PROJECT DEVELOPMENT

DEPARTEMENT CIVIL SITE TOP


PEKERJAAN CIVIL

LAPORAN HARIAN
PEKERJAAN : CIVIL : 1 OF 2
LOKASI : SITE TOP WAKTU PEKERJAAN : Senin,19 Juni 2023
LUAS BANGUNAN : - REPORT NO : 121
KONTRAKTOR : BMR CONTRACT NO :
Pagi Siang Hari Sore
Cuaca
Cerah Hujan (11:55-12:30) Cerah
Work Hours
No Personal Person No Actual
No Equipment Unit No Qty
1 Superintendent Civil 1 1 11 1 Obeng 1 1 Baut
2 Supervisor Civil 0 2 0 2 Tang 1 2 Kayu
3 GL Civil Construction 1 3 11 3 Bor Listrik 1 3 Paku
4 Admin Civil 1 4 11 4 Geraji 4
5 Kepala Tukang 1 5 11 5 Palu 5
6 Welder 1 6 11 6 Meteran 6
7 Tukang 5 7 55 7 7
8 Helper Tukang 0 8 0 8 8
9 9 9 9
10 10 10 10
Jumlah 10 110 3 0

A. DESCRIPTION
- Perakitan Almari Besi
- Pembuatan Tiang Rambu HSE
- Maintenance Listrik Mes 2
- Pembuatan Meja

B. PROBLEM PEKERJAAN
- Kekurangan Material

C. PLANING
- Pemasangan Plapon Mes 2

D. HSE ISSUE

E. ISSUE GENERAL
- TPS Limbah B3 ( Mr No.174,175,177,178 )
- Suport Air Bersih Buat Toilet Office Ex.Bandara ( Mr No.179,180,181,182 )
- Pembuatan Post Cheker ( Mr No.167,168 )
- Pembuatan Toilet Portable area PIT ( Mr No.259,260,261 )
- Worksop Temporari (MR 49 dan 50)
PROJECT DEVELOPMENT
DEPARTEMENT CIVIL SITE TOP
PEKERJAAN CIVIL

LAPORAN HARIAN
PEKERJAAN : CIVIL : 2 OF 2
LOKASI : SITE TOP WAKTU PEKERJAAN Senin,19 Juni 2023
LUAS BANGUNAN : - REPORT NO :121#
:

SITE PHOTOS DOCUMENTATION

1a. 2a.

1b.
2b.

1c.

Diketahui Oleh, Diperiksa Oleh Dibuat Oleh

`
( Sufrizal Ibrahim ) Tri Desis Dwi Tyas Stiawan
Superintendent Civil GL Civil Admin Civil