PEKERJAAN PERSIAPAN BANGUNAN : PERSIAPAN BEDENG PEKERJA LBR :

Tanggal : MANDOR : KODIR


SISA PROGRESS KOMULATIF MINGGU LALU MINGGU INI
NO ITEM PEKERJAAN SAT VOLUME HARGA TOTAL S/D SEKARANG S/D SEKARANG TGL : 15 April 2021 TGL : 22 April 2020
VOL Rp VOL Rp VOL Rp VOL Rp
1 Periode 24 Februari 2023
Tanggal 24 Feb 2023 Ls 1 106,717 106,717 - - 1 106,717 - 1 106,717
Tanggal 24 Feb 2023 Ls 1 286,326 286,326 - - 1 286,326 - 1 286,326
Tanggal 24 Feb 2023 Ls 1 282,800 282,800 - - 1 282,800 - 1 282,800
Tanggal 24 Feb 2023 Ls 1 1,068,884 1,068,884 - - 1 1,068,884 - 1 1,068,884
Tanggal 24 Feb 2023 Ls 1 1,027,506 1,027,506 - - 1 1,027,506 - 1 1,027,506
Tanggal 24 Feb 2023 Ls 1 1,599,042 1,599,042 - - 1 1,599,042 - 1 1,599,042
Tanggal 24 Feb 2023 Ls 1 201,950 201,950 - - 1 201,950 - 1 201,950
Tanggal 24 Feb 2023 Ls 1 330,250 330,250 - - 1 330,250 - 1 330,250
Tanggal 24 Feb 2023 Ls 1 142,000 142,000 - - 1 142,000 - 1 142,000
Tanggal 24 Feb 2023 Ls 1 90,000 90,000 - - 1 90,000 - 1 90,000
Tanggal 24 Feb 2023 Ls 1 828,487 828,487 - - 1 828,487 - 1 828,487
2 Periode 2 Maret 2023 - - - - - - 0 -
Tanggal 2 Maret 2023 Ls 1 1,217,736 1,217,736 - - 1 1,217,736 - 1 1,217,736
Tanggal 2 Maret 2023 Ls 1 96,509 96,509 - - 1 96,509 - 1 96,509
Tanggal 2 Maret 2023 Ls 1 882,081 882,081 - - 1 882,081 - 1 882,081
Tanggal 2 Maret 2023 Ls 1 99,380 99,380 - - 1 99,380 - 1 99,380
Tanggal 2 Maret 2023 Ls 1 81,000 81,000 - - 1 81,000 - 1 81,000
Tanggal 2 Maret 2023 Ls 1 1,459,381 1,459,381 - - 1 1,459,381 - 1 1,459,381
3 Periode 08 Maret 2023 - - - - - 0 -
Tanggal 08 Maret 2023 Ls 1 410,375 410,375 - - 1 410,375 - 1 410,375
Tanggal 08 Maret 2023 Ls 1 109,800 109,800 - - 1 109,800 - 1 109,800
Tanggal 08 Maret 2023 Ls 1 220,000 220,000 - - 1 220,000 - 1 220,000
Tanggal 08 Maret 2023 Ls 1 109,000 109,000 - - 1 109,000 - 1 109,000
Tanggal 08 Maret 2023 Ls 1 861,541 861,541 - - 1 861,541 - 1 861,541
Tanggal 08 Maret 2023 Ls 1 893,345 893,345 - - 1 893,345 - 1 893,345
Tanggal 08 Maret 2023 Ls 1 151,000 151,000 - - 1 151,000 - 1 151,000
Tanggal 08 Maret 2023 Ls 1 252,000 252,000 - - 1 252,000 - 1 252,000
Tanggal 08 Maret 2023 Ls 1 631,941 631,941 - - 1 631,941 - 1 631,941
4 Periode 16 Maret 2023
Tanggal 16 Maret 2023 Ls 1 358,455 358,455 - - 1 358,455 - 1 358,455
Tanggal 16 Maret 2023 Ls 1 686,013 686,013 - - 1 686,013 - 1 686,013
Tanggal 16 Maret 2023 Ls 1 565,513 565,513 - - 1 565,513 - 1 565,513
Tanggal 16 Maret 2023 Ls 1 122,906 122,906 - - 1 122,906 - 1 122,906
Tanggal 16 Maret 2023 Ls 1 470,000 470,000 - - 1 470,000 - 1 470,000
Tanggal 16 Maret 2023 Ls 1 153,000 153,000 - - 1 153,000 - 1 153,000
Tanggal 16 Maret 2023 Ls 1 76,500 76,500 - - 1 76,500 - 1 76,500
PEKERJAAN PERSIAPAN BANGUNAN : PERSIAPAN BEDENG PEKERJA LBR :
Tanggal : MANDOR : KODIR
SISA PROGRESS KOMULATIF MINGGU LALU MINGGU INI
NO ITEM PEKERJAAN SAT VOLUME HARGA TOTAL S/D SEKARANG S/D SEKARANG TGL : 15 April 2021 TGL : 22 April 2020
VOL Rp VOL Rp VOL Rp VOL Rp
Tanggal 16 Maret 2023 Ls 1 61,200 61,200 - - 1 61,200 - 1 61,200
5 Periode 23 Maret 2023 - - - - - - 0 -
Tanggal 23 Maret 2023 Ls 1 528,003 528,003 - - 1 528,003 - 1 528,003
Tanggal 23 Maret 2023 Ls 1 331,750 331,750 - - 1 331,750 - 1 331,750
Tanggal 23 Maret 2023 Ls 1 165,000 165,000 - - 1 165,000 - 1 165,000
Tanggal 23 Maret 2023 Ls 1 77,125 77,125 - - 1 77,125 - 1 77,125
Tanggal 23 Maret 2023 Ls 1 1,653,000 1,653,000 - - 1 1,653,000 - 1 1,653,000
Tanggal 23 Maret 2023 Ls 1 106,338 106,338 - - 1 106,338 - 1 106,338
Tanggal 23 Maret 2023 Ls 1 895,700 895,700 - - 1 895,700 - 1 895,700
Tanggal 23 Maret 2023 Ls 1 212,223 212,223 - - 1 212,223 - 1 212,223
Tanggal 23 Maret 2023 Ls 1 312,500 312,500 - - 1 312,500 - 1 312,500
Tanggal 23 Maret 2023 Ls 1 90,000 90,000 - - 1 90,000 - 1 90,000
Tanggal 23 Maret 2023 Ls 1 226,800 226,800 - - 1 226,800 - 1 226,800
- - - - - - -
Total : 20,531,077 - 20,531,077 - 20,531,077
Retensi 5% :
Dibayarkan : 20,531,077 - 20,531,077 - 20,531,077

