Anda di halaman 1dari 17

GAMBAR RENCANA

PEKERJAAN

Penataan Area Parkir Kendaraan di Pelabuhan


Penyeberangan Kuala Bubon

SUMBER DANA
APBA TA.2022
11.00 35.00

29.62
PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
3.00 9.90 3.15

3.30 0.70
0.70
4.70
1.20 Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh
0.90
3.00
4.00 8.30
3.20 53.0000

KETERANGAN
7.00
7.00 6.30 6.31
T19

N
6.30
8.40 7.80

3.00 3.00

5.43 11.00
T17 T20
6.20

M N
4.60 4.65

47.60
7.25
53.32

8.02 7.90 1.50


7.50

8.30
11.00
10.50
6.00
4.00 4.00 4.40 16.80

6.60
5.00 5.00
5.00
T15

M 0.70 0.70 A GEDUNG TERMINALA


B KANTOR KESEHATAN / RUMAH DINAS
2.00 2.90

50.00 C AREA PARKIR RODA DUA


T14
9.94
D KIOS/KANTIN
E KORIDOR

Saluran Type. B
C K J F POS TIKET PENUMPANG
L
30.40 36.00
30.40

G MUSHALLA
T13
73.90
52.90
H RUANG GENERATOR
L 34.80
T16
I DRIVER SHELTER DAN POS TIKET KENDARAAN

Saluran Type. B
38.15
62.50
J AREA PARKIR TRUK
K AREA PARKIR RUDA EMPAT KEBERANGKATAN
5.90 5.00

99.70
6.60

4.00 T10 4.00 4.40


T11
T12
L AREA PARKIR RODA EMPAT
6.00
10.50

14.90
M GERBANG DAN POS TIKET KENDARAAN

Saluran Type. A

12
.40
7.15

10.30 10.65
7.15

6.40 23.70
N POS JAGA
T8
6.90
1.90

14.80
O WATER TANK
5.75 25.90

9.10
5.88
Saluran Type. B 0.40
T9
5.45

9.80
16.50
P TALUD
9.70
Q KANTOR PENGELOLA
8.30
3.00
141.20

2.70

A TOILET TOILET

D
- 0.02

DRIVER SHELTER

I
37.70
COUNTER TIKET
UNTUK KENDARAAN
+ 0.01

O
Bak Resevoir

T4

0.50

13.35

G H NAMA PEKERJAAN
T6
T5

5.00
T3
Penataan Areal Parkir Kendaraan
1.40
Saluran Type. B

0.95
15.40

Saluran Type. B O F di Pelabuhan Penyeberangan

Bak Resevoir
F Kuala Bubon
12.25

E
Q
e. A
7.15

Typ
septictank Resapan
ran
Salu LOKASI
1.95

E T1

Pelabuhan Penyeberangan Kuala Bubon


septictank Resapan

B
Resapan
septictank

SUMBER DANA
SITE PLAN EXISTING
APBA TA. 2022

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA
ke
Tre

DIGAMBAR DIRENCANA NO. /LEMBAR


stle
De
rma
ga
PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

11.00 35.00

29.62
KETERANGAN
3.00 9.90
4.70
3.30
3.00
4.00 8.30
3.20 53.0000

T19

N
8.40 7.80

3.00 3.00

5.43 11.00
T17 T20
6.20

47.60

53.32
M 7.25
N
8.02 7.90 1.50
7.50

8.30
11.00
6.00
4.00 4.00 4.40 16.80

6.60
5.00 5.00
T15

M A GEDUNG TERMINALA
B KANTOR KESEHATAN / RUMAH DINAS
2.00 2.90

50.00 C AREA PARKIR RODA DUA


T14
9.94
D KIOS/KANTIN
E KORIDOR

Saluran Type. B
C K J F POS TIKET PENUMPANG
L
30.40 30.40 36.00

G MUSHALLA
T13
73.90
52.90
H RUANG GENERATOR
L 34.80
T16
I DRIVER SHELTER DAN POS TIKET KENDARAAN

Saluran Type. B
38.15
62.50
J AREA PARKIR TRUK
K AREA PARKIR RUDA EMPAT KEBERANGKATAN
5.90 5.00

99.70
6.60

4.00 T10 4.00 4.40


T11
T12
L AREA PARKIR RODA EMPAT
6.00 10.50

