Nama : ADRIANO RIWANDI

Nis : 71422001
Ojt :1

No Tanggal Pekerjaan Jam mulai Jam selesai Total Jam Lembur


-Travel to pt.sml
-inspection,parking
1 -2 Februari 2023 -7.00 -18.00 -2 Jam
unit
-make stand unit
-Travel to unit
-Remove (hose boom
cyl,swing
2 -3 Februari 2023 machinery,swivel -7.47 -19.00 -2,5 Jam
joint)
-Travel back
-Travel back to pdg
3 -4 Februari 2023 -8.00 -22.00 -14 Jam
from belilas
-Traveling to belilas
4 -8 Februari 2023 -8.00 -22.00 -14,5 Jam
from padang
-Travel to unit
-Continue remove &
5 -9 Februari 2023 -7.00 -18.00 -2 Jam
machinery

-Travel to unit
-mobilisasi main swing
cyrcle from camp
6 -11 Februari 2023 -Replace swing cyrcle -7.00 18,00 -11 Jam
-Instal bolt mounting
& cyrcle
-Traveling back

-Traveling to unit
-Continue bolt swing
cyrcle
7 -12 Februari 2023 -Instal swivel joint -7.00 -18.30 -11,5 Jam
-Instal hose boom cyl
-Travel back

-Traveling to central
-Refil hyd oil,grease
swing machinery
8 -14 Februari 2023 -Test running,MTA -7.00 19.00 -3 Jam
electronical system,
test operation

-Traveling to unit
D85SS-2
9 -15 Februari 2023 -PPM unit -7.00 18.00 -2 Jam
-make Document
-Travel back to Pdg
10 -16 Februari 2023 -7.00 22.00 -6 Jam
from belilas
-67.30

Dibuat oleh Diperiksa oleh Disetujui oleh

( Adriano Riwandi ) ( lis Sumirat ,SPV. ) ( Aan Kurnia ,SDH. )