LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI UPTD Rumoh Seujahtera Beujroh Meukarya
UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
INSTANSI Dinas Sosial Aceh
DINAS SOSIAL ACEH
Alamat Jl. Sultan Iskandar Muda No. 49 Banda Aceh
Tahun Anggaran 2022
KONTRAKTOR PELAKSANA
Nama Perusahaan CV. INDRA PRATAMA
Penanggung Jawab INDRA MUTAHAR
Jabatan Direktur
Alamat Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PERIODE TANGGAL
MINGGU 1 27 APRIL 2022 S/D 3 MEI 2022
MINGGU 2 4 MEI 2022 S/D 11 MEI 2022
MINGGU 3 12 MEI 2022 S/D 18 MEI 2022
MINGGU 4 19 MEI 2022 S/D 25 MEI 2022
MINGGU 5 26 MEI 2022 S/D 1 JUNI 2022
MINGGU 6 2 JUNI 2022 S/D 8 JUNI 2022
MINGGU 7 9 JUNI 2022 S/D 15 JUNI 2022
MINGGU 8 16 JUNI 2022 S/D 22 JUNI 2022
MINGGU 9 23 JUNI 2022 S/D 29 JUNI 2022
MINGGU 10 30 JUNI 2022 S/D 6 JULI 2022
MINGGU 11 7 JULI 2022 S/D 13 JULI 2022
MINGGU 12 14 JULI 2022 S/D 20 JULI 2022
MINGGU 13 21 JULI 2022 S/D 27 JULI 2022
MINGGU 14 28 JULI 2022 S/D 3 AGUSTUS 2022
MINGGU 15 4 AGUSTUS 2022 S/D 10 AGUSTUS 2022
MINGGU 16 11 AGUSTUS 2022 S/D 17 AGUSTUS 2022
MINGGU 17 18 AGUSTUS 2022 S/D 24 AGUSTUS 2022
BULAN 1 27 APRIL 2022 S/D 25 MEI 2022
BULAN 2 26 MEI 2022 S/D 22 JUNI 2022
BULAN 3 23 JUNI 2022 S/D 20 JULI 2022
BULAN 4 21 JULI 2022 S/D 24 AGUSTUS 2022
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
KEGIATAN
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
LAPORAN MINGGUAN
SURAT PERINTAH KERJA ( SPK )
Nomor : 461.1/0761/2022
Tanggal : 27 April 2022
KEGIATAN
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
MINGGU 1
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 1
INSTANSI : DINAS SOSIAL MINGGU : 1
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 27 APRIL 2022 S/D 3 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 1.26
JUMLAH 943,758,784.04 11,930,000.00 11,930,000.00
PPN 10% 94,375,878.40 1,193,000.00 1,193,000.00
JUMLAH TOTAL 1,038,134,662.45 13,123,000.00 13,123,000.00
DIBULATKAN 1,038,134,662.00 13,123,000.00 13,123,000.00
MINGGU 1
INSTANSI : DINAS SOSIAL MINGGU : 1
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 27 APRIL 2022 S/D 3 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39
Sub Jumlah 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 1.26
JUMLAH 943,758,784.04 11,930,000.00 11,930,000.00
PPN 10% 94,375,878.40 1,193,000.00 1,193,000.00
JUMLAH TOTAL 1,038,134,662.45 13,123,000.00 13,123,000.00
DIBULATKAN 1,038,134,662.00 13,123,000.00 13,123,000.00
MINGGU 2
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 2
INSTANSI : DINAS SOSIAL MINGGU : 2
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 4 MEI 2022 S/D 11 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 63,207,500.00 63,207,500.00 6.70
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 7.96
JUMLAH 943,758,784.04 11,930,000.00 63,207,500.00 75,137,500.00
PPN 10% 94,375,878.40 1,193,000.00 6,320,750.00 7,513,750.00
JUMLAH TOTAL 1,038,134,662.45 13,123,000.00 69,528,250.00 82,651,250.00
DIBULATKAN 1,038,134,662.00 13,123,000.00 69,528,250.00 82,651,250.00
MINGGU 2
INSTANSI : DINAS SOSIAL MINGGU : 2
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 4 MEI 2022 S/D 11 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 126.42 63,207,500.00 50% 126.42 63,207,500.00 50% 6.70
Sub Jumlah 126,415,000.00 13.39 63,207,500.00 63,207,500.00 6.70
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 7.96
JUMLAH 943,758,784.04 11,930,000.00 63,207,500.00 75,137,500.00
PPN 10% 94,375,878.40 1,193,000.00 6,320,750.00 7,513,750.00
JUMLAH TOTAL 1,038,134,662.45 13,123,000.00 69,528,250.00 82,651,250.00
DIBULATKAN 1,038,134,662.00 13,123,000.00 69,528,250.00 82,651,250.00
MINGGU 3
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 3
INSTANSI : DINAS SOSIAL MINGGU : 3
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 12 MEI 2022 S/D 18 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 63,207,500.00 50,566,000.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 13.32
JUMLAH 943,758,784.04 75,137,500.00 50,566,000.00 125,703,500.00
PPN 10% 94,375,878.40 7,513,750.00 5,056,600.00 12,570,350.00
JUMLAH TOTAL 1,038,134,662.45 82,651,250.00 55,622,600.00 138,273,850.00
DIBULATKAN 1,038,134,662.00 82,651,250.00 55,622,600.00 138,273,850.00
MINGGU 3
INSTANSI : DINAS SOSIAL MINGGU : 3
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 12 MEI 2022 S/D 18 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 126.42 63,207,500.00 50% 101.13 50,566,000.00 40% 227.55 113,773,500.00 90% 12.06
Sub Jumlah 126,415,000.00 13.39 63,207,500.00 50,566,000.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 13.32
JUMLAH 943,758,784.04 75,137,500.00 50,566,000.00 125,703,500.00
PPN 10% 94,375,878.40 7,513,750.00 5,056,600.00 12,570,350.00
JUMLAH TOTAL 1,038,134,662.45 82,651,250.00 55,622,600.00 138,273,850.00
DIBULATKAN 1,038,134,662.00 82,651,250.00 55,622,600.00 138,273,850.00
MINGGU 4
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 4
INSTANSI : DINAS SOSIAL MINGGU : 4
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 19 MEI 2022 S/D 25 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 112,900,261.32 11.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 25.28
JUMLAH 943,758,784.04 125,703,500.00 112,900,261.32 238,603,761.32
PPN 10% 94,375,878.40 12,570,350.00 11,290,026.13 23,860,376.13
JUMLAH TOTAL 1,038,134,662.45 138,273,850.00 124,190,287.45 262,464,137.45
DIBULATKAN 1,038,134,662.00 138,273,850.00 124,190,287.00 262,464,137.00
MINGGU 4
INSTANSI : DINAS SOSIAL MINGGU : 4
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 19 MEI 2022 S/D 25 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 82.15 112,900,261.32 40% 82.15 112,900,261.32 40% 11.96
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 112,900,261.32 11.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 227.55 113,773,500.00 90% 12.06
