SEPTEMBER 2023
PT PLN (PERSERO)
UNIT INDUK PENYALURAN DAN PUSAT PENGATUR BEBAN SUMATERA
No. Dokumen PR-OPS-DOS-03
PT PLN (PERSERO)
UNIT INDUK P3B SUMATERA
Berlaku Efektif 1 s.d 7 September 2023
KATA PENGANTAR
DAFTAR ISI
Halaman
KATA PENGANTAR .............................................................................................. i
DAFTAR GAMBAR ............................................................................................... iii
DAFTAR TABEL .................................................................................................. iii
1 PRAKIRAAN BEBAN PUNCAK .......................................................................... 1
2 KEMAMPUAN PASOK ..................................................................................... 2
2.1 Waktu Beban Puncak ............................................................................ 2
2.2 Luar Waktu Beban Puncak ..................................................................... 2
3 NERACA ENERGI .......................................................................................... 2
4 UNIT PEMBANGKIT TIDAK SIAP OPERASI....................................................... 5
5 NERACA DAYA .............................................................................................. 8
6 KAJIAN ALIRAN DAYA ................................................................................... 8
6.1 Kendala Operasi ................................................................................... 9
7 PEMELIHARAAN PENYALURAN ......................................................................10
DAFTAR GAMBAR
DAFTAR TABEL
Tabel 1-1 Perkiraan Beban Harian Periode 1 s.d 7 September 2023 ......................... 1
Tabel 3-1 Perkiraan Neraca Energi Periode 1 s.d 7 September 2023 ........................ 3
Tabel 4-1 Unit Pembangkit Tidak Siap Operasi ....................................................... 6
Tabel 5-1 Perkiraan kondisi Sumatera ................................................................... 8
Tabel 7-1 Jadwal Pekerjaan Pemeliharaan Penyaluran .......................................... 10
Beban puncak tertinggi Sistem Sumatera Periode 1 s.d 7 September 2023 diperkirakan 6.934 MW
terjadi pada hari Selasa, 5 September 2023, dengan daya mampu pasok sebesar 7.334 MW.
Beban puncak harian terendah diperkirakan 6.592 MW terjadi pada hari Minggu, 3 September
2023, dengan daya mampu pasok sebesar 7.436 MW.
7500
6,931 6,934
6912 6,906 6,927
6,708 6,592
6500
5500
4500
3500
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
0:30
2:30
4:30
6:30
8:30
10:30
12:30
14:30
16:30
18:30
20:30
22:30
1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep
2 KEMAMPUAN PASOK
2.1 Waktu Beban Puncak
Prakiraan mampu pasok tertinggi pada waktu beban puncak (WBP) sebesar 7.679 MW.
Berdasarkan prakiraan beban sistem dan kesiapan pembangkit dalam periode minggu ini, sistem
Sumatera diperkirakan mengalami 7 hari kondisi normal dengan cadangan putar tertinggi sebesar
374 MW.
Mampu pasok tertinggi pada LWBP sebesar 5.906 MW. Berdasarkan prakiraan beban sistem dan
kesiapan pembangkit, pada LWBP di Sistem Sumatera diperkirakan tidak terjadi pemadaman
akibat defisit.
3 NERACA ENERGI
Berdasarkan prakiraan alokasi energi di Sumatera Energi yang diterima dari pembangkitan
diperkirakan sebesar 929,997 MWh. Prakiraan neraca energi di Sumatera pada periode minggu
ini adalah seperti pada Tabel 3-1.
NO URAIAN ENERGI CF PF
5 PT PLN (Persero) Pembangkitan Sewa, Inalum, IPP Wilayah/Lain-lain 48,357 MWh % %
EXCESS PLTBG TUING (PT GUNUNG PELAWAN LESTARI) 217 MWh 99.4 % 99.4 %
EXCESS PLTBM KUALA (PT UKINDO) 133 MWh 99.0 % 99.0 %
EXCESS PLTBM SIBUHUAN 65 MWh 96.7 % 98.8 %
EXCESS POWER PLTA INALUM (PT INALUM) 5,040 MWh 33.3 % 41.2 %
EXCESS POWER PLTU PELABUHAN TARAHAN 335 MWh 66.5 % 66.5 %
EXCESS POWER PLTU PT BA - MWh - % - %
PLTA KRUENG ISEP 1,679 MWh 99.9 % 99.9 %
PLTA LEBONG 1,322 MWh 65.6 % 98.4 %
PLTBG KWALA SAWIT 102 MWh 60.7 % 92.0 %
PLTBG MSE - ARUNG DALAM 167 MWh 49.7 % 99.4 %
PLTBG PAGAR MERBAU 100 MWh 72.0 % 98.3 %
PLTBG PASIR MANDOGE 251 MWh 74.7 % 99.6 %
PLTBG SUNGAI TERLUNG (PT BANGKA BIOGAS SYNERGY) 139 MWh 41.4 % 96.5 %
PLTBG TERBANGGI ILIR 115 MWh 27.4 % 50.0 %
PLTBM TEMPILANG (PT ENERGY KARYA PERSADA) - MWh - % - %