14.90
M GERBANG DAN POS TIKET KENDARAAN

Saluran Type. A

12
.40
7.15

10.30 10.65
7.15

23.70
N POS JAGA
T8

25.90
14.80
O WATER TANK
5.75

9.10
5.88
Saluran Type. B
T9
9.80
16.50
P TALUD
9.70
Q KANTOR PENGELOLA
8.30
3.00
141.20

2.70

A TOILET TOILET

D
I
2,5

3
5 COUNTER TIKET

3
UNTUK KENDARAAN
+ 0.01
Bak Resevoir

20,7
3
G H

13,84
3
T6

NAMA PEKERJAAN

3
T5

2,7
Saluran Type. B
O F

3
7

4
1,3 3

3,1
Bak Resevoir
F Penataan Areal Parkir Kendaraan

3.

2,2

3
E di Pelabuhan Penyeberangan

3,7
2

Q
7,3

3
1
0,6
0,3
Kuala Bubon
e. A

3
Typ
septictank Resapan
ran
Salu

3
E

3
T1

1,72
LOKASI

3
septictank Resapan

3
B

3
Pelabuhan Penyeberangan Kuala Bubon

3
Resapan
septictank

3
SITE PLAN PENGEMBANGAN

3
SUMBER DANA

3
APBA TA. 2022

3
KUASA PENGGUNA ANGGARAN

3
BIDANG PELAYARAN

3
DINAS PERHUBUNGAN ACEH

3
ke
MUHAMMAD AL QADRI, S.SiT, MT

2
Tres

NIP. 19790417 200012 1 004


tle
De

GAMBAR SKALA
rma
ga

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

TAMPAK ARAH A
RENCANA PAGAR PADA CAUSEWAY
3

3
1,37

3
3
NAMA PEKERJAAN
2

3 3 3 3 2
3 3 3
3 3 3
3 3 3 3
3
3,1

3 3 3
1,72 3 3 3
4

3 3 3
3 3 3
3 3 3
2,2

Penataan Areal Parkir Kendaraan


7,3

ke Trestle Dermaga di Pelabuhan Penyeberangan


A Kuala Bubon
0,3

3,7
0,6 1

LOKASI

Pelabuhan Penyeberangan Kuala Bubon

SUMBER DANA

DENAH RENCANA PAGAR PADA CAUSEWAY APBA TA. 2022

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

Skor Tiang Pipa Galvanis dia. 3" t. 3mm

Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm Skor Tiang Pipa Galvanis dia. 3" t. 3mm

Pipa Galvanis dia. 3" t. 3mm Pipa Galvanis dia. 3" t. 3mm Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm Pipa Galvanis dia. 3" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm

Pipa Galvanis dia. 2,5" t. 3mm Pipa Galvanis dia. 2,5" t. 3mm Pipa Galvanis dia. 2,5" t. 3mm

Pipa Galvanis dia. 2,5" t. 3mm

0.44

Pipa Galvanis dia. 2" t. 2 mm

1.96

Pipa Galvanis dia. 2,5" t. 3mm

0.34

Pipa Galvanis dia. 3" t. 3mm


Rigit Beton Existing 0.23

Rigit Beton Existing

2 NAMA PEKERJAAN

1 Penataan Areal Parkir Kendaraan


di Pelabuhan Penyeberangan
Kuala Bubon

LOKASI

Pelabuhan Penyeberangan Kuala Bubon

SUMBER DANA
0.29 0.44

APBA TA. 2022

1.96
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

0.34
MUHAMMAD AL QADRI, S.SiT, MT
0.23 NIP. 19790417 200012 1 004

Rigit Beton Existing GAMBAR SKALA

0.87

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

Skor Tiang Pipa Galvanis dia. 3" t. 3mm

Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm

Pipa Galvanis dia. 3" t. 3mm Pipa Galvanis dia. 3" t. 3mm Pipa Galvanis dia. 3" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm Pipa Galvanis dia. 2" t. 2 mm