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 25.28
JUMLAH 943,758,784.04 125,703,500.00 112,900,261.32 238,603,761.32
PPN 10% 94,375,878.40 12,570,350.00 11,290,026.13 23,860,376.13
JUMLAH TOTAL 1,038,134,662.45 138,273,850.00 124,190,287.45 262,464,137.45
DIBULATKAN 1,038,134,662.00 138,273,850.00 124,190,287.00 262,464,137.00
MINGGU 5
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 5
INSTANSI : DINAS SOSIAL MINGGU : 5
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 26 MEI 2022 S/D 1 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 112,900,261.32 225,800,522.64 23.93
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 37.25
JUMLAH 943,758,784.04 238,603,761.32 112,900,261.32 351,504,022.64
PPN 10% 94,375,878.40 23,860,376.13 11,290,026.13 35,150,402.26
JUMLAH TOTAL 1,038,134,662.45 262,464,137.45 124,190,287.45 386,654,424.90
DIBULATKAN 1,038,134,662.00 262,464,137.00 124,190,287.00 386,654,424.00
MINGGU 5
INSTANSI : DINAS SOSIAL MINGGU : 5
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 26 MEI 2022 S/D 1 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 82.15 112,900,261.32 40% 82.15 112,900,261.32 40% 164.30 225,800,522.64 80% 23.93
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 112,900,261.32 225,800,522.64 23.93
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 227.55 113,773,500.00 90% 12.06
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 37.25
JUMLAH 943,758,784.04 238,603,761.32 112,900,261.32 351,504,022.64
PPN 10% 94,375,878.40 23,860,376.13 11,290,026.13 35,150,402.26
JUMLAH TOTAL 1,038,134,662.45 262,464,137.45 124,190,287.45 386,654,424.90
DIBULATKAN 1,038,134,662.00 262,464,137.00 124,190,287.00 386,654,424.00
MINGGU 6
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 6
INSTANSI : DINAS SOSIAL MINGGU : 6
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 2 JUNI 2022 S/D 8 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 225,800,522.64 45,159,945.93 270,960,468.57 28.71
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 20,442,381.03 20,442,381.03 2.17
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 44.20
JUMLAH 943,758,784.04 351,504,022.64 65,602,326.96 417,106,349.60
PPN 10% 94,375,878.40 35,150,402.26 6,560,232.70 41,710,634.96
JUMLAH TOTAL 1,038,134,662.45 386,654,424.90 72,162,559.66 458,816,984.56
DIBULATKAN 1,038,134,662.00 386,654,424.00 72,162,559.00 458,816,984.00
MINGGU 6
INSTANSI : DINAS SOSIAL MINGGU : 6
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 2 JUNI 2022 S/D 8 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 164.30 225,800,522.64 80% 20.54 28,225,065.33 10% 184.84 254,025,587.97 90% 26.92
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79 13.56 16,934,880.60 100% 13.56 16,934,880.60 100% 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 225,800,522.64 45,159,945.93 270,960,468.57 28.71
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 227.55 113,773,500.00 90% 12.06
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 526.63 20,442,381.03 50% 526.63 20,442,381.03 50% 2.17
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66 20,442,381.03 20,442,381.03 2.17
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 44.20
JUMLAH 943,758,784.04 351,504,022.64 65,602,326.96 417,106,349.60
PPN 10% 94,375,878.40 35,150,402.26 6,560,232.70 41,710,634.96
JUMLAH TOTAL 1,038,134,662.45 386,654,424.90 72,162,559.66 458,816,984.56
DIBULATKAN 1,038,134,662.00 386,654,424.00 72,162,559.00 458,816,984.00
MINGGU 7
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 7
INSTANSI : DINAS SOSIAL MINGGU : 7
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 9 JUNI 2022 S/D 15 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 270,960,468.57 28,225,065.33 299,185,533.90 31.70
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 20,442,381.03 40,884,762.06 61,327,143.09 6.50
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 52.80
JUMLAH 943,758,784.04 417,106,349.60 81,234,907.39 498,341,256.99
PPN 10% 94,375,878.40 41,710,634.96 8,123,490.74 49,834,125.70
JUMLAH TOTAL 1,038,134,662.45 458,816,984.56 89,358,398.13 548,175,382.69
DIBULATKAN 1,038,134,662.00 458,816,984.00 89,358,398.00 548,175,382.00
MINGGU 7
INSTANSI : DINAS SOSIAL MINGGU : 7
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 9 JUNI 2022 S/D 15 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 184.84 254,025,587.97 90% 20.54 28,225,065.33 10% 205.38 282,250,653.30 100% 29.91
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79 13.56 16,934,880.60 100% 13.56 16,934,880.60 100% 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 270,960,468.57 28,225,065.33 299,185,533.90 31.70
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 227.55 113,773,500.00 90% 12.06
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 526.63 20,442,381.03 50% 526.63 20,442,381.03 50% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 526.63 20,442,381.03 50% 526.63 20,442,381.03 50% 2.17
Sub Jumlah 81,769,524.12 8.66 20,442,381.03 40,884,762.06 61,327,143.09 6.50
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 52.80
JUMLAH 943,758,784.04 417,106,349.60 81,234,907.39 498,341,256.99
PPN 10% 94,375,878.40 41,710,634.96 8,123,490.74 49,834,125.70
JUMLAH TOTAL 1,038,134,662.45 458,816,984.56 89,358,398.13 548,175,382.69
DIBULATKAN 1,038,134,662.00 458,816,984.00 89,358,398.00 548,175,382.00
MINGGU 8
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 8
INSTANSI : DINAS SOSIAL MINGGU : 8
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 16 JUNI 2022 S/D 22 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03 9,704,337.06 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 299,185,533.90 299,185,533.90 31.70
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 12,641,500.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 61,327,143.09 20,442,381.03 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 6,625,000.00 0.70
