Brief Information On WAH and Implementation Schedule
Brief Information On WAH and Implementation Schedule
A. Introduction
Informasi singkat ini menjelaskan apa yang seharusnya dilakukan oleh TUV SUD Verification
Team dalam mendampingi the Engineering Procurement and Construction (EPC) Contractor
pada saat the Implementation of BP Plant Building’s Facades Blast Protection System agar
para pelaksana pekerjaan terhindar dari bahaya jatuh dari ketinggian dan kecelakaan kerja.
Melalui presentasi ini TUV SUD Verification Team memastikan kepada BP Castrol Management
bahwa salah satu bagian dari tugas lapangan team kami adalah:
1. Mempelajari lebih lanjut tentang:
a. A brief guide of Work at Height Regulations 2005 (WAHR)
b. Permenakertrans No. Per 01/Men/1980 tentang K3 pada konstruksi bangunan
c. Permenaker No. Per 05/Men/1985 Tentang pesawat angkat dan angkut Pasal 35 s/d 48
d. Permenaker No 09 Tahun 2016 mengenai keselamatan dan kesehatan kerja pekerjaan di
ketinggian
e. Direktur Jendral Pembinaan Pengawasan Ketenagakerjaan (DJPPK) No KEP.
45/DJPPK/IX/2008 Pedoman K3 Bekerja di Ketinggian dengan menggunakan akses tali
(Rope Access)
f. Undang-undang No 1 Tahun 1970 tentang Keselamatan Kerja
g. European Standards (EN, CEN and CE) on Safety Working at High Standards: EN-12277
for Harnesses, EN-12492 for Helmets, EN-12275 for Connectors, EN-12276 for Frictional
Anchors.
h. International Standards for Working at High such as OSHA PART 1910, BS 1139 Metal
Scaffolding, AS/NZS 1576 Scaffolding.
i. Scaffold Safety Handbook, issued on July 2003 by Loss Prevention Department, Saudi
Aramco.
Note: Semua peraturan, undang-undang dan standar bekerja di ketinggian tersebut di atas
dapat dilampirkan apabila diperlukan.
Months
No. Activities
I II III IV V VI VII
Preliminary tender preparation, procurement
1. package, Main Contractor selection and
technical verification
Monitoring the process of making Detailed
Engineering Design (DED), work methodologies,
2. standard operating procedures (SOP) and
working schedule by the Main Contractor,
discussing and verifying the results.
Monitoring the Main and Sub-Contractors
preparation and preliminary activities in
mobilizing staff and workers, renting workshops
and temporary boarding houses, renting
3.
scaffolding and checking the readiness of all
personal protective equipment (PPE), working
equipment and tools in the workshops and which
will be used at the site.
Monitoring all of building’s façades dismounting
works based on work methodologies, SOP and
carried out according to the schedule. Unscrew
4. and remove all of Main Office wooden cabinets
and tables behind the facade glasses, including
the ACP wall and its frames and all of fixed glass
windows in all partitions walls.
Monitoring and verifying the procurement of the
approved building's façades protection materials
5.
to the Vendors / Sub-Contractors according to
technical specifications and shop drawings.
Monitoring and verifying the manufacturing and
installation process of all facades components,
to ensure the facade materials qualities and
robust frames fixation system according to
finished products technical specification and to
6.
ensure it can be completed on time. Conducting
product tests at sites and approving quality of
the finished products. Includes monitoring and
verifying of reinstallation Main Office wooden
cabinets and tables behind the facade glasses.
Monitoring and verifying the Main Contractor’s
Project Completion Report, including inspection,
7. acceptance, closing punch lists and handover
process of Main Contractor's works to BP
Castrol Management.