PROJECT : PEKERJAAN PASANG KERAMIK

OWNER : LAPORAN HARIAN


LOKASI : 703 HARI KE 1
TANGGAL :
Tanggal 29 September 2022
LUAS AREA :-

REALISASI KEMAJUAN PEKERJAAN

HARI LALU HARI INI S/D HARI INI REALISASI


NO RINCIAN KEGIATAN DAN PEKERJAAN VOLUME SATUAN BOBOT
(%)
PERSENTASE PERSENTASE PERSENTASE
VOLUME VOLUME VOLUME
PROGRES (%) PROGRES (%) PROGRES (%)

I PEKERJAAN PENDAHULUAN
1 Pengukuran Exixting 1.00 Ls
2 Mobilisasi Demobilsasi 1.00 Ls
3 Pembersihan Lahan 1.00 Ls
4 Man Power Org 6.0
5 Unit Alat Berat Unit

II PEKERJAAN PASANG KERAMIK Lt. 1


1 Pasang Keramik 60 x 60 cm (Luas Area 35.36 M2) 98 Keping - 0.00% 44.0 44.90% 44.0 44.90% 44.90%
2 Mortar -
2.1 Pasir 2,227 Kg - 0.00% 1,000.1 44.90% 1,000.1 44.90% 44.90%
2.2 Semen 368 Kg - 0.00% 165.1 44.90% 165.1 44.90% 44.90%
2.3 Semen Warna 53 Kg - 0.00% - 0.00% - 0.00% 0.00%

III PEKERJAAN PASANG KERAMIK Lt. 2


1 Pasang Keramik 60 x 60 cm (Luas Area 16.63.26 M2) 46 Keping - 0.00% - 0.00% - 0.00% 0.00%
2 Mortar -
2.1 Pasir 1,048 Kg - 0.00% - 0.00% - 0.00% 0.00%
2.2 Semen 173 Kg - 0.00% - 0.00% - 0.00% 0.00%
2.3 Semen Warna 25 Kg - 0.00% - 0.00% - 0.00% 0.00%

VIII PEKERJAAN FINISHING


1 Pekerjaan Lain - lain 1.00 Ls
2 Pembersihan Akhir 1.00 Ls