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64 39,872,700.00 39,872,700.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 65.16
JUMLAH 943,758,784.04 498,341,256.99 116,566,418.09 614,907,675.08
PPN 10% 94,375,878.40 49,834,125.70 11,656,641.81 61,490,767.51
JUMLAH TOTAL 1,038,134,662.45 548,175,382.69 128,223,059.90 676,398,442.59
DIBULATKAN 1,038,134,662.00 548,175,382.00 128,223,059.00 676,398,442.00
MINGGU 8
INSTANSI : DINAS SOSIAL MINGGU : 8
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 16 JUNI 2022 S/D 22 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03 22.20 9,704,337.06 100% 22.20 9,704,337.06 100% 1.03
Sub Jumlah 9,704,337.06 1.03 9,704,337.06 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 205.38 282,250,653.30 100% 205.38 282,250,653.30 100% 29.91
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79 13.56 16,934,880.60 100% 13.56 16,934,880.60 100% 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 299,185,533.90 299,185,533.90 31.70
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 25.28 12,641,500.00 10% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 12,641,500.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 526.63 20,442,381.03 50% 526.63 20,442,381.03 50% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 61,327,143.09 20,442,381.03 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 26.50 6,625,000.00 50% 26.50 6,625,000.00 50% 0.70
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 6,625,000.00 0.70
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08 37.97 39,872,700.00 30% 37.97 39,872,700.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64 39,872,700.00 39,872,700.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 65.16
JUMLAH 943,758,784.04 498,341,256.99 116,566,418.09 614,907,675.08
PPN 10% 94,375,878.40 49,834,125.70 11,656,641.81 61,490,767.51
JUMLAH TOTAL 1,038,134,662.45 548,175,382.69 128,223,059.90 676,398,442.59
DIBULATKAN 1,038,134,662.00 548,175,382.00 128,223,059.00 676,398,442.00
MINGGU 9
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 9
INSTANSI : DINAS SOSIAL MINGGU : 9
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 23 JUNI 2022 S/D 29 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 1,325,000.00 7,950,000.00 0.84
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 66.41
JUMLAH 943,758,784.43 625,472,392.52 1,325,000.00 626,797,392.52
PPN 10% 94,375,878.44 62,547,239.25 132,500.00 62,679,739.25
JUMLAH TOTAL 1,038,134,662.88 688,019,631.78 1,457,500.00 689,477,131.78
DIBULATKAN 1,038,134,662.00 688,019,631.00 1,457,500.00 689,477,131.00
MINGGU 9
INSTANSI : DINAS SOSIAL MINGGU : 9
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 23 JUNI 2022 S/D 29 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 26.50 6,625,000.00 50% 5.30 1,325,000.00 10% 31.80 7,950,000.00 60% 0.84
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 1,325,000.00 7,950,000.00 0.84
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 66.41
JUMLAH 943,758,784.43 625,472,392.52 1,325,000.00 626,797,392.52
PPN 10% 94,375,878.44 62,547,239.25 132,500.00 62,679,739.25
JUMLAH TOTAL 1,038,134,662.88 688,019,631.78 1,457,500.00 689,477,131.78
DIBULATKAN 1,038,134,662.00 688,019,631.00 1,457,500.00 689,477,131.00
MINGGU 10
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 10
INSTANSI : DINAS SOSIAL MINGGU : 10
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 30 JUNI 2022 S/D 6 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 7,950,000.00 5,300,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 66.98
JUMLAH 943,758,784.43 626,797,392.52 5,300,000.00 632,097,392.52
PPN 10% 94,375,878.44 62,679,739.25 530,000.00 63,209,739.25
JUMLAH TOTAL 1,038,134,662.88 689,477,131.78 5,830,000.00 695,307,131.78
DIBULATKAN 1,038,134,662.00 689,477,131.00 5,830,000.00 695,307,131.00
MINGGU 10
INSTANSI : DINAS SOSIAL MINGGU : 10
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 30 JUNI 2022 S/D 6 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 31.80 7,950,000.00 60% 21.20 5,300,000.00 40% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 7,950,000.00 5,300,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 66.98
JUMLAH 943,758,784.43 626,797,392.52 5,300,000.00 632,097,392.52
PPN 10% 94,375,878.44 62,679,739.25 530,000.00 63,209,739.25
JUMLAH TOTAL 1,038,134,662.88 689,477,131.78 5,830,000.00 695,307,131.78
DIBULATKAN 1,038,134,662.00 689,477,131.00 5,830,000.00 695,307,131.00
MINGGU 11
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 11
INSTANSI : DINAS SOSIAL MINGGU : 11
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 7 JULI 2022 S/D 13 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 17,770,890.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 68.86
JUMLAH 943,758,784.43 632,097,392.52 17,770,890.50 649,868,283.02
PPN 10% 94,375,878.44 63,209,739.25 1,777,089.05 64,986,828.30
JUMLAH TOTAL 1,038,134,662.88 695,307,131.78 19,547,979.55 714,855,111.33
DIBULATKAN 1,038,134,662.00 695,307,131.00 19,547,979.00 714,855,111.00
MINGGU 11
INSTANSI : DINAS SOSIAL MINGGU : 11
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 7 JULI 2022 S/D 13 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 17,770,890.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 68.86
JUMLAH 943,758,784.43 632,097,392.52 17,770,890.50 649,868,283.02
PPN 10% 94,375,878.44 63,209,739.25 1,777,089.05 64,986,828.30
JUMLAH TOTAL 1,038,134,662.88 695,307,131.78 19,547,979.55 714,855,111.33
DIBULATKAN 1,038,134,662.00 695,307,131.00 19,547,979.00 714,855,111.00
MINGGU 12
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 12
INSTANSI : DINAS SOSIAL MINGGU : 12
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 14 JULI 2022 S/D 20 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 73.46
