RENCANA ANGGARAN BIAYA SUMUR BOR 24 METER KELAS STANDAR

Jasa dan Material Bahan Pipa

A. PEKERJAAN JASA
HARGA SATUAN
NO URAIAN PEKERJAAN VOLUME SATUAN TOTAL KET
@ Rp.
1. Pengeboran pilot hole diameter (Ø) 4" 36 m 150,000.00 5,400,000.00 Jasa
2. Mobilisasi dan Akomodasi 2 LOT - - Jasa
TOTAL PEKERJAAN JASA (A) 5,400,000.00

A. MATERIAL DAN POMPA


HARGA SATUAN
NO URAIAN PEKERJAAN VOLUME SATUAN @ Rp. TOTAL KET

I MATERIAL
1. Pipa PVC AW diameter (Ø) 3" 6 bgt 200,000.00 1,200,000.00 champion
2. Pipa PVC AW diameter (Ø) 3/4" 6 btg 35,000.00 210,000.00 champion
3. SDL (sochet drat luar) 3/4" 2 bh 5,000.00 10,000.00 champion
4. SDD (sochet drat dalam) 3/4" 2 bh 5,000.00 10,000.00 champion
5. Knee 3/4" 2 bh 5,000.00 10,000.00 champion
6. Stop Kran 3/4" 1 bh 15,000.00 15,000.00
7. Lem PVC 1 klg 25,000.00 25,000.00 Isarplas
8. Seltip 2 roll 5,000.00 10,000.00
9. Tusen Klep Kuningan 1" 1 bh 35,000.00 35,000.00
10. SDL (sochet drat luar) 1" X 3/4" 2 BH - -

II POMPA SET
1. Pompa Kecil 1 bh 450,000.00 - -
TOTAL MATERIAL DAN POMPA (B) 1,525,000.00
GRAN TOTAL A + B 6,925,000.00

Pekanbaru, 09 Oktober 2022


By, Putra Teknik (Hp/ WA: 0821 6976 3028)