LAPORAN KEUANGAN

RENOVASI MUSHOLLA AN-NUR RT 003/003


TAHUN 2021-2022

DANA
NO TANGGAL KETERANGAN
PEMASUKAN PENGELUARAN
1 23 Agustus - 3 Sept 2022 9,750,000 Dari Jln Sawo Raya
4,250,000 Dari Jamaah dan Warga
8,455,900 Sisa saldo bulan Agustus 2022

2 23-30 Agustus 2022 4,086,000 Pembelian material bahan


3 1-28 September 2022 1,366,500 Pembelian material bahan
4 1-31 Oktober 2022 1,331,000 Pembelian material bahan

3,400,000 Gaji tukang 21 HK (Agustus)


3,570,000 Gaji tukang 21 HK (september)
5,950,000 Gaji tukang 31 HK ( Oktober)
850,000 Gaji tukang 5 HK (November)

5 September - November 1,050,000 Pembayaran listrik Mushollah Annur

Detail Dana
A Pemasukan 22,455,900
B Pengeluaran 21,603,500
C Saldo 852,400
D Keterangan Rp. 22.455.900 - 21.603.500 = Rp. 852.400

Jakarta, 04 November 2022


Mengetahui,
Ketua RT Bendahara DKM Musholla An-nur

Ahmad Yani Burhan H. Mohamad yakub


PEMASUKAN DAN PENGELUARAN UANG
RENOVASI MUSHOLLA AN-NUR SELAMA 14 BULAN
18 DESEMBER 2021 S/D 05 NOVEMBER 2022

DANA
NO. TANGGAL
PEMASUKAN PENGELUARAN
1 18 DES 2021 - 5 JAN 2022 15,530,000 11,358,000
2 09 JAN - 23 JAN 2022 11,120,000 15,692,000
3 25 JAN - 28 FEB 2022 13,605,000 16,588,000
4 01 MAR - 30 MAR 2022 5,340,000 25,783,000
5 07 APR - 30 MEI 2022 24,492,000 9,770,200
6 09 JUN - 14 AGS 2022 23,340,000 14,884,300
7 23 AGS - 5 NOV 2022 22,455,900 21,603,000
JUMLAH 115,882,900 115,678,500
SALDO 204,400

JADI, JUMLAH BIAYA RENOVASI MUSHOLLA AN-NUR SELAMA 14 BULAN


ADALAH SEBESAR = Rp. 115.882.100
BELUM DITAMBAH DENGAN YANG SUDAH MENYUMBANG BERUPA
BAHAN BANGUNAN BERUPA SEMEN DAN PASIR.