JUMLAH 943,758,784.43 649,868,283.02 43,458,500.00 693,326,783.02
PPN 10% 94,375,878.44 64,986,828.30 4,345,850.00 69,332,678.30
JUMLAH TOTAL 1,038,134,662.88 714,855,111.33 47,804,350.00 762,659,461.33
DIBULATKAN 1,038,134,662.00 714,855,111.00 47,804,350.00 762,659,461.00
MINGGU 12
INSTANSI : DINAS SOSIAL MINGGU : 12
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 14 JULI 2022 S/D 20 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 73.46
JUMLAH 943,758,784.43 649,868,283.02 43,458,500.00 693,326,783.02
PPN 10% 94,375,878.44 64,986,828.30 4,345,850.00 69,332,678.30
JUMLAH TOTAL 1,038,134,662.88 714,855,111.33 47,804,350.00 762,659,461.33
DIBULATKAN 1,038,134,662.00 714,855,111.00 47,804,350.00 762,659,461.00
MINGGU 13
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 13
INSTANSI : DINAS SOSIAL MINGGU : 13
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 21 JULI 2022 S/D 27 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 4,950,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 73.99
JUMLAH 943,758,784.43 693,326,783.02 4,950,000.00 698,276,783.02
PPN 10% 94,375,878.44 69,332,678.30 495,000.00 69,827,678.30
JUMLAH TOTAL 1,038,134,662.88 762,659,461.33 5,445,000.00 768,104,461.33
DIBULATKAN 1,038,134,662.00 762,659,461.00 5,445,000.00 768,104,461.00
MINGGU 13
INSTANSI : DINAS SOSIAL MINGGU : 13
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 21 JULI 2022 S/D 27 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08 1.00 750,000.00 100% 1.00 750,000.00 100% 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22 37.00 2,035,000.00 100% 37.00 2,035,000.00 100% 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03 5.00 325,000.00 100% 5.00 325,000.00 100% 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03 4.00 300,000.00 100% 4.00 300,000.00 100% 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11 16.00 1,040,000.00 100% 16.00 1,040,000.00 100% 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 4,950,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 73.99
JUMLAH 943,758,784.43 693,326,783.02 4,950,000.00 698,276,783.02
PPN 10% 94,375,878.44 69,332,678.30 495,000.00 69,827,678.30
JUMLAH TOTAL 1,038,134,662.88 762,659,461.33 5,445,000.00 768,104,461.33
DIBULATKAN 1,038,134,662.00 762,659,461.00 5,445,000.00 768,104,461.00
MINGGU 14
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 14
INSTANSI : DINAS SOSIAL MINGGU : 14
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 28 JULI 2022 S/D 3 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 14,065,966.41 325,109,814.36 34.45
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 36,374,000.00 63,654,500.00 6.74
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 6,600,000.00 46,473,015.00 130% 4.92
JUMLAH BOBOT PEKERJAAN (%) 100.00 80.03
JUMLAH 943,758,784.43 698,276,783.02 57,039,966.41 755,316,749.43
PPN 10% 94,375,878.44 69,827,678.30 5,703,996.64 75,531,674.94
JUMLAH TOTAL 1,038,134,662.88 768,104,461.33 62,743,963.05 830,848,424.38
DIBULATKAN 1,038,134,662.00 768,104,461.00 62,743,963.00 830,848,424.00
MINGGU 14
INSTANSI : DINAS SOSIAL MINGGU : 14
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 28 JULI 2022 S/D 3 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81 11.40 7,619,918.46 100% 11.40 7,619,918.46 100% 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04 2.40 408,012.00 100% 2.40 408,012.00 100% 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03 1.20 283,206.00 100% 1.20 283,206.00 100% 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19 1.55 1,754,829.95 100% 1.55 1,754,829.95 100% 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42 1.00 4,000,000.00 100% 1.00 4,000,000.00 100% 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 14,065,966.41 325,109,814.36 34.45
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08 1.00 750,000.00 100% 1.00 750,000.00 100% 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22 37.00 2,035,000.00 100% 37.00 2,035,000.00 100% 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03 5.00 325,000.00 100% 5.00 325,000.00 100% 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03 4.00 300,000.00 100% 4.00 300,000.00 100% 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11 16.00 1,040,000.00 100% 16.00 1,040,000.00 100% 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 72.75 36,374,000.00 40% 127.31 63,654,500.00 70% 6.74
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 36,374,000.00 63,654,500.00 6.74
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70 6.00 6,600,000.00 100% 6.00 6,600,000.00 100% 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 6,600,000.00 46,473,015.00 4.92
JUMLAH BOBOT PEKERJAAN (%) 100.00 80.03
JUMLAH 943,758,784.43 698,276,783.02 57,039,966.41 755,316,749.43
PPN 10% 94,375,878.44 69,827,678.30 5,703,996.64 75,531,674.94
JUMLAH TOTAL 1,038,134,662.88 768,104,461.33 62,743,963.05 830,848,424.38
DIBULATKAN 1,038,134,662.00 768,104,461.00 62,743,963.00 830,848,424.00
MINGGU 15
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 15
INSTANSI : DINAS SOSIAL MINGGU : 15
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 4 AGUSTUS 2022 S/D 10 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 325,109,814.36 325,109,814.36 34.45
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 63,654,500.00 27,280,500.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 46,473,015.00 102,495,015.00 148,968,030.00 15.78
JUMLAH BOBOT PEKERJAAN (%) 100.00 93.78
JUMLAH 943,758,784.43 755,316,749.43 129,775,515.00 885,092,264.43
PPN 10% 94,375,878.44 75,531,674.94 12,977,551.50 88,509,226.44
JUMLAH TOTAL 1,038,134,662.88 830,848,424.38 142,753,066.50 973,601,490.88
DIBULATKAN 1,038,134,662.00 830,848,424.00 142,753,066.00 973,601,490.00
MINGGU 15
INSTANSI : DINAS SOSIAL MINGGU : 15