PLTD RIMO - MWh - % - %
PLTD SW AIR ANYIR - MWh - % - %
PLTD SW MENTOK 420 MWh 41.7 % 50.0 %
PLTD SW TOBOALI 399 MWh 39.6 % 59.4 %
PLTD TAPAK TUAN 17 MWh 3.8 % 12.6 %
PLTG PRABUMULIH 850 MWh 42.2 % 48.2 %
PLTG SAKO 840 MWh 41.7 % 50.0 %
PLTGU MUSI II 1,799 MWh 54.0 % 60.3 %
PLTM AEK SIBUNDONG 974 MWh 58.0 % 98.3 %
PLTM AEK SILANG 2 1,680 MWh 100.0 % 100.0 %
PLTM BAKAL SEMARAK 750 MWh 89.3 % 99.2 %
PLTM BATU BALAI (PT MANNA ENERGI UTAMA) 170 MWh 33.7 % 67.5 %
PLTM BATU BRAK 527 MWh 40.7 % 95.1 %
PLTM BATU GAJAH 1,680 MWh 100.0 % 100.0 %
PLTM DOLOK MASIHUL (PT GLOBAL KARAI ENERGI) 1,126 MWh 100.0 % 100.0 %
PLTM DOLOK SANGGUL (PT ENERGI SAKTI SENTOSA) 1,087 MWh 35.9 % 99.9 %
PLTM DOLOK SANGGUL (PT HUMBAHAS BUMI ENERGI) 840 MWh 100.0 % 100.0 %
PLTM DOLOK SANGGUL (PT MEGA POWER MANDIRI) 1,133 MWh 89.9 % 100.0 %
PLTM ENDIKAT 180 MWh 13.4 % 61.0 %
PLTM KANDIBATA 1,200 MWh 73.6 % 100.0 %
PLTM LAE KOMBIH 3 890 MWh 66.2 % 100.0 %
PLTM LAWE SIKAP 678 MWh 57.7 % 99.9 %
PLTM PADANG GUCI 2 149 MWh 12.7 % 41.3 %
PLTM PARMONANGAN 2 945 MWh 51.1 % 99.9 %
PLTM PT SCE 688 MWh 45.5 % 100.0 %
PLTM SEUPAKAT ACEH - MWh - % - %
PLTM SIDAMANIK (PT GLOBAL HIDRO ENERGI) 1,294 MWh 92.8 % 99.9 %
PLTM SION 1,675 MWh 99.7 % 99.9 %
PLTM SUNGAI BUAYA 504 MWh 100.0 % 100.0 %
PLTM TANAH JAWA (PT BERSAUDARA SIMALUNGUN ENERGI) 1,260 MWh 100.0 % 100.0 %
PLTM TUNGGANG 804 MWh 48.3 % 49.9 %
PLTMG JAYALOKA (PT MURA ENERGI BUANA) 650 MWh 48.4 % 50.9 %
PLTMG LHOKSEUMAWE (PT KERTAS KRAFT ACEH) - MWh - % - %
PLTMG SEMATANG BORANG - MWh - % - %
PLTMG SIBERIDA RENGAT 2,520 MWh 100.0 % 100.0 %
PLTMG SW LIRIK 788 MWh 46.9 % 100.0 %
PLTMG TANJUNG JABUNG - MWh - % - %
PLTMH ANGKUP 26 MWh 44.2 % 91.0 %
PLTMH GUMANTI III RIAU 1,071 MWh 98.8 % 99.6 %
PLTMH GUNTUNG 337 MWh 50.1 % 99.8 %
PLTMH INDURING 151 MWh 44.9 % 90.8 %
PLTMH KOMERING 40 MWh 17.0 % 48.6 %
PLTMH KOTA AGUNG (PT GREEN LAHAT) 240 MWh 14.4 % 53.8 %
PLTMH LAU GUNUNG 1,680 MWh 100.0 % 100.0 %
PLTMH LUBUK GADANG 1,344 MWh 100.0 % 100.0 %
PLTMH LUBUK SAO II 436 MWh 99.8 % 99.8 %
PLTMH NAPAL MELINTANG 14 MWh 16.7 % 83.3 %
PLTMH PADANG GUCI 210 MWh 20.8 % 50.0 %
PLTMH PELANGAI HULU 1,453 MWh 88.3 % 99.9 %
PLTMH SAKO 509 MWh 50.5 % 99.7 %
PLTMH SALIDO KECIL 99 MWh 89.3 % 92.1 %
PLTMH SANGIR HULU 801 MWh 47.7 % 53.0 %
PLTMH SENGAK 18 MWh 14.9 % 63.0 %
PLTMH SIAMANG 49 MWh 19.4 % 97.2 %
PLTS JAKABARING 26 MWh 7.7 % 14.1 %
PLTU BATURAJA 1,671 MWh 49.7 % 49.7 %
Berdasarkan neraca energi diatas, fuel mix energi pada periode minggu ini diperkirakan sebagai
berikut :
SURYA 0.003
BIOGAS 0.12
HSD 1.16
IDO -
BIOMASSA 0.02
PANAS BUMI 11.75 MFO -
AIR 15.28
BATU BARA 49.09
GAS 22.58
HSD PANAS BUMI IDO MFO AIR GAS BATU BARA BIOMASSA BIOGAS SURYA
MULAI SELESAI
PEMBANGKIT (MW) STATUS KETERANGAN
TANGGAL PUKUL TANGGAL PUKUL
PLTA
SIPANSIHAPORAS #01 33.00 24-Aug-23 0:00 13-Sep-23 24:00 PO Annual Inspection plus pekerjaan penormalan system control
RENUN #02 37.91 4-Sep-23 8:00 4-Sep-23 16:00 Performance Test
RENUN #01 34.91 5-Sep-23 8:00 5-Sep-23 16:00 Performance Test
BATUTEGI #01 14.00 5-Sep-23 8:00 5-Sep-23 16:00 MO Pemeliharaan rutin bulanan
KOTO PANJANG #01 38.00 6-Sep-23 8:00 6-Sep-23 16:00 MO Pemeliharaan rutin bulanan
PLTD
PULO PISANG #01 (SWD WARTSILA) 2.30 4-Sep-23 18:00 5-Sep-23 20:00 Uji emisi (WBP selama 2 jam) sesuai unit operasi
PULO PISANG #02 (NIIGATA) 2.19 4-Sep-23 18:00 5-Sep-23 20:00 Uji emisi (WBP selama 2 jam) sesuai unit operasi
PULO PISANG #04 (DEUTZ) 0.66 4-Sep-23 18:00 5-Sep-23 20:00 Uji emisi (WBP selama 2 jam) sesuai unit operasi
PULO PISANG #05 (DEUTZ) 0.67 4-Sep-23 18:00 5-Sep-23 20:00 Uji emisi (WBP selama 2 jam) sesuai unit operasi
PULO PISANG #06 (SWD WERKSPOOR) 2.36 4-Sep-23 18:00 5-Sep-23 20:00 Uji emisi (WBP selama 2 jam) sesuai unit operasi
TELUK BETUNG #10 (SULZER) 2.31 5-Sep-23 8:00 5-Sep-23 16:00 MO Pemeliharaan rutin P2 bulanan
TARAHAN #05 (SWD) 2.70 6-Sep-23 8:00 6-Sep-23 16:00 MO Pemeliharaan rutin P2 bulanan
TARAHAN #06 (SWD) 2.76 7-Sep-23 8:00 7-Sep-23 16:00 MO Pemeliharaan rutin P2 bulanan
PLTG
MPP TARAHAN #01 28.48 2-Sep-23 14:00 2-Sep-23 17:00 Performance Test (beban 50% dan 75% selama masing-masing 1 jam)
MPP TARAHAN #02 28.01 2-Sep-23 14:00 2-Sep-23 17:00 Performance Test (beban 50% dan 75% selama masing-masing 1 jam)
