REALISASI KEMAJUAN PEKERJAAN (KURVA "S")

Kegiatan : Pembangunan Rumah Sakit TNI TK.IV Gorontalo KESDAM XIII/MDK Bulan Ke: Januari S/d Juni
Lokasi : Gorontalo
Departemen/Lembaga : KEMHAN RI - BARANAHAN Periode : 2-Jan-23 S/d 30-Jun-23
Kontraktor : PT. Dwipa Bhirawapersada
Surat Perjanjian : TRAK/1029/XI/2022/PUSKON PDN - Tgl. 3 Nov 2022
JANUARI FEBRUARI MARET APRIL MEI JUNI
MINGGU KE MINGGU KE MINGGU KE MINGGU KE MINGGU KE MINGGU KE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
No Uraian Pekerjaan Bobot ( % ) 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147 154 161 168 175 182 Keterangan
2-Jan 9-Jan 16-Jan 23-Jan 30-Jan 6-Feb 13-Feb 20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun 26-Jun
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb 26-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 30-Jun

A PEKERJAAN PERSIAPAN & SMK3 0.6053 0.0636 0.0636 0.0636 0.0636 0.0636 0.0636 0.0636 0.0636 0.0636 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 - - - - - - - - -

B GEDUNG A (IGD DAN POLIKLINIK)

I PEKERJAAN STRUKTUR 20.5842 - - 0.2224 0.2224 0.2224 0.7207 1.3009 2.4788 3.5933 5.1406 3.3414 3.3414 - - - - - - - - - - - -

II PEKERJAAN ARSITEKTUR 25.9781 - - - - - - - - - 0.9421 0.9421 0.9421 4.7140 3.7718 2.5168 0.8992 0.6245 1.5444 2.2468 2.0536 1.9459 0.9309 0.9518 0.9518

III PEKERJAAN MEP 11.7973 - - - -


RENCANA
- -
KONTRAK
- - - - - - 1.8554 0.4223 1.8820 2.4728 1.8848 2.1577 0.9245 0.1978 - - - -

LIBUR IDUL FITRI

182 Hari Kalender


C BANGUNAN VK

A PEKERJAAN STRUKTUR 8.8426 - - - - - 0.2098 0.2098 1.7902 1.7902 2.1329 1.3548 1.3548 - - - - - - - - - - - -

B PEKERJAAN ARSITEKTUR 9.8476 - - - - - - - - - - 0.4504 1.9579 2.4625 1.4708 0.5929 0.7481 0.3589 0.5906 0.4730 0.2255 0.2585 0.2585 - -

C PEKERJAAN MEP 5.0329 - - - - -


REALISASI
- -
KONTRAK
- - - - 0.5737 0.6567 0.7057 0.1320 0.7282 0.5962 0.7242 0.6559 0.1336 0.1268 - - -

D BANGUNAN GEDUNG PUMP ROOM 1.7893 - - - - - - - - - - 0.2224 0.2224 0.2224 0.3761 0.1538 0.1538 0.1538 0.1538 - - - - - 0.1310

E BANGUNAN GENSET 2.2087 - - - - - - - - - 0.3354 0.4890 0.4890 0.4890 0.1536 0.1536 - - - - - 0.0247 0.0247 0.0247 0.0247

F PEKERJAAN ME KAWASAN 10.4252 - - - - - - - - - - 2.0850 2.0850 2.0850 - - - - - 0.6950 0.6950 0.6950 0.6950 0.6950 0.6950

G PEKERJAAN HALAMAN, SALURAN KELILING KAWASAN 0.6841 - - - - - - - - - 0.1710 0.1710 0.1710 0.0342 - - - - - - - 0.0342 0.0342 0.0342 0.0342

H ALAT SATRI 0.3686 - - - - - - - - - - - - - - - - - 0.0614 0.0614 0.0614 0.0614 0.0614 0.0614 -

I PENYAMBUNGAN DAYA PLN, PDAM & AMDAL/SPL PERIJINAN 1.8361 - - - 0.0246 0.0246 0.0246 0.0246 0.0983 0.0983 0.0983 0.0983 0.0983 0.0701 0.0701 0.5530 0.5530
- - - - - - - -

Jumlah Nilai Pekerjaan Sebelum PPN 11% 100.000

Rencana Kemajuan Pekerjaan 0.0636 0.0636 0.2859 0.3105 0.3105 1.0186 1.5988 4.4308 5.5454 8.8259 9.1602 11.2413 12.5247 6.9058 5.4367 - - 5.0020 3.6181 5.2322 5.0566 3.3669 3.2168 2.0750 2.3203 2.3898
Komulatif Rencana Kemajuan Pekerjaan - 0.0636 0.1271 0.4130 0.7236 1.0341 2.0527 3.6515 8.0823 13.6277 22.4536 31.6138 42.8551 55.3799 62.2857 67.7224 67.7224 67.7224 72.7244 76.3425 81.5747 86.6312 89.9982 93.2150 95.2900 97.6102 100.0000
Realisasi Kemajuan Pekerjaan - -
Komulatif Realisasi Kemajuan Pekerjaan - -
Deviasi - 0.0636

Diketahui Oleh: Diperiksa Oleh :


Dibuat Oleh :
KETUA TIM DIREKSI Manajemen Konstruksi/Kons.Pengawas
KONTRAKTOR PELAKSANA
PT. DUTA CIPTA KARYA
PT. DWIPA BHIRAWA PERSADA

Ir. Yossef Miarso


YUSUP YOGANTARA, ST.