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 4 AGUSTUS 2022 S/D 10 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81 11.40 7,619,918.46 100% 11.40 7,619,918.46 100% 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04 2.40 408,012.00 100% 2.40 408,012.00 100% 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03 1.20 283,206.00 100% 1.20 283,206.00 100% 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19 1.55 1,754,829.95 100% 1.55 1,754,829.95 100% 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42 1.00 4,000,000.00 100% 1.00 4,000,000.00 100% 0.42
Sub Jumlah 325,109,814.36 34.45 325,109,814.36 325,109,814.36 34.45
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08 1.00 750,000.00 100% 1.00 750,000.00 100% 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22 37.00 2,035,000.00 100% 37.00 2,035,000.00 100% 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03 5.00 325,000.00 100% 5.00 325,000.00 100% 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03 4.00 300,000.00 100% 4.00 300,000.00 100% 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11 16.00 1,040,000.00 100% 16.00 1,040,000.00 100% 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 127.31 63,654,500.00 70% 54.56 27,280,500.00 30% 181.87 90,935,000.00 100% 9.64
Sub Jumlah 90,935,000.00 9.64 63,654,500.00 27,280,500.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64 59.64 62,622,000.00 100% 59.64 62,622,000.00 100% 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 75.95 79,746,030.00 60% 8.45
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70 6.00 6,600,000.00 100% 6.00 6,600,000.00 100% 0.70
Sub Jumlah 207,634,550.00 22.00 46,473,015.00 102,495,015.00 148,968,030.00 15.78
JUMLAH BOBOT PEKERJAAN (%) 100.00 93.78
JUMLAH 943,758,784.43 755,316,749.43 129,775,515.00 885,092,264.43
PPN 10% 94,375,878.44 75,531,674.94 12,977,551.50 88,509,226.44
JUMLAH TOTAL 1,038,134,662.88 830,848,424.38 142,753,066.50 973,601,490.88
DIBULATKAN 1,038,134,662.00 830,848,424.00 142,753,066.00 973,601,490.00
MINGGU 16
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 16
INSTANSI : DINAS SOSIAL MINGGU : 16
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 11 AGUSTUS 2022 S/D 17 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 325,109,814.36 325,109,814.36 34.45
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 90,935,000.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 148,968,030.00 26,582,010.00 175,550,040.00 18.60
JUMLAH BOBOT PEKERJAAN (%) 100.00 96.60
JUMLAH 943,758,784.43 885,092,264.43 26,582,010.00 911,674,274.43
PPN 10% 94,375,878.44 88,509,226.44 2,658,201.00 91,167,427.44
JUMLAH TOTAL 1,038,134,662.88 973,601,490.88 29,240,211.00 1,002,841,701.88
DIBULATKAN 1,038,134,662.00 973,601,490.00 29,240,211.00 1,002,841,701.00
MINGGU 16
INSTANSI : DINAS SOSIAL MINGGU : 16
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 11 AGUSTUS 2022 S/D 17 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81 11.40 7,619,918.46 100% 11.40 7,619,918.46 100% 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04 2.40 408,012.00 100% 2.40 408,012.00 100% 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03 1.20 283,206.00 100% 1.20 283,206.00 100% 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19 1.55 1,754,829.95 100% 1.55 1,754,829.95 100% 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42 1.00 4,000,000.00 100% 1.00 4,000,000.00 100% 0.42
Sub Jumlah 325,109,814.36 34.45 325,109,814.36 325,109,814.36 34.45
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08 1.00 750,000.00 100% 1.00 750,000.00 100% 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22 37.00 2,035,000.00 100% 37.00 2,035,000.00 100% 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03 5.00 325,000.00 100% 5.00 325,000.00 100% 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03 4.00 300,000.00 100% 4.00 300,000.00 100% 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11 16.00 1,040,000.00 100% 16.00 1,040,000.00 100% 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 181.87 90,935,000.00 100% 181.87 90,935,000.00 100% 9.64
Sub Jumlah 90,935,000.00 9.64 90,935,000.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64 59.64 62,622,000.00 100% 59.64 62,622,000.00 100% 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 75.95 79,746,030.00 60% 25.32 26,582,010.00 20% 101.26 106,328,040.00 80% 11.27
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70 6.00 6,600,000.00 100% 6.00 6,600,000.00 100% 0.70
Sub Jumlah 207,634,550.00 22.00 148,968,030.00 26,582,010.00 175,550,040.00 18.60
JUMLAH BOBOT PEKERJAAN (%) 100.00 96.60
JUMLAH 943,758,784.43 885,092,264.43 26,582,010.00 911,674,274.43
PPN 10% 94,375,878.44 88,509,226.44 2,658,201.00 91,167,427.44
JUMLAH TOTAL 1,038,134,662.88 973,601,490.88 29,240,211.00 1,002,841,701.88
DIBULATKAN 1,038,134,662.00 973,601,490.00 29,240,211.00 1,002,841,701.00
MINGGU 17
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI MINGGU 17
INSTANSI : DINAS SOSIAL MINGGU : 17
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 18 AGUSTUS 2022 S/D 24 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 325,109,814.36 325,109,814.36 34.45
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 90,935,000.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 175,550,040.00 32,084,510.00 207,634,550.00 22.00
JUMLAH BOBOT PEKERJAAN (%) 100.00 100.00
JUMLAH 943,758,784.43 911,674,274.43 32,084,510.00 943,758,784.43
PPN 10% 94,375,878.44 91,167,427.44 3,208,451.00 94,375,878.44
JUMLAH TOTAL 1,038,134,662.88 1,002,841,701.88 35,292,961.00 1,038,134,662.88
DIBULATKAN 1,038,134,662.00 1,002,841,701.00 35,292,961.00 1,038,134,662.00
MINGGU 17
INSTANSI : DINAS SOSIAL MINGGU : 17
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 18 AGUSTUS 2022 S/D 24 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
