
JUM'AT : Pekerjaan pembuatan nat lantai dan pembersihan lantai & kaca blok A3-11
SABTU : Pekerjaan pembuatan nat lantai dan pembersihan lantai & kaca blok A3-11
MINGGU :-
SENIN : Pekerjaan perataan taman dan urugan taman blok A3-12
SELASA : Pembersihan dan langsir alat kerja ke bedeng dari blok A5-39 & A3-11
RABU : Pekerjaan langsir urugan blok A5-47
KAMIS : Pekerjaan langsir urugan dan pembersihan rumah blok A5-47
REKAP PENGAJUAN SABTUAN ALL IN
SAPPHIRE MANSION KARANGRAU
SUBKON : SUKIR
TANGGAL : 30 SEPTEMBER -06 OKTOBER 2022

PROGRES NILAI PEKERJAAN


NO BLOK NILAI KONTRAK retensi 5% URAIAN PEKERJAAN KETERANGAN
minggu lalu minggu ini deviasi TENAGA

1 RUKO 1A Rp 363,750,000 60.20% 62.09% 1.89% Rp 1,718,719 Rp 85,936


2 RUKO 2A Rp 363,750,000 60.50% 63.54% 3.04% Rp 2,764,500 Rp 138,225
3 A4-18 Rp 164,904,000 43.84% 45.18% 1.34% Rp 552,428 Rp 27,621

Rp 5,035,647 Rp 251,782
Nilai Pengajuan (A) Rp 5,035,647
Sisa Pengajuan Minggu Lalu (B) Rp -
Retensi 5% (C) Rp 251,782
Tenaga TK.Kayu (F) Rp -
Tenaga Rakit besi Rp -
Pencairan Minggu Lalu Rp -
Rp -
Rp -
Rp -

Jumlah Yang Harus Dibayar (A)+(B)-(C+D)=(D) Rp 4,783,865

MENGETAHUI Dibuat, 06 Okt 2022

…...................... BAGAS ANDREAN S


Koordinator Area Teknik
REKAP PENGAJUAN SABTUAN ALL IN
SAPPHIRE MANSION KARANGRAU
SUBKON : TARSAM
TANGGAL : 30 SEPTEMBER -06 OKTOBER 2022

PROGRES NILAI PEKERJAAN


NO BLOK NILAI KONTRAK retensi 5% URAIAN PEKERJAAN KETERANGAN
minggu lalu minggu ini deviasi TENAGA

1 A1-1 Rp 627,234,000 47.90% 49.05% 1.15% Rp 1,803,298 Rp 90,165


2 A1-8 Rp 586,850,000 86.22% 86.89% 0.67% Rp 982,974 Rp 49,149
3 A1-9 Rp 625,978,000 47.60% 48.87% 1.27% Rp 1,987,480 Rp 99,374

Rp 4,773,752 Rp 238,688
Nilai Pengajuan (A) Rp 4,773,752
Sisa Pengajuan Minggu Lalu (B) Rp -
Retensi 5% (C) Rp 238,688
Tenaga TK.Kayu (F) Rp -
Tenaga Rakit besi Rp -
Pencairan Minggu Lalu Rp -
Rp -
Rp -
Rp -

Jumlah Yang Harus Dibayar (A)+(B)-(C+D)=(D) Rp 4,535,064

MENGETAHUI Dibuat, 06 Okt 2022

…...................... BAGAS ANDREAN S


Koordinator Area Teknik
REKAP PENGAJUAN SABTUAN ALL IN
SAPPHIRE MANSION KARANGRAU
SUBKON : WARDIONO
TANGGAL : 30 SEPTEMBER -06 OKTOBER 2022

PROGRES NILAI PEKERJAAN


NO BLOK NILAI KONTRAK retensi 5% URAIAN PEKERJAAN KETERANGAN
minggu lalu minggu ini deviasi TENAGA

1 RUKO 3A Rp 375,000,000 23.55% 24.45% 0.90% Rp 843,750 Rp 42,188


2 RUKO 4A Rp 375,000,000 23.88% 24.35% 0.47% Rp 440,625 Rp 22,031
3 A3-9 Rp 180,000,000 93.96% 93.96% 0.00% Rp - Rp -

Rp 1,284,375 Rp 64,219
Nilai Pengajuan (A) Rp 1,284,375
Sisa Pengajuan Minggu Lalu (B) Rp -
Retensi 5% (C) Rp 64,219
Tenaga TK.Kayu (F) Rp -
Tenaga Rakit besi Rp -
Pencairan Minggu Lalu Rp -
Rp -
Rp -
Rp -