MPP TARAHAN #03 28.39 2-Sep-23 14:00 2-Sep-23 17:00 Performance Test (beban 50% dan 75% selama masing-masing 1 jam)
MPP TARAHAN #04 28.01 2-Sep-23 14:00 2-Sep-23 17:00 Performance Test (beban 50% dan 75% selama masing-masing 1 jam)
GLUGUR #01 (J.B.E) 10.00 4-Sep-23 18:00 4-Sep-23 20:00 Pengujian silencer exhaust, sesuai unit operasi
MPP PAYA PASIR #02 26.83 5-Sep-23 8:00 5-Sep-23 16:00 MO Monthly Inspection
MPP BALAI PUNGUT #01 27.74 5-Sep-23 16:00 5-Sep-23 22:00 Uji emisi bulanan (selama 2 jam bergantian)
MPP BALAI PUNGUT #02 27.80 5-Sep-23 16:00 5-Sep-23 22:00 Uji emisi bulanan (selama 2 jam bergantian)
MPP BALAI PUNGUT #03 26.96 5-Sep-23 16:00 5-Sep-23 22:00 Uji emisi bulanan (selama 2 jam bergantian)
MPP BALAI PUNGUT #01 27.74 6-Sep-23 8:00 6-Sep-23 16:00 MO Monthly Inspection
MPP BALAI PUNGUT #01 27.74 7-Sep-23 8:00 7-Sep-23 16:00 MO Perbaikan CEMS (penambahan lubang sampling)
PLTU
TENAYAN #02 87.50 18-Aug-23 4:11 14-Sep-23 24:00 PO Simple Inspection
BUKIT ASAM #04 52.50 26-Aug-23 0:00 9-Oct-23 24:00 PO Serious Inspection
Cleaning banker coal feeder (beban 40 MW netto), TENTATIVE sesuai dengan
SEBALANG #01 75.00 1-Sep-23 8:00 4-Sep-23 16:00 MD
kondisi sistem Sumatera dan batubara, bisa support beban max di WBP
Cleaning banker coal feeder (beban 40 MW netto), TENTATIVE sesuai dengan
SEBALANG #02 75.00 1-Sep-23 8:00 3-Sep-23 16:00 MD
kondisi sistem Sumatera dan batubara, bisa support beban max di WBP
SEBALANG #02 75.00 4-Sep-23 0:00 18-Sep-23 24:00 MO Boiler Inspection
NAGAN RAYA #02 80.00 5-Sep-23 10:00 5-Sep-23 12:00 Performance Test (beban 80 MW netto)
TARAHAN #04 85.00 5-Sep-23 8:00 5-Sep-23 16:00 MD Kalibrasi coal feeder 4A (beban 75 MW netto)
SEBALANG #01 75.00 5-Sep-23 9:00 5-Sep-23 15:00 Performance Test uji daya mampu dan efisiensi (beban 50% dan beban 75%)
SEBALANG #01 75.00 6-Sep-23 9:00 6-Sep-23 15:00 Performance Test uji daya mampu dan efisiensi (beban 85% dan beban 100%)
Cleaning banker coal feeder (beban 40 MW netto), TENTATIVE sesuai dengan
SEBALANG #01 75.00 7-Sep-23 8:00 7-Sep-23 16:00 MD
kondisi sistem Sumatera dan batubara, bisa support beban max di WBP
NAGAN RAYA #02 80.00 7-Sep-23 0:00 18-Oct-23 24:00 PO Mean Inspection
TARAHAN #04 85.00 7-Sep-23 8:00 7-Sep-23 16:00 MD Kalibrasi coal feeder 4B (beban 75 MW netto)
PLTGU
BELAWAN GT 1.1 90.00 2-Sep-23 0:00 5-Sep-23 16:00 MO Penggantian filter air intake dan pengujian interchange trafo SFC GT 1.1 dan GT 1.2
BELAWAN GT 1.2 90.00 2-Sep-23 0:00 4-Sep-23 16:00 MO Pengujian interchange trafo SFC GT 1.1 dan GT 1.2
BELAWAN ST 1.0 80.00 2-Sep-23 0:00 4-Sep-23 20:00 MO Penggantian filter air intake dan pengujian interchange trafo SFC GT 1.1 dan GT 1.2
Penggantian filter air intake dan pengujian interchange trafo SFC GT 1.1 (beban 35 MW
BELAWAN ST 1.0 80.00 4-Sep-23 20:00 5-Sep-23 20:00 MD
netto)
PLTMG
ARUN #05 8.50 9-Aug-23 0:00 7-Sep-23 24:00 PO TBM interval 32000 jam
ARUN #19 8.50 9-Aug-23 0:00 7-Sep-23 24:00 PO TBM interval 32000 jam
ARUN EKSPANSI #04 18.27 28-Aug-23 0:00 1-Sep-23 24:00 PO TBM interval 15000 jam
Pergantian seal O-ring mulai 29 Agustus 2023 pukul 08:00 WIB s.d 1 September 2023
ARUN EKSPANSI #01 17.90 29-Aug-23 8:00 1-Sep-23 24:00 ME
pukul 20:00 WIB, extend s.d 1 September 24:00 WIB
ARUN EKSPANSI #01 17.90 2-Sep-23 0:00 6-Sep-23 24:00 PO TBM interval 15000 jam
BALAI PUNGUT DURI #02 14.32 4-Sep-23 8:00 5-Sep-23 17:00 MO Pemeliharaan periodik 47000 jam (LWBP)
BALAI PUNGUT DURI #03 14.32 6-Sep-23 9:00 6-Sep-23 15:00 MO Pemeliharaan CGR
BALAI PUNGUT DURI #01 14.32 6-Sep-23 0:00 12-Sep-23 24:00 PO Pemeliharaan periodik 57000 jam plus pelepasan running in filter dan perbaikan CAR
ARUN EKSPANSI #02 18.22 7-Sep-23 0:00 14-Sep-23 24:00 PO TBM interval 15000 jam
BALAI PUNGUT DURI #04 14.32 7-Sep-23 9:00 7-Sep-23 15:00 MO Pemeliharaan CGR
BALAI PUNGUT DURI #07 14.32 7-Sep-23 9:00 7-Sep-23 15:00 MO Pemeliharaan CGR
PLTMH
BATANG GADIS #01 0.38 2-Sep-23 8:00 3-Sep-23 16:00 MO Pemeliharaan TW III, cleaning HE & performance (LWBP)
BATANG GADIS #02 0.38 2-Sep-23 8:00 3-Sep-23 16:00 MO Pemeliharaan TW III, cleaning HE & performance (LWBP)
TONDUHAN #01 0.19 3-Sep-23 8:00 3-Sep-23 16:00 Performance Test Pra Annual Inspection Plus
TONDUHAN #02 0.19 3-Sep-23 8:00 3-Sep-23 16:00 Performance Test Pra Annual Inspection Plus
TONDUHAN #01 0.19 4-Sep-23 0:00 13-Sep-23 24:00 PO Annual Inspection plus penggantian bearing & pengerukan sendimen