MINGGU LALU MINGGU INI s/d MINGGU INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81 11.40 7,619,918.46 100% 11.40 7,619,918.46 100% 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04 2.40 408,012.00 100% 2.40 408,012.00 100% 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03 1.20 283,206.00 100% 1.20 283,206.00 100% 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19 1.55 1,754,829.95 100% 1.55 1,754,829.95 100% 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42 1.00 4,000,000.00 100% 1.00 4,000,000.00 100% 0.42
Sub Jumlah 325,109,814.36 34.45 325,109,814.36 325,109,814.36 34.45
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08 1.00 750,000.00 100% 1.00 750,000.00 100% 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22 37.00 2,035,000.00 100% 37.00 2,035,000.00 100% 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03 5.00 325,000.00 100% 5.00 325,000.00 100% 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03 4.00 300,000.00 100% 4.00 300,000.00 100% 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11 16.00 1,040,000.00 100% 16.00 1,040,000.00 100% 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 18,200,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 181.87 90,935,000.00 100% 181.87 90,935,000.00 100% 9.64
Sub Jumlah 90,935,000.00 9.64 90,935,000.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64 59.64 62,622,000.00 100% 59.64 62,622,000.00 100% 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 101.26 106,328,040.00 80% 25.32 26,582,010.00 20% 126.58 132,910,050.00 100% 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58 11.01 5,502,500.00 100% 11.01 5,502,500.00 100% 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70 6.00 6,600,000.00 100% 6.00 6,600,000.00 100% 0.70
Sub Jumlah 207,634,550.00 22.00 175,550,040.00 32,084,510.00 207,634,550.00 22.00
JUMLAH BOBOT PEKERJAAN (%) 100.00 100.00
JUMLAH 943,758,784.43 911,674,274.43 32,084,510.00 943,758,784.43
PPN 10% 94,375,878.44 91,167,427.44 3,208,451.00 94,375,878.44
JUMLAH TOTAL 1,038,134,662.88 1,002,841,701.88 35,292,961.00 1,038,134,662.88
DIBULATKAN 1,038,134,662.00 1,002,841,701.00 35,292,961.00 1,038,134,662.00
LAPORAN BULANAN
SURAT PERINTAH KERJA ( SPK )
Nomor : 461.1/0761/2022
Tanggal : 27 April 2022
KEGIATAN
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
BULAN 1
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI BULAN 1
INSTANSI : DINAS SOSIAL BULAN : 1
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 27 APRIL 2022 S/D 25 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 112,900,261.32 11.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 25.28
JUMLAH 943,758,784.04 238,603,761.32 238,603,761.32
PPN 10% 94,375,878.40 23,860,376.13 23,860,376.13
JUMLAH TOTAL 1,038,134,662.45 262,464,137.45 262,464,137.45
DIBULATKAN 1,038,134,662.00 262,464,137.00 262,464,137.00
BULAN 1
INSTANSI : DINAS SOSIAL BULAN : 1
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 27 APRIL 2022 S/D 25 MEI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03
Sub Jumlah 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 82.15 112,900,261.32 40% 82.15 112,900,261.32 40% 11.96
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 112,900,261.32 11.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 227.55 113,773,500.00 90% 12.06
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 113,773,500.00 12.06
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33
Sub Jumlah 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40
Sub Jumlah 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64
Sub Jumlah 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64
JUMLAH BOBOT PEKERJAAN (%) 100.00 25.28
JUMLAH 943,758,784.04 238,603,761.32 238,603,761.32
PPN 10% 94,375,878.40 23,860,376.13 23,860,376.13
JUMLAH TOTAL 1,038,134,662.45 262,464,137.45 262,464,137.45
DIBULATKAN 1,038,134,662.00 262,464,137.00 262,464,137.00
BULAN 2
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI BULAN 2
INSTANSI : DINAS SOSIAL BULAN : 2
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 26 MEI 2022 S/D 22 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 9,704,337.06 1.03 9,704,337.06 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 186,285,272.58 299,185,533.90 31.70
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 12,641,500.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 6,625,000.00 0.70
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 9,093,500.00 9,093,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 204,191,000.00 21.64 39,872,700.00 39,872,700.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 65.16
JUMLAH 943,758,784.04 238,603,761.32 358,116,913.76 596,720,675.08
PPN 10% 94,375,878.40 23,860,376.13 35,811,691.38 59,672,067.51
JUMLAH TOTAL 1,038,134,662.45 262,464,137.45 393,928,605.14 656,392,742.59
DIBULATKAN 1,038,134,662.00 262,464,137.00 393,928,605.00 656,392,742.00
BULAN 2
INSTANSI : DINAS SOSIAL BULAN : 2
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 26 MEI 2022 S/D 22 JUNI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 22.20 m2 437,132.30 9,704,337.06 1.03 22.20 9,704,337.06 100% 22.20 9,704,337.06 100% 1.03
Sub Jumlah 9,704,337.06 1.03 9,704,337.06 9,704,337.06 1.03
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 13.77 m2 1,750,000.00 24,097,500.00 2.55
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.20 m2 1,350,000.00 8,370,000.00 0.89
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.20 m2 1,200,000.00 3,840,000.00 0.41
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 28.35 m2 850,000.00 24,097,500.00 2.55
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.29 m2 750,000.00 2,467,500.00 0.26
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11
Sub Jumlah 63,912,500.00 6.77
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 205.38 m2 1,374,285.00 282,250,653.30 29.91 82.15 112,900,261.32 40% 123.23 169,350,391.98 60% 205.38 282,250,653.30 100% 29.91