Jumlah Yang Harus Dibayar (A)+(B)-(C+D)=(D) Rp 1,220,156

MENGETAHUI Dibuat, 06 Okt 2022

…...................... BAGAS ANDREAN S


Koordinator Area Teknik
REKAP PENGAJUAN SABTUAN ALL IN
SAPPHIRE MANSION KARANGRAU
SUBKON : TOMO
TANGGAL : 30 SEPTEMBER -06 OKTOBER 2022

PROGRES NILAI PEKERJAAN


NO BLOK NILAI KONTRAK retensi 5% URAIAN PEKERJAAN KETERANGAN
minggu lalu minggu ini deviasi TENAGA

1 A2-17 Rp 399,299,600 79.76% 79.76% 0.00% Rp - Rp -


2 A2-18 Rp 268,727,100 53.07% 54.71% 1.64% Rp 1,101,781 Rp 55,089
3 A2-27 Rp 233,949,050 29.71% 35.60% 5.89% Rp 3,444,900 Rp 172,245
4 A5-39 Rp 161,680,000 100.00% 100.00% 0.00% Rp - Rp -

Rp 4,546,681 Rp 227,334
Nilai Pengajuan (A) Rp 4,546,681
Sisa Pengajuan Minggu Lalu (B) Rp -
Retensi 5% (C) Rp 227,334
Tenaga TK.Kayu (F) Rp -
Tenaga Rakit besi Rp -
Pencairan Minggu Lalu Rp -
Rp -
Rp -
Rp -

Jumlah Yang Harus Dibayar (A)+(B)-(C+D)=(D) Rp 4,319,347

MENGETAHUI Dibuat, 06 Okt 2022

…...................... BAGAS ANDREAN S


Koordinator Area Teknik
REKAP PENGAJUAN SABTUAN ALL IN
SAPPHIRE MANSION KARANGRAU
SUBKON : SUKIRAN
TANGGAL : 30 SEPTEMBER -06 OKTOBER 2022

PROGRES NILAI PEKERJAAN


NO BLOK NILAI KONTRAK retensi 5% URAIAN PEKERJAAN KETERANGAN
minggu lalu minggu ini deviasi TENAGA

1 A3-11 Rp 241,868,150 100.00% 100.00% 0.00% Rp - Rp -


2 A5-47 Rp 144,000,000 97.98% 97.98% 0.00% Rp - Rp -

Rp - Rp -
Nilai Pengajuan (A) Rp -
Sisa Pengajuan Minggu Lalu (B) Rp -
Retensi 5% (C) Rp -
Tenaga TK.Kayu (F) Rp -
Tenaga Rakit besi Rp -
Pencairan Minggu Lalu Rp -
Rp -
Rp -
Rp -

Jumlah Yang Harus Dibayar (A)+(B)-(C+D)=(D) Rp -

MENGETAHUI Dibuat, 06 Okt 2022

…...................... BAGAS ANDREAN S


Koordinator Area Teknik
REKAP PENGAJUAN SABTUAN ALL IN
SAPPHIRE MANSION KARANGRAU
SUBKON : ANDRI
TANGGAL : 30 SEPTEMBER -06 OKTOBER 2022

PROGRES NILAI PEKERJAAN


NO BLOK NILAI KONTRAK retensi 5% URAIAN PEKERJAAN KETERANGAN
minggu lalu minggu ini deviasi TENAGA

1 A2-21 Rp 297,051,000 86.84% 86.84% 0.00% Rp - Rp -


2 A3-23 Rp 183,000,000 91.74% 91.74% 0.00% Rp - Rp -

Rp - Rp -
Nilai Pengajuan (A) Rp -
Sisa Pengajuan Minggu Lalu (B) Rp -
Retensi 5% (C) Rp -
Tenaga TK.Kayu (F) Rp -
Tenaga Rakit besi Rp -
Pencairan Minggu Lalu Rp -
Rp -
Rp -
Rp -