TONDUHAN #02 0.19 4-Sep-23 0:00 13-Sep-23 24:00 PO Annual Inspection plus & pengerukan sedimen
RAISAN #01 0.65 6-Sep-23 8:00 6-Sep-23 16:00 Performance Test
RAISAN #02 0.65 7-Sep-23 8:00 7-Sep-23 16:00 Performance Test
PLTA
SINGKARAK #03 43.66 1-Sep-23 9:00 1-Sep-23 16:00 MO Pemeliharaan rutin bulanan
SINGKARAK #03 43.66 2-Sep-23 0:00 8-Sep-23 24:00 MO Penggantian CT PT
SINGKARAK #02 43.66 4-Sep-23 9:00 4-Sep-23 16:00 MO Pemeliharaan rutin bulanan
TES #01 0.54 4-Sep-23 8:00 4-Sep-23 13:00 MO Pemeliharaan rutin bulanan
TES #02 0.54 4-Sep-23 8:00 4-Sep-23 13:00 MO Pemeliharaan rutin bulanan
MUSI #01 69.70 4-Sep-23 8:00 4-Sep-23 16:00 MO Pemeliharaan rutin bulanan
SINGKARAK #01 43.66 4-Sep-23 9:00 5-Sep-23 16:00 Pdm Test (LWBP, unit bergantian)
SINGKARAK #02 43.66 4-Sep-23 9:00 5-Sep-23 16:00 Pdm Test (LWBP, unit bergantian)
SINGKARAK #03 43.66 4-Sep-23 9:00 5-Sep-23 16:00 Pdm Test (LWBP, unit bergantian)
SINGKARAK #04 43.66 4-Sep-23 9:00 5-Sep-23 16:00 Pdm Test (LWBP, unit bergantian)
MANINJAU #03 16.95 5-Sep-23 9:00 5-Sep-23 13:00 MO Pemeliharaan rutin bulanan
TES #01 0.54 6-Sep-23 8:00 6-Sep-23 16:00 Pdm Test
TES #02 0.54 6-Sep-23 8:00 6-Sep-23 16:00 Pdm Test
TES #03 4.27 6-Sep-23 8:00 6-Sep-23 16:00 Pdm Test
TES #04 4.27 6-Sep-23 8:00 6-Sep-23 16:00 Pdm Test
BATANG AGAM #02 3.49 7-Sep-23 9:00 7-Sep-23 13:00 MO Pemeliharaan rutin bulanan
PLTD
SUNGAI JUARO #01 (HITACHI) 9.48 6-Sep-23 8:00 6-Sep-23 16:00 MO Perbaikan kebocoran oli trafo (Lepas PMT)
PLTG
BOT PAYO SELINCAH #02 46.78 4-Sep-23 0:00 10-Sep-23 24:00 MO Pekerjaan alignment engine turbine
BOT PAYO SELINCAH #02 46.78 6-Sep-23 0:00 6-Sep-23 24:00 MO Pekerjaan washing compressor 2A
PLTGU
Waterwash , penggantian pre filter , perbaikan control steam turbin , pengelasan
INDRALAYA #02 (ST 1.0) 15.00 6-Sep-23 0:00 8-Sep-23 24:00 MO
kebocoran RWP dan BFP
PLTMG
SEI GELAM (CNG) 93.50 23-Aug-23 0:30 27-Sep-23 24:00 PD Pemeliharaan TBM 32000 jam unit #6
SEI GELAM (CNG) 93.50 23-Aug-23 0:30 27-Sep-23 24:00 PD Pemeliharaan TBM 32000 jam unit #8
SEI GELAM (CNG) 93.50 1-Sep-23 0:00 1-Sep-23 24:00 MD Perbaikan kebocoran exhaust gas pada multiduct cyl A10 unit #5
SEI GELAM (CNG) 93.50 4-Sep-23 0:00 4-Sep-23 24:00 MD Pengecekan exhaust sistem unit #4
SEI GELAM (CNG) 93.50 5-Sep-23 0:00 5-Sep-23 24:00 MD Pengecekan exhaust sistem unit #1
SEI GELAM (CNG) 93.50 6-Sep-23 0:00 6-Sep-23 24:00 MD Pengecekan exhaust sistem unit #2
SEI GELAM (CNG) 93.50 7-Sep-23 0:00 7-Sep-23 24:00 MD Pengecekan exhaust sistem unit #7
MULAI SELESAI
PEMBANGKIT (MW) STATUS KETERANGAN
TANGGAL PUKUL TANGGAL PUKUL
PLTD
MERAWANG #08 (CATERPILLAR #2) 4.23 3-Aug-23 21:12 23-Sep-23 24:00 MO Major overhaul
MERAWANG #09 (MIRRLEES #3) 4.70 21-Aug-23 0:00 4-Sep-23 24:00 MO Major overhaul
PLTBM
TEMPILANG (PT ENERGY KARYA PERSADA) 5.00 1-Sep-23 0:00 20-Sep-23 24:00 PO Maintenance Boiler and Turbin
SUNGAI TERLUNG (PT BANGKA BIOGAS SYNERGY) 2.00 5-Sep-23 0:00 7-Sep-23 24:00 MO Penggantian cylinder haed
1.4 IPP
PLTA
SEMANGKA #01 27.70 19-Aug-23 0:00 17-Sep-23 24:00 PO Penggantian runner
HASANG 41.22 6-Sep-23 8:00 6-Sep-23 16:30 MO Pekerjaan weir flushing
PLTU
SUMSEL V #02 150.00 1-Aug-23 10:06 19-Sep-23 24:00 PO Major Overhaul
KEBAN AGUNG #02 120.00 12-Aug-23 9:39 30-Sep-23 24:00 PO Serious Inspection
PLTP
SARULLA SIL 115.40 5-Sep-23 0:00 5-Sep-23 24:00 MD Uji kinerja aliran dengan TFT (beban 109.4 MW netto)
SARULLA SIL 115.40 6-Sep-23 0:00 6-Sep-23 24:00 MD Uji kinerja aliran dengan TFT (beban 96.4 MW netto)
Pemeliharaan tahunan (Unit #1 beroperasi 32.5 MW netto dan unit #2 beroperasi 32.5
SARULLA NIL 124.82 1-Sep-23 0:00 7-Sep-23 24:00 PD
MW netto)
RANTAU DEDAP 70.72 3-Sep-23 8:00 3-Sep-23 9:00 MD Test Turbine Valve (selama ± 60 menit)
MUARA LABOH 86.03 6-Sep-23 10:00 6-Sep-23 11:30 MD Test Turbine Valve (beban 72 MW netto ± 90 menit)
PLTMG
TANJUNG JABUNG 7.20 3-Sep-23 0:00 16-Sep-23 24:00 MD Pemeliharaan 60000 jam unit #2
JAYALOKA 10.00 2-Sep-23 8:00 2-Sep-23 16:00 MD Maintenance Charge Air Cooler unit #2
PLTGU
MUSI II 19.83 2-Sep-23 0:00 4-Sep-23 17:00 MD Washing turbine unit #2 (beban 14.7 MW netto)
PLTMH
KOMERING 1.40 2-Sep-23 8:00 15-Sep-23 16:00 MO Pemeliharaan rutin (LWBP)
KOTA AGUNG (PT GREEN LAHAT) 9.90 4-Sep-23 0:00 15-Sep-23 24:00 PO Major overhaul