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 13.56 m2 1,248,885.00 16,934,880.60 1.79 13.56 16,934,880.60 100% 13.56 16,934,880.60 100% 1.79
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
Sub Jumlah 306,805,452.36 32.51 112,900,261.32 186,285,272.58 299,185,533.90 31.70
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 227.55 113,773,500.00 90% 25.28 12,641,500.00 10% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 113,773,500.00 12,641,500.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 12,125,080.00 1.28
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 26.50 6,625,000.00 50% 26.50 6,625,000.00 50% 0.70
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 6,625,000.00 0.70
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,909,000.00 14.08 37.97 39,872,700.00 30% 37.97 39,872,700.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 17.32 m2 500,000.00 8,660,000.00 0.92
Sub Jumlah 204,191,000.00 21.64 39,872,700.00 39,872,700.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 65.16
JUMLAH 943,758,784.04 238,603,761.32 376,303,913.76 614,907,675.08
PPN 10% 94,375,878.40 23,860,376.13 37,630,391.38 61,490,767.51
JUMLAH TOTAL 1,038,134,662.45 262,464,137.45 413,934,305.14 676,398,442.59
DIBULATKAN 1,038,134,662.00 262,464,137.00 413,934,305.00 676,398,442.00
BULAN 3
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI BULAN 3
INSTANSI : DINAS SOSIAL BULAN : 3
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 23 JUNI 2022 S/D 20 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 17,770,890.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 6,625,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 73.46
JUMLAH 943,758,784.43 625,472,392.52 67,854,390.50 693,326,783.02
PPN 10% 94,375,878.44 62,547,239.25 6,785,439.05 69,332,678.30
JUMLAH TOTAL 1,038,134,662.88 688,019,631.78 74,639,829.55 762,659,461.33
DIBULATKAN 1,038,134,662.00 688,019,631.00 74,639,829.00 762,659,461.00
BULAN 3
INSTANSI : DINAS SOSIAL BULAN : 3
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 23 JUNI 2022 S/D 20 JULI 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 311,043,847.95 32.96
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 12,125,080.00 17,770,890.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 26.50 6,625,000.00 50% 26.50 6,625,000.00 50% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 6,625,000.00 6,625,000.00 13,250,000.00 1.40
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 54.56 27,280,500.00 30% 2.89
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 27,280,500.00 2.89
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 37.97 39,873,015.00 30% 4.22
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 39,873,015.00 4.22
JUMLAH BOBOT PEKERJAAN (%) 100.00 73.46
JUMLAH 943,758,784.43 625,472,392.52 67,854,390.50 693,326,783.02
PPN 10% 94,375,878.44 62,547,239.25 6,785,439.05 69,332,678.30
JUMLAH TOTAL 1,038,134,662.88 688,019,631.78 74,639,829.55 762,659,461.33
DIBULATKAN 1,038,134,662.00 688,019,631.00 74,639,829.00 762,659,461.00
BULAN 4
KEGIATAN
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM
LOKASI PEKERJAAN : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
NOMOR KONTRAK : 461.1/0761/2022
TANGGAL KONTRAK : 27 APRIL 2022
BIAYA KONTRAK : Rp. 1.038.134.662,-
SATU MILYAR TIGA PULUH DELAPAN JUTA SERATUS TIGA PULUH EMPAT RIBU ENAM RATUS ENAM PULUH DUA RUPIAH
TAHUN ANGGARAN : 2022
PELAKSANA :
CV. INDRA PRATAMA
Jln. Banda Aceh Medan Km. 23 Indra Puri - Aceh Besar
PEMERINTAH ACEH
DINAS SOSIAL
Jl. Sultan Iskandar Muda No. 49 Banda Aceh Kode Pos 23243 Telepon ( 0651 ) 44325, 44326 Faks ( 0651 ) 44325
BANDA ACEH
REKAPITULASI BULAN 4
INSTANSI : DINAS SOSIAL BULAN : 4
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 21 JULI 2022 S/D 24 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 14,065,966.41 325,109,814.36 34.45
V PEKERJAAN PLAFOND
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 167,761,535.00 207,634,550.00 22.00
JUMLAH BOBOT PEKERJAAN (%) 100.00 100.00
JUMLAH 943,758,784.43 693,326,783.02 181,827,501.41 943,758,784.43
PPN 10% 94,375,878.44 69,332,678.30 18,182,750.14 94,375,878.44
JUMLAH TOTAL 1,038,134,662.88 762,659,461.33 200,010,251.55 1,038,134,662.88
DIBULATKAN 1,038,134,662.00 762,659,461.00 200,010,251.00 1,038,134,662.00
BULAN 4
INSTANSI : DINAS SOSIAL BULAN : 4
PEKERJAAN : LANJUTAN PEMBANGUNAN RUANG KLINIK, KOMPUTER DAN PERPUSTAKAAN PANTI TUNA NETRA UPTD RSBM PERIODE : 21 JULI 2022 S/D 24 AGUSTUS 2022
NO./TGL. KONTRAK : 461.1/0761/2022 TANGGAL 27 APRIL 2022 PELAKSANA : CV. INDRA PRATAMA
NILAI PEKERJAAN : Rp. 1.038.134.662,- LOKASI : UPTD RUMOH SEUJAHTERA BEUJROH MEUKARYA
TAHUN ANGGARAN : 2022
KEMAJUAN PEKERJAAN
NILAI KONTRAK
BULAN LALU BULAN INI s/d BULAN INI BOBOT
NO. URAIAN PEKERJAAN VOLUME TOTAL
HARGA SATUAN BOBOT BOBOT BOBOT BOBOT (%)
JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp) VOL JUMLAH HARGA (Rp)
(Rp) (%) (%) (%) (%)
I. PEKERJAAN PERSIAPAN
1 Pengukuran dan Pembersihan Lapangan 1.00 ls 1,000,000.00 1,000,000.00 0.11 1.00 1,000,000.00 100% 1.00 1,000,000.00 100% 0.11
2 Pengadaan dan Pemasangan Papan Nama Proyek 1.00 ls 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
3 Biaya K3 dan lainnya 1.00 ls 10,430,000.00 10,430,000.00 1.11 1.00 10,430,000.00 100% 1.00 10,430,000.00 100% 1.11
Sub Jumlah 11,930,000.00 1.26 11,930,000.00 11,930,000.00 1.26
II. PEKERJAAN PASANGAN DAN DINDING
1 Keramik Dinding Uk. 25 x 40 cm ( Polished ) 19.24 m2 437,132.30 8,410,425.45 0.89 19.24 8,410,425.45 100% 19.24 8,410,425.45 100% 0.89
Sub Jumlah 8,410,425.45 0.89 8,410,425.45 8,410,425.45 0.89
III PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Pintu UPVC Type P1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 11.48 m2 1,750,000.00 20,081,250.00 2.13 11.48 20,081,250.00 100% 11.48 20,081,250.00 100% 2.13