Pipa Galvanis dia. 2,5" t. 3mm Pipa Galvanis dia. 2,5" t. 3mm Pipa Galvanis dia. 2,5" t. 3mm Pipa Galvanis dia. 2,5" t. 3mm

0.44

Pipa Galvanis dia. 2" t. 2 mm

1.96

Pipa Galvanis dia. 2,5" t. 3mm

0.34

Pipa Galvanis dia. 3" t. 3mm


0.23

Rigit Beton Existing Rigit Beton Existing

2 NAMA PEKERJAAN

Penataan Areal Parkir Kendaraan


di Pelabuhan Penyeberangan
Kuala Bubon

LOKASI

Pelabuhan Penyeberangan Kuala Bubon

0.44

SUMBER DANA

APBA TA. 2022

1.96

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

0.34

0.23

Rigit Beton Existing


MUHAMMAD AL QADRI, S.SiT, MT
NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

0,30

Tiang Kolom Pipa Galvanis dia. 4" t. 3mm


0,10
Tiang Kolom Pipa Galvanis dia. 4" t. 3mm

Baut dia.1"

0,10
Stiffenir Plat 12 mm

Beton Cor Beton Cor 0,11

Besi angker dia.12mm NAMA PEKERJAAN


0,16

Rigit Beton Existing


0,20
Penataan Areal Parkir Kendaraan
0,50 Besi angker dia.12mm di Pelabuhan Penyeberangan
Kuala Bubon

Anchor Chemical Injection


Anchor dia.1"

LOKASI

DETAIL 2
Pelabuhan Penyeberangan Kuala Bubon

0,30

SUMBER DANA

DETAIL 1 APBA TA. 2022

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

NAMA PEKERJAAN

Penataan Areal Parkir Kendaraan


di Pelabuhan Penyeberangan
Kuala Bubon

LOKASI

TAMPAK ARAH D PAGAR PADA Pelabuhan Penyeberangan Kuala Bubon


SISI DARAT PELABUHAN

SUMBER DANA

APBA TA. 2022

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm KETERANGAN

Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm Pipa Galvanis dia. 3" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm
Bingkai Pintu Pagar Pipa Galvanis dia. 3" t. 3mm
Pipa Galvanis dia. 3" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm

Pipa Galvanis dia. 2" t. 2 mm


Pipa Galvanis dia. 2,5" t. 3mm Pipa Galvanis dia. 2,5" t. 3mm

0.50 0.44

Pipa Galvanis dia. 2" t. 2 mm

1.96

2.40

Pipa Galvanis dia. 2,5" t. 3mm

0.44

Pipa Galvanis dia. 3" t. 3mm NAMA PEKERJAAN

Rigit Beton Existing Rigit Beton Existing Penataan Areal Parkir Kendaraan
di Pelabuhan Penyeberangan
0.30
Kuala Bubon

3
1.45 1.45

LOKASI

Pelabuhan Penyeberangan Kuala Bubon

SUMBER DANA

APBA TA. 2022

KUASA PENGGUNA ANGGARAN


3.00
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

Rigit Beton Existing


DIGAMBAR DIRENCANA NO. /LEMBAR
PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN
Skor Tiang Pipa Galvanis dia. 3" t. 3mm

Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm

Pipa Galvanis dia. 3" t. 3mm Pipa Galvanis dia. 3" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm Pipa Galvanis dia. 2" t. 2 mm