ENDIKAT 8.00 4-Sep-23 0:00 15-Sep-23 24:00 PO Major overhaul
PLTU
Gangguan gagal start (MB mulai 1 Januari s.d 31 Desember 2018), gangguan
BELAWAN #03 35.00 1-Jan-19 0:00 2023 24:00 FO
kebocoran boiler sejak 22 November 2017 Pukul 21:45 WIB
BELAWAN #04 35.00 27-Jan-21 18:00 2023 24:00 FO Gangguan kendala gas (tidak bisa convert ke minyak)
PLTG
TELUK LEMBU #03 15.00 11-Jun-21 8:01 2023 24:00 FO Gangguan kendala gas
BALAI PUNGUT DURI #2 14.85 27-Aug-21 18:59 2023 24:00 FO Gangguan vibrasi
SW TELUK LEMBU II (PT PJBS) 50.00 29-Jul-22 9:32 2023 24:00 FO Gangguan kendala gas
TELUK LEMBU #02 13.86 4-Mar-23 10:26 2023 24:00 FO Gangguan kendala gas
MPP TARAHAN #01 28.48 30-Jun-23 18:42 Dec-23 24:00 FO Gangguan fuel control dan sudu turbin
Gangguan (sebelumnya pekerjaan Maintenance Outage mulai 10 s.d 24 Juli 2023,
SEBALANG 16.34 1-Aug-23 0:00 2023 24:00 FO
extend s.d 31 Juli 2023)
PLTG
BOT TALANG DUKU #03 (LM 2500) 21.50 16-Aug-19 0:00 - 24:00 FO Gangguan (sebelumnya zero Condition mulai 8 April s.d 15 Agustus 2019)
BOT TALANG DUKU #02 (TM 2500) 35.10 17-Dec-19 18:06 - 24:00 FO Gangguan indikasi TDT 1007 high
Gangguan (sebelumnya pekerjaan HSRI mulai 22 Maret s.d 17 September 2019,
JAKA BARING #01 16.00 1-Feb-20 0:00 - 24:00 FO
extend s.d 31 Januari 2020)
BOT PAYO SELINCAH #01 46.78 6-Jun-20 0:00 2023 24:00 FO Gangguan (sebelumnya kendala gas fuel valve 1B mulai 5 Juni 2019)
JAKA BARING #02 17.50 1-Sep-20 0:00 - 24:00 FO Habis kontrak gas
JAKA BARING #03 17.00 1-Sep-20 0:00 - 24:00 FO Habis kontrak gas
TALANG DUKU #01 12.00 1-Nov-20 0:00 - 24:00 FO Habis kontrak gas
KERAMASAN #3 15.00 12-Jan-21 16:31 - 24:00 FO Gangguan rotor turbine (usulan RU)
KERAMASAN #1 9.80 8-Feb-21 0:27 - 24:00 FO Gangguan kebocoran minyak pada isolator PMT (usulan RU)
KERAMASAN #2 9.80 2-Aug-22 10:58 2023 24:00 FO Gangguan kendala gas
BORANG #03 11.00 8-Nov-22 19:53 2023 24:00 FO Gangguan kendala gas
PLTU
PANGKALAN SUSU #01 180.00 25-Aug-23 0:00 22-Oct-23 24:00 FO Gangguan (sebelumnya pekerjaan recovery generator mulai 1 s.d 24 Agustus 2023)
PLTGU
KERAMASAN #02 37.00 29-Aug-23 19:15 2023 24:00 FO Gangguan kebocoran backpass boiler
2.3 IPP
PLTGU
GUNUNG MEGANG #02 (GT 1.2) 40.00 18-Mar-23 9:55 2023 24:00 FO Gangguan vibrasi generator
GUNUNG MEGANG #03 (ST 1.0) 30.00 22-Aug-23 21:24 2023 24:00 FO Gangguan kebocoran tube boiler
PLTU
Maintenance Derating Balancing SA fan
(Tidak diakomodir, PLTU Tenayan Unit 2 pekerjaan Simple Inspection mulai 18
TENAYAN #01 87.50 1-Sep-23 0:00 3-Sep-23 24:00
Agustus s.d 14 September 2023)
PLTU
Pekerjaan thicness wall tube
LABUHAN ANGIN #01 70.00 2-Sep-23 0:00 8-Sep-23 24:00
(Tidak diakomodir, terkait kondisi sistem Sumatera)
Pekerjaan perbaikan kebocoran bed material
LABUHAN ANGIN #02 70.00 2-Sep-23 0:00 8-Sep-23 24:00
(Tidak diakomodir, terkait kondisi sistem Sumatera)
5 NERACA DAYA
Neraca Daya Sumatera pada WBP dapat dilihat pada Gambar 5-1 berikut.
10000
9500
9000
8500
8000
7500
7000
6500
6000
5500
5000
4500
4000
3500
3000
2500
2000
1500
1000
500
0
1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep
Daya Mampu Cadangan Operasi Derating Pemeliharaan Gangguan (FO) Beban Puncak
Perkiraan kondisi sistem Sumatera dapat dilihat pada Tabel 5-1 berikut.
LNGSA SUMUT
150 kV
KIT : 1908 MW
PBDAN
150 kV INALUM : 90 MW
BEBAN : 1949 MW
ACEH
KIT : 538 MW RIAU
BEBAN : 487 MW
RTPAT KIT : 686 MW
151 kV
BEBAN : 864 MW
BBATU
152 kV
NPSDM
285 kV KTPJG
151 kV
PYBUH
281 kV
JAMBI
KIT : 77 MW
TLKTN
SUMBAR KLJAO
152 kV BEBAN : 402 MW
280 kV
KIT : 547 MW
BEBAN : 744 MW
RMBAI PSLCH
276 kV 152 kV
BANGKA
MBNGO NADRI KIT : 178 MW
279 kV 282 kV
MNTOK SLIAT BEBAN : 190 MW
158 kV . 150 kV
BNGKO SMSLV
280 kV 283 kV
BENGKULU KOBA
153 kV
LBGAU
KIT : 444 MW 285 kV
BEBAN : 165 MW PKLNG TBALI
159 kV 153 kV
KYANG
152 kV
GMWNG
154 kV
BTRJA
152 kV
BKMNG
SUMSEL
151 kV
KIT : 1713 MW
BEBAN : 909 MW
LAMPUNG
KIT : 752 MW
BEBAN : 1223 MW KLNDA
149 kV
Kondisi pasokan sistem Sumatera dipengaruhi oleh ketidaksiapan beberapa unit pembangkit
akibat gangguan maupun pemeliharaan. Di sistem Sumatera tidak terdapat GI dengan kualitas
7 PEMELIHARAAN PENYALURAN
Penyaluran 70 kV, 150 kV, 275 kV di sistem Sumatera yang tidak siap operasi karena dipelihara
selama Periode 1 s.d 7 September 2023 tertera di dalam Tabel 7-1 berikut.