2 Pintu UPVC Type P2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 6.35 m2 1,350,000.00 8,565,750.00 0.91 6.35 8,565,750.00 100% 6.35 8,565,750.00 100% 0.91
3 Pintu UPVC Type P3 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.52 m2 1,200,000.00 4,224,000.00 0.45 3.52 4,224,000.00 100% 3.52 4,224,000.00 100% 0.45
4 Jendela UPVC Type J1 (Sesuai Gambar Lengkap Aksesories + Terpasang) 8.55 m2 850,000.00 7,267,500.00 0.77 8.55 7,267,500.00 100% 8.55 7,267,500.00 100% 0.77
5 Jendela UPVC Type J2 (Sesuai Gambar Lengkap Aksesories + Terpasang) 3.04 m2 750,000.00 2,280,000.00 0.24 3.04 2,280,000.00 100% 3.04 2,280,000.00 100% 0.24
6 Ventilasi UPVC Type V1 2.00 Unit 520,000.00 1,040,000.00 0.11 2.00 1,040,000.00 100% 2.00 1,040,000.00 100% 0.11
Sub Jumlah 43,458,500.00 4.60 43,458,500.00 43,458,500.00 4.60
IV PEKERJAAN LANTAI
1 Pasangan Lantai Granit uk. 60x60 cm polished 213.00 m2 1,374,285.00 292,722,705.00 31.02 213.00 292,722,705.00 100% 213.00 292,722,705.00 100% 31.02
2 Pasangan Lantai Granit uk. 60x60 cm Unpolished (Teras) 14.67 m2 1,248,885.00 18,321,142.95 1.94 14.67 18,321,142.95 100% 14.67 18,321,142.95 100% 1.94
3 Jalur Pemandu (Guiding Block) 11.40 m2 668,413.90 7,619,918.46 0.81 11.40 7,619,918.46 100% 11.40 7,619,918.46 100% 0.81
4 Tanah Urug 2.40 m3 170,005.00 408,012.00 0.04 2.40 408,012.00 100% 2.40 408,012.00 100% 0.04
5 Pasir Urug 1.20 m3 236,005.00 283,206.00 0.03 1.20 283,206.00 100% 1.20 283,206.00 100% 0.03
6 Beton Cor Selasar 1.55 m3 1,131,426.81 1,754,829.95 0.19 1.55 1,754,829.95 100% 1.55 1,754,829.95 100% 0.19
7 Pekerjaan Tangga ( Lengkap Terpasang ) 1.00 Ls 4,000,000.00 4,000,000.00 0.42 1.00 4,000,000.00 100% 1.00 4,000,000.00 100% 0.42
Sub Jumlah 325,109,814.36 34.45 311,043,847.95 14,065,966.41 325,109,814.36 34.45
V PEKERJAAN PLAFOND
1 Pekerjaan Plafond PVC + Rangka ( Lengkap Terpasang ) 252.83 m2 500,000.00 126,415,000.00 13.39 252.83 126,415,000.00 100% 252.83 126,415,000.00 100% 13.39
Sub Jumlah 126,415,000.00 13.39 126,415,000.00 126,415,000.00 13.39
VI PEKERJAAN PENGECATAN
1 Pelapisan Cat Alkali Sealer 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
2 Pengecatan Dinding 1053.26 m2 38,817.35 40,884,762.06 4.33 1053.26 40,884,762.06 100% 1053.26 40,884,762.06 100% 4.33
Sub Jumlah 81,769,524.12 8.66 81,769,524.12 81,769,524.12 8.66
VII PEKERJAAN PLUMBING
1 Pipa PVC Ø 4''+ Aksesories 6.00 m' 157,929.75 947,578.50 0.10 6.00 947,578.50 100% 6.00 947,578.50 100% 0.10
2 Pipa PVC Ø 3''+ Aksesories 12.00 m' 137,469.75 1,649,637.00 0.17 12.00 1,649,637.00 100% 12.00 1,649,637.00 100% 0.17
3 Pipa PVC Ø 3/4''+ Aksesories 35.00 m' 97,515.00 3,413,025.00 0.36 35.00 3,413,025.00 100% 35.00 3,413,025.00 100% 0.36
4 Instalasi Air Bersih (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
5 Instalasi Air Kotor (termasuk galian, pembobokan, penyambungan koneksi) 2.00 titik 1,500,000.00 3,000,000.00 0.32 2.00 3,000,000.00 100% 2.00 3,000,000.00 100% 0.32
6 Floor Drain 2.00 unit 91,355.00 182,710.00 0.02 2.00 182,710.00 100% 2.00 182,710.00 100% 0.02
7 Kran Air 4.00 unit 144,485.00 577,940.00 0.06 4.00 577,940.00 100% 4.00 577,940.00 100% 0.06
8 Kloset Duduk Monoblock 2.00 unit 3,003,825.00 6,007,650.00 0.64 2.00 6,007,650.00 100% 2.00 6,007,650.00 100% 0.64
9 Washtafel Setara Toto 2.00 unit 3,058,715.00 6,117,430.00 0.65 2.00 6,117,430.00 100% 2.00 6,117,430.00 100% 0.65
10 Septic Tank + Resapan 1.00 Ls 5,000,000.00 5,000,000.00 0.53 1.00 5,000,000.00 100% 1.00 5,000,000.00 100% 0.53
Sub Jumlah 29,895,970.50 3.17 29,895,970.50 29,895,970.50 3.17
VIII PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel dan Kabel
a. Pekerjaan Box Panel Lengkap Terpasang 1.00 unit 500,000.00 500,000.00 0.05 1.00 500,000.00 100% 1.00 500,000.00 100% 0.05
b. Pekerjaan Kabel Penghubung 1.00 ls 750,000.00 750,000.00 0.08 1.00 750,000.00 100% 1.00 750,000.00 100% 0.08
2 Pekerjaan Instalasi Penerangan dan Stop Kontak
a. Lampu LED 10 Watt 37.00 unit 55,000.00 2,035,000.00 0.22 37.00 2,035,000.00 100% 37.00 2,035,000.00 100% 0.22
b. Saklar Tunggal 5.00 unit 65,000.00 325,000.00 0.03 5.00 325,000.00 100% 5.00 325,000.00 100% 0.03
c. Saklar Ganda 4.00 unit 75,000.00 300,000.00 0.03 4.00 300,000.00 100% 4.00 300,000.00 100% 0.03
d. Stop Kontak 16.00 titik 65,000.00 1,040,000.00 0.11 16.00 1,040,000.00 100% 16.00 1,040,000.00 100% 0.11
e. Instalasi Titik Api 53.00 unit 250,000.00 13,250,000.00 1.40 53.00 13,250,000.00 100% 53.00 13,250,000.00 100% 1.40
Sub Jumlah 18,200,000.00 1.93 13,250,000.00 18,200,000.00 1.93
IX PEKERJAAN ATAP
1 Cover Atap bahan Panel ACP PVDF Setara Seven T= 3mm +Rangka Besi Hollow 40x40 181.87 m2 500,000.00 90,935,000.00 9.64 54.56 27,280,500.00 30% 127.31 63,654,500.00 70% 181.87 90,935,000.00 100% 9.64
Sub Jumlah 90,935,000.00 9.64 27,280,500.00 90,935,000.00 9.64
X PEKERJAAN FINISHING DAN LAIN-LAIN
1 ACP PVDF Setara Seven T= 4 mm cutting Huruf Braille + Rangka Hollow 60 x 60 59.64 m2 1,050,000.00 62,622,000.00 6.64 59.64 62,622,000.00 100% 59.64 62,622,000.00 100% 6.64
2 ACP PVDF Setara Seven T = 3 mm cutting tulisan + Rangka Hollow 40 x 40 126.58 m2 1,050,000.00 132,910,050.00 14.08 37.97 39,873,015.00 30% 88.61 93,037,035.00 70% 126.58 132,910,050.00 100% 14.08
3 Pemasangan GRC Motif T = 3 cm Pada Teras 11.01 m2 500,000.00 5,502,500.00 0.58 11.01 5,502,500.00 100% 11.01 5,502,500.00 100% 0.58
4 Railing Tangga Besi Hollow 6.00 m' 1,100,000.00 6,600,000.00 0.70 6.00 6,600,000.00 100% 6.00 6,600,000.00 100% 0.70
Sub Jumlah 207,634,550.00 22.00 39,873,015.00 167,761,535.00 207,634,550.00 22.00
JUMLAH BOBOT PEKERJAAN (%) 100.00 100.00
JUMLAH 943,758,784.43 693,326,783.02 181,827,501.41 943,758,784.43
PPN 10% 94,375,878.44 69,332,678.30 18,182,750.14 94,375,878.44
JUMLAH TOTAL 1,038,134,662.88 762,659,461.33 200,010,251.55 1,038,134,662.88
DIBULATKAN 1,038,134,662.00 762,659,461.00 200,010,251.00 1,038,134,662.00