Pipa Galvanis dia. 2,5" t. 3mm

0.44

Pipa Galvanis dia. 2,5" t. 3mm

2.90 1.96
Pipa Galvanis dia. 2" t. 2 mm

Pipa Galvanis dia. 2,5" t. 3mm


NAMA PEKERJAAN
0.44

Pipa Galvanis dia. 3" t. 3mm Penataan Areal Parkir Kendaraan


0.10 di Pelabuhan Penyeberangan
0.26
Rigit Beton Existing Kuala Bubon
0.50
Rigit Beton Existing
0.30
3.00

4
0.30 3 LOKASI

Pelabuhan Penyeberangan Kuala Bubon

0.29

SUMBER DANA

APBA TA. 2022

KUASA PENGGUNA ANGGARAN


3.00
BIDANG PELAYARAN
2.50
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

Rigit Beton Existing

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

Tiang Kolom Pipa Galvanis dia. 4" t. 3mm

Beton Cor

Besi angker dia.12mm

0,50 Besi angker dia.12mm

0,30

NAMA PEKERJAAN

Tiang Kolom Pipa Galvanis dia. 4" t. 3mm


0,10 Penataan Areal Parkir Kendaraan
di Pelabuhan Penyeberangan
Baut dia.1" Kuala Bubon
0,10
Stiffenir Plat 12 mm
0,30

LOKASI
Beton Cor 0,11

DETAIL 4
Pelabuhan Penyeberangan Kuala Bubon

0,16
0,20
Rigit Beton Existing

SUMBER DANA

Anchor Chemical Injection APBA TA. 2022


Anchor dia.1"

DETAIL 3 KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

- 0.02

DRIVER SHELTER

B
I

3
5
COUNTER TIKET
UNTUK KENDARAAN

3
+ 0.01

99.70

2
0,7
0.50

D C H

13,84
3

NAMA PEKERJAAN

T6 Penataan Areal Parkir Kendaraan


di Pelabuhan Penyeberangan
3

Kuala Bubon
2,7

LOKASI

Pelabuhan Penyeberangan Kuala Bubon

F
3

7
1,3 3
4
3,1

F SUMBER DANA
3.

2,2

APBA TA. 2022


3,7

KUASA PENGGUNA ANGGARAN


7,3
BIDANG PELAYARAN
1 DINAS PERHUBUNGAN ACEH
0,6
0,3

E MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

Rangka Atap Pipa Galvanis dia. 4" t. 3mm


Atap UPVC
Reng Atap Besi Hollo 50.50.2
Rangka Atap Pipa Galvanis dia. 4" t. 3mm

0,5
5
0,5

NAMA PEKERJAAN

DENAH RANGKA DAN ATAP

2
Penataan Areal Parkir Kendaraan
TEMPAT PARKIR RODA DUA di Pelabuhan Penyeberangan
Kuala Bubon

LOKASI

Pelabuhan Penyeberangan Kuala Bubon

7,3
SUMBER DANA

APBA TA. 2022

0,3
1
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN

0,6
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

3 3 3 3 2,83
F PAGAR BESI

4,1
4
5

1,69
Tiang Kolom Pipa Galvanis dia. 4" t. 3mm
PAGAR BESI PAGAR BESI NAMA PEKERJAAN

4,1
Penataan Areal Parkir Kendaraan

8
di Pelabuhan Penyeberangan
PINTU PORTALPAGAR BESI

Kuala Bubon
F

3
PAGAR BESI

LOKASI

2
Pelabuhan Penyeberangan Kuala Bubon
DENAH TIANG KOLOM DAN PAGAR

1,1
8
TEMPAT PARKIR RODA DUA
PAGAR BESI

SUMBER DANA

APBA TA. 2022

7,3
KUASA PENGGUNA ANGGARAN
BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