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBU
2-Sep 8:00 2-Sep 16:00 GI TLCUT Penggantian Kubikel PS TD#1 BAY Kubikel 3
3-Sep 8:00 3-Sep 16:00 GI LSMWE Pemasangan Kubikel BBVT TD#2 BAY Kubikel 3
4-Sep 8:00 5-Sep 16:00 SUTT BIRUN - SIGLI Assesmen Isolator Level I (Inspeksi KADET) Tower 128-139 Tanpa Padam 5
4-Sep 8:00 5-Sep 16:00 SUTT SMLGA - SIGLI Assesmen Isolator Level I (Inspeksi KADET) Tower 128-139 Tanpa Padam 5
4-Sep 8:00 5-Sep 16:00 GI LSMWE Pemeliharaan 2 Tahunan Batere dan Rectifier 110 VDC Bank 1 Tanpa Padam 5
4-Sep 8:00 7-Sep 16:00 SUTT NAGAN - SIGLI Thermovisi Jaringan SUTT 150 kV Tanpa Padam 5
4-Sep 8:00 7-Sep 16:00 SUTT BACEH - ULEKR Thermovisi Jaringan SUTT 150 kV Tanpa Padam 5
4-Sep 8:00 7-Sep 16:00 SUTT ULEKR - KRAYA Thermovisi Jaringan SUTT 150 kV Tanpa Padam 5
4-Sep 8:00 7-Sep 16:00 SUTT NAGAN - SIGLI Thermovisi Jaringan SUTT 150 kV T. 1-65 Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI ULEKR Pemeliharaan 2 Tahunan BAY Penghantar 150 kV BACEH 1 BAY PHT 3
5-Sep 8:00 5-Sep 16:00 GI BLPDI Pengujian PD Online dan Ultrasound Kubikel 20 kV Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 PGELI ASSESMEN ISOLATOR SERANDANG MENGGUNAKAN KADET Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 PORSA Penggantian Isolator FO Phasa T arah T.141 Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 KTJNG Pemeliharaan 2 Tahunan BAY TD 1 DAN KUB 20 KV 3
6-Sep 8:00 6-Sep 16:00 GI BACEH Pemeliharaan 2 Tahunan BAY Penghantar BAY ULKRG 1 3
6-Sep 8:00 6-Sep 16:00 GI MLBOH Pengujian PD Online dan Ultrasound Kubikel 20 kV Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 SUTT BIRUN - SIGLI Assesmen Isolator Level I (Inspeksi KADET) Tower 192-203 Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 SUTT SMLGA - SIGLI Assesmen Isolator Level I (Inspeksi KADET) Tower 192-203 Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GI LSMWE Pemeliharaan 2 Tahunan Batere dan Rectifier 110 VDC Bank 2 Tanpa Padam 5
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBU
6-Sep 8:00 6-Sep 16:00 PORSA Penggantian Isolator FO Phasa R arah T.140 Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 BTAGI Pemeliharaan 2 Tahunan & Har PMS Bus PHT TTKNG 1 3
7-Sep 8:00 7-Sep 16:00 GI BACEH Pemeliharaan 2 Tahunan BAY Capacitor Bank 3 25 MVAr BAY CAP 3
7-Sep 8:00 7-Sep 16:00 GI NAGAN Pengujian PD Online dan Ultrasound Kubikel 20 kV Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GI BTAGI Pemeliharaan 2 Tahunan BAY trafo Daya 2 & Kub 20 kV 3
7-Sep 8:00 7-Sep 16:00 GI BTAGI PEMELIHARAAN PMS BUS DAN PEMBERSIHAN HV CLAMP Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GI PORSA Pembersihan Isolator Kotor Phasa RST Tanpa Padam 5
SBT
1-Sep 8:00 1-Sep 16:00 GI RIAU Uji Comtrade SUTT 150 kV RIAU - TNYAN 2 3
GI MBNGO, GI MTEBO,
1-Sep 8:00 11-Sep 16:00 Pengukuran PD Online, Seluruh Kubikel dan kabel power incoming Tanpa Padam 5
GI BNGKO & GI SPNUH
1-Sep 8:00 1-Sep 16:00 GI PLIMO Pengecekan error kWh meter dan AMR, TD#1,2 & PS GI Tanpa Padam 5
2-Sep 8:00 2-Sep 16:00 GI DUMAI Pemeliharaan 2 tahunan SUTT 150 kV DUMAI - KDMAI 1 & BUS A 150 kV 3
3-Sep 8:00 3-Sep 16:00 GI DUMAI Pemeliharaan 2 tahunan SUTT 150 kV DUMAI - KDMAI 2 & BUS A 150 kV 3
4-Sep 8:00 4-Sep 16:00 GI RNGAT Pemeliharaan 2 tahunan SUTT 150 kV RNGAT - TMLAN 1 3
5-Sep 8:00 5-Sep 16:00 GITET PYBUH PEMELIHARAAN 2 TAHUNAN REAKTOR 275 KV 50 MVAR & OHL 6B5 3
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBT
5-Sep 8:00 5-Sep 16:00 GI MSBAK PD ONLINE, Tanpa Padam Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI PSPTH Pengecekan error kWh meter dan AMR, TD#1,2,3 & PS GI Tanpa Padam 5
5-Sep 8:00 7-Sep 16:00 GI KTPJG Pemeriksaan Relay Defense Scheme, RDS Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GITET PYBUH PEMELIHARAAN 2 TAHUNAN REAKTOR 275 KV 50 MVAR & OHL 6B5 3
6-Sep 8:00 6-Sep 16:00 GI SALAK Modifikasi rangkaian CTD TD#2 60 MVA 3
6-Sep 8:00 6-Sep 16:00 GI BNGUS Har 2 Tahunan Kubikel 20 kV TD#2 30 MVA 3
6-Sep 8:00 6-Sep 11:00 GI NADRI Penggantian Keypad Relay Proteksi F.Cincau 2
6-Sep 8:00 6-Sep 13:00 GITET NADRI PD ONLINE, Tanpa Padam Tanpa Padam 5
6-Sep 8:00 6-Sep 13:00 GITET NADRI PEMELIHARAAN RECTIFIER, Tanpa Padam Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GI KID Pengecekan error kWh meter dan AMR, TD#1,2 & PS GI Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GITET PYBUH PEMELIHARAAN 2 TAHUNAN OHL 275 KV 6AB5 DIAMETER # 5 COUPLE 3
- PEMASANGAN EWARS
7-Sep 8:00 7-Sep 16:00 GI PSMAN TD#1 60 MVA 3
- Pemisahan DC sisi 150 & 20 kV
7-Sep 8:00 7-Sep 14:00 GI PSLCH Penggantian Power Meter F.KELAPA & F.KAKTUS 2
7-Sep 8:00 7-Sep 13:00 GI SGLAM PD ONLINE, Tanpa Padam Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GI MBNGO Pengecekan wiring SCADA SUTT 150 kV MBNGO - MTEBO 1 3
7-Sep 8:00 7-Sep 16:00 GI BGAPI Pengecekan error kWh meter dan AMR, TD#1 & PS GI Tanpa Padam 5
SBS
1-Sep 8:00 1-Sep 16:00 BRANG Inspeksi CBM Level 2 proteksi Tanpa Padam 5
GI KTPNG- GI KLNDA-
1-Sep 8:00 1-Sep 16:00 GI SDMLY-GI NEW CBM LEVEL 2 PROTEKSI Tanpa Padam 5
TARHAN - GI TARHAN
1-Sep 9:00 1-Sep 16:00 PLTU KBANG PEMELIHARAAN PHT LAHAT 2 SUTT 150 KV LAHAT-KBANG 2 3
1-Sep 9:00 1-Sep 16:00 GI AIR ANYIR Commisioning PTP Scada GI Air Anyir (BAY Trafo GT -2) BAY Trafo GT -2 3
