SCEDULLE PEKERJAAN

PEKERJAAN PENYELIDIKAN TANAH ( BORING)


LOKASI : BOGOR JAWA BARAT

No. SOIL STUDY


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

A. PERSIAPAN (PREPARATION)

B. MOB / DEMOB ALAT DAN PERSONIL (MOBILITY)

C. PEKERJAAN LAPANGAN (FIELD WORK)

Bandung, 14 Januari 2023

AS. MUNANDAR
PENAWARAN BIAYA
PEKERJAAN PENYELIDIKAN TANAH ( BORING)
LOKASI : BOGOR JAWA BARAT

HARGA
No. SOIL STUDY UNIT VOLUME BIAYA
SATUAN

A. PERSIAPAN (PREPARATION)
1 Persiapan LS 1 IDR 1.000.000 IDR 1.000.000
SUB TOTAL ( A ) IDR 1.000.000
B. MOB / DEMOB ALAT DAN PERSONIL (MOBILITY)

1 Mob / Demob alat dan personil Bdg - Lokasi PP Ls 1 IDR 8.500.000 IDR 8.500.000
SUB TOTAL ( B ) IDR 8.500.000
C. PEKERJAAN LAPANGAN (FIELD WORK)

1 Bor inti m 90 IDR 500.000 IDR 45.000.000


2 SPT per 2 m Test 45 IDR 150.000 IDR 6.750.000
3 Pengambilan Sample UDS/DS Buah 15 IDR 120.000 IDR 1.800.000
4 Corebox Buah 18 IDR 100.000 IDR 1.800.000
6 Pindah Titik Bor Inti Titik 3 IDR 200.000 IDR 600.000
8 Biaya Keamanan Ls 1 IDR 1.000.000 IDR 1.000.000
9 Basecamp Bln 1 IDR 2.000.000 IDR 2.000.000
SUB TOTAL ( C ) IDR 58.950.000
GRAND TOTAL IDR 68.450.000

PPN (11%) IDR 7.529.500


TERBILANG : Tujuh Puluh Lima Juta Sembilan Ratus Tujuh Puluh Sembilan Ribu Lima Ratus Rupiah Sub Total IDR 75.979.500
Negosiasi IDR

Bandung, 14 Januari 2023

AS. MUNANDAR