Jumlah Yang Harus Dibayar (A)+(B)-(C+D)=(D) Rp -

MENGETAHUI Dibuat, 06 Okt 2022

…...................... BAGAS ANDREAN S


Koordinator Area Teknik
OPNAM FASUM / INFRASTRUKTUR DIVISI KONTRUKSI DIVISI
SAPPHIRE MANSION KARANGRAU PURWOKERTO
KONSTRUKSI
PERIODE : 06 OKTOBER 2022

Nama Pekerjaan : Pekerjaan Pemeliharaan Jalan Paving


No. IM : SUBKON
Subkon : TOFIK
Blok : A2-21, A2-20, A2-11, A2-12, A2-10 & Jalan utama
10
Prestasi Pekerjaan Sisa Kontrak
Total Pengajuan
Opname Minggu Lalu Opname Minggu Ini
Harga Total Nilai
No. Nama Pekerjaan Volume sat
Satuan Pekerjaan Volume
Volu
me Jumlah Harga Volume Jumlah Harga Volume Jumlah Harga Jumlah Harga
A PEKERJAAN PEMELIHARAAN JALAN
1 Bongkar pasang paving jalan 76.06 M2 Rp 20,000 Rp 1,521,200 - Rp - 76.06 Rp 1,521,200 76.06 Rp 1,521,200 - Rp -
2 Pemasangan bata saluran 13.00 M2 Rp 4,000 Rp 52,000 - Rp - 13.00 Rp 52,000 13.00 Rp 52,000 - Rp -
3 Kancingan paving 13.00 M3 Rp 2,000 Rp 26,000 - Rp - 13.00 Rp 26,000 13.00 Rp 26,000 - Rp -

Jumlah Rp - Rp 1,599,200 Rp 1,599,200 Rp -


Purwokerto Thursday, September 29, 2022
Diketahui oleh, Diperiksa oleh, Diajukan oleh, Dibuat oleh,

IBNU PURWANTO PRAMA TOFIK BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DAFTAR ABSEN HARIAN PERCEPATAN PEKERJAAN
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU
PERIODE TANGGAL : 2 OKTOBER - 8 OKTOBER 2022
SUB.PEKERJAAN : Trisno
POTONG SUBKON
NO REKENING PEMBAYARAN : CASH
BLOK /SUBKON RUMAH : A2-21 Andriyanto
ANDRIYANTO BLOK A2-
TANGGAL PENGAJUAN : Kamis, 06 Oktober 2022 21
1 HARIAN PERCEPATAN
HARI /TANGGAL JUMLAH
UPAH PER- JUMLA
NO NAMA JABATAN MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU PEMBAYARAN POTONG SUBKON
HOK (Rp) H HOK
2 3 4 5 6 7 8 (Rp)
PENYELESAIAN BLOK SUBKON
1 Trisno KEPALA TUKANG 100,000 - - - - 1 1 1 3 300,000
2 Risman TUKANG 85,000 - - - - 1 1 1 3 255,000
3 Slamet TUKANG 85,000 - - - - 1 1 1 3 255,000
4 Parsun KENEK 70,000 - - - - 1 1 1 3 210,000
5 Widodo KENEK 70,000 - - - - 1 1 1 3 210,000

1,230,000
JUMLAH TOTAL PEMBAYARAN Rp 1,230,000
Jumlah Dibulatkan
Kamis, 06 Oktober 2022
Disetujui Diperiksa oleh, Diabsen oleh,

IBNU PURWANTO PRAMA BAGAS ANDREAN SANGAJI


BM Jabagsel PERENCANAAN PELAKSANA
KET : MINGGU :
SENIN :
SELASA :
RABU :
KAMIS : Pekerjaan plesteran dan acian dinding dalam
JUM'AT : Pekerjaan plesteran dan acian dinding dalam
SABTU : Pekerjaan plesteran dan acian dinding luar depan & belakang
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER PEKERJAAN KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
SUB.PEKERJAAN : YOYO (Sub borong tenaga + material pasang)
NO REKENING PEMBAYARAN : CASH POTONG SUBKON
BLOK /SUBKON RUMAH : A1-8 TARSAM TARSAM BLOK A1-8
TANGGAL PENGAJUAN : 06 Oktober 2022