1-Sep 9:00 4-Sep 16:00 GI PBLIH Pek. Relokasi dan Pemeliharaan Tower Telekomunikasi Radio Tanpa Padam 5
1-Sep 9:00 6-Sep 16:00 GI Sekayu Pek. Pemasangan dan Pemeliharaan Tower Telekomunikasi Radio Tanpa Padam 5
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBS
1-Sep 8:00 1-Sep 16:00 GNDUS Pemeliharaan Semester Rectifier #1 Tanpa Padam 5
1-Sep 8:00 1-Sep 16:00 BTUNG - SKAYU INSPEKSI DRONE T.72 - T.78 PHT BTUNG - SKAYU Tanpa Padam 5
1-Sep 8:00 1-Sep 16:00 KOTIM Inspeksi CBM Proteksi Level 2 Tanpa Padam 5
1-Sep 8:00 1-Sep 16:00 BGRAN Inspeksi CBM Proteksi Level 2 Tanpa Padam 5
1-Sep 9:00 1-Sep 16:00 KNTEN Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
1-Sep 9:00 1-Sep 16:00 TJAPI Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
2-Sep 9:00 2-Sep 16:00 PLTU KBANG PEMELIHARAAN PHT LAHAT 2 SUTT 150 KV LAHAT-KBANG 2 3
JSA Perbaikan Hot Spot Kontak Utama PMS Bus 1 Fasa T BAY
4-Sep 8:00 4-Sep 16:00 GI Pagelaran Tanpa Padam 5
Trafo #1
GI SUTAMI - GI SKRME -
4-Sep 8:00 4-Sep 16:00 CBM LEVEL 2 PROTEKSI Tanpa Padam 5
GI JTANG
Thermovisi
30,37,41,42,44,46,48,49,50,51,53,54,55,56,56A,57,58,59,60,63,64
SUTT 150 kV PGLAM -
4-Sep 8:00 7-Sep 16:00 ,66,67,68,69,72,74,75,76,77,79,80,81,82,87,89,93,94,95,112,113,1 Tanpa Padam 5
MANNA
14,115,116,117,118,119,120,121,122,123,170,173,176,177,181,1
82,183,184,189,190,197,204,209,211,219,220 (67 tower)
4-Sep 9:00 4-Sep 12:00 GI Sukamerindu Har 2 Tahunan Penyulang 20kV Kb Seri Penyulang 20kV Kb Seri 3
4-Sep 13:00 4-Sep 16:00 GI Sukamerindu Har 2 Tahunan Penyulang 20kV Basuki Rahmat Penyulang 20kV Basuki Rahmat 3
4-Sep 8:00 4-Sep 16:00 GI SUKAMERINDU Pengukuran Thermovisi MTU Switchyard 70 KV Tanpa Padam 5
4-Sep 8:00 4-Sep 16:00 GI PEKALONGAN Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
4-Sep 8:00 4-Sep 16:00 GI PULAU BAAI Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
4-Sep 8:00 4-Sep 16:00 GI TES Pengukuran Thermovisi MTU Switchyard 70 KV Tanpa Padam 5
4-Sep 8:00 4-Sep 16:00 GI LUBUK LINGGAU Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
GITET LUBUK
4-Sep 8:00 4-Sep 16:00 Pengukuran Thermovisi MTU Switchyard 275 KV Tanpa Padam 5
LINGGAU
4-Sep 9:00 4-Sep 16:00 GI AIR ANYIR Commissoning PTP SCADA Gl Air Anyir (BAY Trafo TFT-1) BAY Trafo TFT -1 3
4-Sep 9:00 10-Sep 16:00 GITET SGLIN Pek. Pemasangan dan Pemeliharaan Tower Telekomunikasi Radio Tanpa Padam 5
4-Sep 8:00 4-Sep 16:00 GI TRATU HAR 2 TAHUNAN BAY KOPEL 70 KV KOPEL 70 KV 3
4-Sep 8:00 4-Sep 16:00 TLKLP Inspeksi CBM Level 2 proteksi Tanpa Padam 5
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBS
4-Sep 8:00 4-Sep 16:00 NRING Perbaikan Asimetris PMS Bus 1 PHT 150 KV MARIANA 1 PHT MARIANA 1 DAN PADAM BUSBAR 1 150 kV 3
4-Sep 8:00 4-Sep 16:00 MRINA - BRANG Pemeliharaan anti binatang MRINA - BRANG T.6, T.13, T.26 Tanpa Padam 5
4-Sep 8:00 4-Sep 16:00 GI KYUNG HAR 2 TAHUNAN CHARGER & BAT.48 VDC BANK 1 CHARGER & BAT.48 VDC BANK 1 3
4-Sep 9:00 4-Sep 16:00 TLKLP Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
4-Sep 9:00 4-Sep 16:00 GNDUS Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
4-Sep 9:00 4-Sep 16:00 KOBAR Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 DPSNA PEMELIHARAAN Pht. 150 KV DENTE TELDAS # 1 Pht. 150 KV DENTE TELDAS # 1 3
PEMELIHARAAN KOPEL PLTD 1 TRH11, PENYULANG 20KV KOPEL PLTD 1 TRH11, PENYULANG 20KV SURUT
5-Sep 8:00 5-Sep 12:00 TRHAN 1
SURUT TRH25 TRH25
5-Sep 8:00 6-Sep 16:00 GI Dipasena Bantuan Personil HAR Tahunan BAY Pht Dente Teladas 1 & 2 Tanpa Padam 5
JSA Perbaikan Hot Spot Kontak Utama PMS Line Fasa R BAY Pht
5-Sep 8:00 5-Sep 16:00 GI Ulubelu Tanpa Padam 5
Batutegi & Kontak Utama PMS Line Fasa ST BAY Pht Pagelaran
SUTT 150 kV Kotabumi - Download TLA SUTT 150 kV Kotabumi - Bukit Kemuning T.40, T.63,
5-Sep 8:00 5-Sep 16:00 Tanpa Padam 5
Bukit Kemuning T.87
GI KALIANDA-
5-Sep 8:00 5-Sep 16:00 Pengujian Lokal TWS GI KALIANDA GI SEBALANG Tanpa Padam 5
SEBALANG
5-Sep 8:00 5-Sep 16:00 GI BUKIT ASAM Pemeliharaan 2 Tahunan BAY TD#2 150/20 kV 60 MVA TD #2 60 MVA 3
5-Sep 9:00 5-Sep 12:00 GI Sukamerindu Har 2 Tahunan Penyulang 20kV exp. Pulau Bai Penyulang 20kV exp. Pulau Bai 3
5-Sep 13:00 5-Sep 16:00 GI Sukamerindu Har 2 Tahunan Penyulang 20kV Tambak Udang Penyulang 20kV Tambak Udang 3
5-Sep 8:00 5-Sep 16:00 GI LAHAT Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GITET LAHAT Pengukuran Thermovisi MTU Switchyard 275 KV Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI MANNA Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI BUKIT ASAM Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI PAGAR ALAM Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBS
5-Sep 9:00 5-Sep 16:00 GI AIR ANYIR Commissoning PTP SCADA Gl Air Anyir (BAY Trafo TFT-2) BAY Trafo TFT -2 3
5-Sep 9:00 5-Sep 16:00 GI BORANG Pemasangan Backup supply inverter 48 to 220 VAC GI Borang Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI TLKLP HAR 2 TAHUNAN BAY TRAFO 150/20 kV 60 MVA (3) TRAFO 150/20 kV 60 MVA (3) 3
5-Sep 8:00 5-Sep 16:00 GI BGRAN Perbaikan karet tuas mekanik PMT 70 KV TRF 30 MVA 1 BAY TRF 30 MVA 1 3
5-Sep 8:00 5-Sep 16:00 GI PNDPO Inspeksi CBM Level 2 Proteksi Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GNDUS Inspeksi CBM Level 2 proteksi Tanpa Padam 5
5-Sep 8:00 5-Sep 16:00 GI Tanjung Api-api Perbaikan Hotspot Dropper Crossbar Fasa T BAY TD 2 Tanpa Padam 5