0,3
1
MUHAMMAD AL QADRI, S.SiT, MT
NIP. 19790417 200012 1 004

0,6
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

TAMPAK ARAH B
RENCANA TEMPAT PARKIR RODA DUA

NAMA PEKERJAAN

Penataan Areal Parkir Kendaraan


di Pelabuhan Penyeberangan
Kuala Bubon

LOKASI
Atap UPVC
Reng Atap Besi Hollo 50.50.2
Rangka Atap Pipa Galvanis dia. 4" t. 3mm

Listplank UPVC Listplank UPVC Pelabuhan Penyeberangan Kuala Bubon


Rangka Listplank Besi Hollo 40.40.2 Rangka Listplank Besi Hollo 40.40.2
Tiang Kolom Pipa Galvanis dia. 4" t. 3mm Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm Tiang Kolom Pintu Pagar Pipa Galvanis dia. 4" t. 3mm
0.50
Bingkai Pintu Pagar Pipa Galvanis dia. 3" t. 3mm Galvanis dia. 4" t. 3mm
Pipa Galvanis dia. 2,5" t. 3mm
Pipa Galvanis dia. 2" t. 2 mm
Bingkai Pintu Pagar Pipa Galvanis dia. 2,5" t. 3mm
0.30
Pipa Galvanis dia. 2" t. 2 mm

SUMBER DANA
Pipa Galvanis dia. 2,5" t. 2 mm
(Pintu Portal)

Pipa Galvanis dia. 2" t. 2 mm


(Pintu Portal)
APBA TA. 2022
3.10

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
0.21
DINAS PERHUBUNGAN ACEH

TAMPAK ARAH B
RENCANA TEMPAT PARKIR RODA DUA
MUHAMMAD AL QADRI, S.SiT, MT
NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

Listplank UPVC

Tiang Kolom Pipa Galvanis dia. 4" t. 3mm


Pagar Pipa Galvanis dia. 2,5" t. 2 mm

Pipa Galvanis dia. 2" t. 2 mm

NAMA PEKERJAAN

Penataan Areal Parkir Kendaraan


di Pelabuhan Penyeberangan
Kuala Bubon

TAMPAK ARAH C LOKASI

RENCANA TEMPAT PARKIR RODA DUA Pelabuhan Penyeberangan Kuala Bubon

SUMBER DANA

APBA TA. 2022

KUASA PENGGUNA ANGGARAN


BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

MUHAMMAD AL QADRI, S.SiT, MT


NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR


PEMERINTAH ACEH
DINAS PERHUBUNGAN ACEH
Jl. Mayjend. T. Hamzah Bendahara No. 52 Banda Aceh

KETERANGAN

Atap UPVC
Reng Atap Besi Hollo 50.50.2
Rangka Atap Pipa Galvanis dia. 4" t. 3mm

0.50 5.00 0.50

1.00 1.00 1.00

Listplank UPVC
0.30 Rangka Listplank Besi Hollo 40.40.2
Tiang Kolom Pipa Galvanis dia. 4" t. 3mm

2.80

0.10
0.11 0.10 NAMA PEKERJAAN
0.16 Rigit Beton Existing
0.30
Penataan Areal Parkir Kendaraan

5 di Pelabuhan Penyeberangan
Kuala Bubon
TAMPAK POT. F - F 0,30

RENCANA TEMPAT PARKIR RODA DUA


LOKASI

Pelabuhan Penyeberangan Kuala Bubon


Tiang Kolom Pipa Galvanis dia. 4" t. 3mm
0,10

Baut dia.1"

0,10
Stiffenir Plat 12 mm
SUMBER DANA

Beton Cor 0,11


APBA TA. 2022

0,16
0,20 KUASA PENGGUNA ANGGARAN
Rigit Beton Existing BIDANG PELAYARAN
DINAS PERHUBUNGAN ACEH

Anchor Chemical Injection


Anchor dia.1"

MUHAMMAD AL QADRI, S.SiT, MT

DETAIL 5
NIP. 19790417 200012 1 004
GAMBAR SKALA

DIGAMBAR DIRENCANA NO. /LEMBAR