HARGA SATUAN JUMLAH HARGA


NO PEKERJAAN BLOK VOLUME SATUAN KETERANGAN PEKERJAAN
(Rp) (Rp)

PERBAIKAN
1 Pekerjaan plafon flat A1-8 134.5 m2 20,000 2,690,000 PROGRES 100%
2 Pekerjaan drop seling A1-8 38.2 m2 25,000 955,000
3 Pekerjaan tali air A1-8 250 m2 3,500 875,000

JUMLAH TOTAL PEMBAYARAN 4,520,000 LUNAS

Purwokerto, 06 Oktober 2022


Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

IBNU PURWANTO PRAMA YOYO BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
PEKERJAAN : URUGAN
SUB.PEKERJAAN : DADU (Suplaiyer)
NO REKENING PEMBAYARAN
: CASH
TANGGAL PENGAJUAN : 6-Oct-22 SUPLAIYER

HARGA
JUMLAH KETERANGAN
NO TANGGAL DRIVER VOLUME SATUAN SATUAN
HARGA (Rp) PEKERJAAN
(Rp)
URUGAN KAVLING

Langsir bata merah ke A4-


1 29-Sep-22 3500 bh 90 315,000
18
2 29-Sep-22 1 Rit 200,000 200,000 Langsir precast
3 3-Oct-22 1 Rit 215,000 215,000 A4-18

JUMLAH TOTAL PEMBAYARAN 3502 RIT 730,000

Purwokerto, 6-Oct-2022
Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

IBNU PURWANTO PRAMA DADU BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER PEKERJAAN KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
SUB.PEKERJAAN : BAGYO (Sub Borong Tenaga)
NO REKENING PEMBAYARAN : CASH POTONG SUBKON
BLOK /SUBKON RUMAH : A3-11 SUKIRAN SUKIRAN BLOK A3-11
TANGGAL PENGAJUAN : 06 Oktober 2022
HARGA
SATU JUMLAH
NO PEKERJAAN BLOK VOLUME SATUAN KETERANGAN PEKERJAAN
AN HARGA (Rp)
(Rp)
PERBAIKAN
1 Perbaikan cat interior A3-11 61.7 m2 5,000 308,500 PROGRES 100%

JUMLAH TOTAL PEMBAYARAN 308,500 LUNAS

Purwokerto, 06 Oktober 2022


Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

IBNU PURWANTO PRAMA BAGYO BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER PEKERJAAN KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
SUB.PEKERJAAN : BAGYO (Sub Borong Tenaga) POTONG SUBKON
NO REKENING PEMBAYARAN : CASH
BLOK /SUBKON RUMAH : A3-9 WARDIONO
WARDIONO BLOK A3-
TANGGAL PENGAJUAN : 06 Oktober 2022 9
HARGA
SATU JUMLAH
NO PEKERJAAN BLOK VOLUME SATUAN KETERANGAN PEKERJAAN
AN HARGA (Rp)
(Rp)
PERBAIKAN
1 Bongkar pasang genteng A3-9 3 m2 25,000 75,000 PROGRES 100%
Pekerjaan acian ban
2 A3-9 1.3 m2 15,000 19,500
banan

JUMLAH TOTAL PEMBAYARAN 94,500 LUNAS

Purwokerto, 06 Oktober 2022


Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

IBNU PURWANTO PRAMA BAGYO BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER PEKERJAAN KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
SUB.PEKERJAAN : DODI (Sub Borong Tenaga)
NO REKENING PEMBAYARAN : CASH POTONG SUBKON
BLOK /SUBKON RUMAH : A3-11 SUKIRAN SUKIRAN BLOK A3-11
TANGGAL PENGAJUAN : 06 Oktober 2022
HARGA
SATUA JUMLAH
NO PEKERJAAN BLOK VOLUME SATUAN KETERANGAN PEKERJAAN
N HARGA (Rp)
(Rp)
PERBAIKAN
1 Pemasangan floordrain A3-11 1 bh 15,000 15,000
2 Plester aci dinding luar A3-11 0.6 m2 50,000 30,000
3 Pekerjaan kompound plafon A3-11 5 m2 5,000 25,000
4 Bongkar pasang genteng A3-11 2 m2 25,000 50,000
5 Pekerjaan acian ban banan A3-11 5 m2 15,000 75,000
6 Pemasangan exhaustfan A3-11 1 ls 75,000 75,000
JUMLAH TOTAL PEMBAYARAN 270,000 LUNAS