5-Sep 8:00 6-Sep 16:00 MRINA - KYUNG THERMOVISI DEADEND CLAMP T.1, T.2, T.16, T.25, T.32, T.43 Tanpa Padam 5
Har 2 Tahunan
5-Sep 9:00 5-Sep 16:00 GI SPTGA Penyulang 20 kV Merapi, Seminung 3
Penyulang 20 kV Merapi, Seminung
5-Sep 18:00 5-Sep 22:00 BRANG Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 TLKLP Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 GNDUS Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 KNTEN Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 TJAPI Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 KOBAR Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 BTUNG Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 SKAYU Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
5-Sep 18:00 5-Sep 22:00 SULIN Thermovisi Seluruh MTU BAY Switchyard dan Kubikel 20 kV GI Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 DPSNA PEMELIHARAAN Pht. 150 KV DENTE TELDAS # 2 Pht. 150 KV DENTE TELDAS # 2 3
6-Sep 8:00 8-Sep 16:00 BKMNG PENARIKAN KABEL CT REF HV & REF LV TD#1 GI BKMNG Tanpa Padam 5
6-Sep 8:00 8-Sep 16:00 DPSNA HAR BATERAI BANK 1 & 2 110 VDC DAN BANK 1 48 VDC PADAM BERGANTIAN 3
6-Sep 8:00 6-Sep 16:00 DPSNA KNOWLEDGE SHARING PROTEKSI Tanpa Padam 5
GI TARAHAN - NEW
6-Sep 8:00 6-Sep 16:00 Pengujian Lokal TWS GI NEW TARAHAN DAN TARAHAN Tanpa Padam 5
TARAHAN
6-Sep 8:00 6-Sep 16:00 GI BUKIT ASAM Pemeliharaan 2 Tahunan BAY Incoming TD#2 150/20 kV 60 MVA TD #2 60 MVA 3
6-Sep 8:00 6-Sep 16:00 GI Sukamerindu Har 2 Tahunan BAY Kapasitor 2x25 MVAR BAY Kapasitor 2x25 MVAR 3
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBS
GI BLAMBANGAN
6-Sep 8:00 6-Sep 12:00 HAR 2 TAHUNAN BUSBAR 20KV TD 1 30 MVA BAY TD #1 30 MVA 3
UMPU
GI BLAMBANGAN
6-Sep 8:00 6-Sep 16:00 Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
UMPU
6-Sep 8:00 6-Sep 16:00 GI BATURAJA Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GI MARTAPURA Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GI MUARA DUA Pengukuran Thermovisi MTU Switchyard 150 KV Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GI/GITET LUMUT BALAI Pengukuran Thermovisi MTU Switchyard 150 KV dan 275 kV Tanpa Padam 5
6-Sep 9:00 6-Sep 16:00 GI AIR ANYIR Commissoning PTP SCADA Gl Air Anyir (BAY Trafo MPP-1) BAY Trafo MPP -1 3
6-Sep 8:00 6-Sep 16:00 GI BMBRU HAR 2 TAHUNAN TRAFO 70/20 kV 30 MVA (1) BAY TRAFO 70/20 kV 30 MVA (1) 3
6-Sep 8:00 6-Sep 16:00 GI PBLIH Inspeksi CBM Level 2 Proteksi Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 KNTEN Inspeksi CBM Level 2 proteksi Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 TLKLP Pemeliharaan Semester Rectifier #1 Tanpa Padam 5
6-Sep 8:00 8-Sep 16:00 SJARO-SKDKN Thermovisi Jaringan T.4-5 , 12-13 , 13-14 , 17-18 (18 TITIK) Tanpa Padam 5
6-Sep 8:00 6-Sep 16:00 GI Bukit Kemuning Penggantian IED Meter PHT Besai-1 SUTT 150 KV BKMNG-BESAI 1 3
6-Sep 9:00 6-Sep 12:00 GI PBLIH Modifikasi MCCB ATS PS GI MCCB 380 V AC (Padam Supply AC 380) 3
6-Sep 9:00 6-Sep 16:00 SULIN Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
6-Sep 22:00 6-Sep 22:00 BRANG Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 TLKLP Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 GNDUS Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 KNTEN Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 TJAPI Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 KOBAR Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 BTUNG Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 SKAYU Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
6-Sep 18:00 6-Sep 22:00 SULIN Thermovisi Seluruh Tiang Pertama Penyulang 20 kV GI Tanpa Padam 5
Mulai Selesai
Lokasi Uraian Pekerjaan/Pemeliharaan Peralatan yang Bebas Tegangan Sifat
Tanggal Pukul Tanggal Pukul
SBS
7-Sep 8:00 7-Sep 12:00 GI SUKARAME PEMELIHARAAN BUSBAR 20 KV TRAFO 1 # 60 MVA PADAM BAY TRAFO 1 1
GI SUTAMI - GI SKRME -
7-Sep 8:00 7-Sep 16:00 PENGUJIAN LOKAL TWS Tanpa Padam 5
GI TELUK BETUNG
7-Sep 8:00 7-Sep 12:00 GI BUKIT ASAM Pemeliharaan 2 Tahunan BUSBAR 20 KV + BBVT TD#1 60 MVA TD#1 60 MVA 3
GI BLAMBANGAN
7-Sep 8:00 7-Sep 12:00 HAR 2 TAHUNAN BUSBAR 20KV TD 2 60 MVA BAY TD #2 60 MVA 3
UMPU
SUTT 150 kV Puncture Test dan Penggantian Insulator Tension (Kaca menjadi
7-Sep 7:30 7-Sep 16:00 BATURAJA - GIS Polymer, Tension Single Konduktor Single Insulator) SUTT 150 kV Tanpa Padam 5
SEMEN 1 Baturaja - GIS Semen 2 T.06 Arah T.05 Fasa Atas
7-Sep 9:00 7-Sep 16:00 GI AIR ANYIR Commissoning PTP SCADA Gl Air Anyir (BAY Trafo MPP 2) BAY Trafo MPP -2 3
7-Sep 9:00 7-Sep 16:00 GI Boombaru Pemeliharaan Radio Telekomunikasi GI Boombaru Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GI SPTGA Inspeksi SLO Trafo 60 MVA 1 BAY Trafo 60 MVA#1 3
7-Sep 8:00 7-Sep 16:00 GI TLKLP HAR 2 TAHUNAN CHARGER & BAT.110 VDC BANK 2 CHARGER & BAT.110 VDC BANK 2 3
7-Sep 8:00 7-Sep 16:00 TJAPI Inspeksi CBM Level 2 proteksi Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 MRINA Inspeksi CBM Proteksi Level 2 Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GI Tanjung Api-api Perbaikan Hotspot Clamp CT Fasa S BAY PHT Muntok 1 Tanpa Padam 5
7-Sep 8:00 7-Sep 16:00 GI Bukit Kemuning HAR SCADA All BAY Tanpa Padam 5
7-Sep 9:00 7-Sep 16:00 BTUNG Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5
7-Sep 9:00 7-Sep 16:00 SKAYU Pengukuran PD Online Kubikel 20 kV GI Tanpa Padam 5