Purwokerto, 06 Oktober 2022


Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

…............................... PRAMA DODI BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER PEKERJAAN KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
SUB.PEKERJAAN : DODI (Sub Borong Tenaga)
NO REKENING PEMBAYARAN : CASH
BLOK /SUBKON RUMAH : A3-4
POTONG PROPERTY
TANGGAL PENGAJUAN : 06 Oktober 2022
HARGA
SATUA JUMLAH
NO PEKERJAAN BLOK VOLUME SATUAN KETERANGAN PEKERJAAN
N HARGA (Rp)
(Rp)
PERBAIKAN
1 Instalasi water turen A3-4 1 bh 125,000 125,000

JUMLAH TOTAL PEMBAYARAN 125,000 LUNAS

Purwokerto, 06 Oktober 2022


Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

IBNU PURWANTO PRAMA DODI BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
DIVISI KONTRUKSI DIVISI
OPNAM SUPLAIYER PEKERJAAN KONSTRUKSI
PEMBANGUNAN PERUMAHAN "SAPPHIRE MANSION" KARANGRAU -PURWOKERTO
1
SUB.PEKERJAAN : EDI (Sub borong tenaga)
NO REKENING PEMBAYARAN : CASH POTONG SUBKON
BLOK /SUBKON RUMAH : A5-47 SUKIRAN SUKIRAN BLOK A5-47
TANGGAL PENGAJUAN : 06 Oktober 2022
HARGA
JUMLAH
NO PEKERJAAN BLOK VOLUME SATUAN SATUAN KETERANGAN PEKERJAAN
HARGA (Rp)
(Rp)
PERBAIKAN
Pekerjaan pemasangan closet
1 A5-47 1 bh 200,000 200,000 PROGRES 100%
duduk
2 Pemasangan floordrain A5-47 1 bh 15,000 15,000
3 Pemasangan hand shower + railing A5-47 1 set 75,000 75,000
4 Pemasangan keramik dinding A5-47 4 m2 30,000 120,000
5 Pemasangan keramik lantai A5-47 1 m2 30,000 30,000
6 Pemasangan pintu kamar mandi A5-47 1 set 75,000 75,000

JUMLAH TOTAL PEMBAYARAN 515,000 LUNAS

Purwokerto, 06 Oktober 2022


Diketahui oleh, Diperiksa Diajukan oleh, Di buat,

IBNU PURWANTO PRAMA EDI BAGAS ANDREAN SANGAJI


BM Jabagsel Perencanaan Subkon QA
OPNAM FASUM / INFRASTRUKTUR DIVISI KONTRUKSI DIVISI
SAPPHIRE MANSION KARANGRAU PURWOKERTO
KONSTRUKSI
PERIODE : 06 OKTOBER 2022

Nama Pekerjaan : Pekerjaan Plesteran Kolom Pagar


No. IM : SUBKON
Subkon Fasum : BUANG (Sub Borong Tenaga)
Blok : Pagar depan tahap 1 blok A4

Prestasi Pekerjaan Sisa Kontrak


Harga Total Nilai Pengajuan Minggu Ini
No. Nama Pekerjaan Volume sat Adend Opname Minggu Lalu Opname Minggu Ini
Satuan Pekerjaan Volume
um Volume Jumlah Harga Volume Jumlah Harga Volume Jumlah Harga Jumlah Harga
PAGAR KELILING PAS BATA
Pekerjaan plesteran kolom
- Rp - 63.00 Rp 2,205,000 63.00 Rp 2,205,000 - Rp -
1 pagar 63.00 m2 Rp 35,000 Rp - Rp 2,205,000

Jumlah Rp 2,205,000 Rp - Rp 2,205,000 Rp 2,205,000 Rp -

Purwokerto Thursday, October 6, 2022


Diketahui oleh, Diperiksa oleh, Diajukan oleh, Dibuat oleh,

…........................ Prama BUANG BAGAS ANDREAN S


BM Jabagsel Perencanaan Subkon QA