Disetujui Oleh Diperiksa Oleh Dibuat Oleh Diajukan Oleh

Amin Slamet Supriyo Utomo Wijiyanto Adi Kurniawan Iwan


Project Manager Site Manager Cost Control Quantity Surveyor Pelaksana Mandor
P T
6 1.2 7.2 2 14.4
1.7 1.2 2.04 10 20.4
1.2 1.2 1.44 2 2.88
37.68
Kepada Yth
Bagian Keuangan
PT.Bhineka Ciptabahana Pura
Jakarta

RISALAH PEMBAYARAN OPNAME MANDOR


NOMOR SURAT :

1 Nama proyek : INDOGROSIR - TANGERANG - BANTEN

Nama mandor : IWAN

Surat Perjanjian Kontrak Mandor :

Pekerjaan : RETENSI PEKERJAAN STRUKTUR

Nilai kontrak : Rp. 45,759,000

Nilai Progress Hasil Opname : Rp. 20,531,077

Periode : s/d 2019

Dikurangi Retensi : 20,531,077 x 5% Rp.

Dikurangi Kasbon : Tgl.15 April 2021 Rp.

Dikurangi Kasbon : Rp.

Dikurangi Kasbon :

Dikurangi Kasbon :
TOTAL Rp. 20,531,077

DIBULATKAN Rp. 20,531,000


Risalah ini digunakan untuk membayar sebesar
Terbilang :

Cikarang , 21 Juni 2023


Diperiksa & Disetujui Yang membuat Risalah

Yeremias Raynhard Supriyo Utomo Adi Kurniawan


Project Manager Site Manager Supervisor

Mengetahui & Menyetujui Mengetahui & Setuju dibayar

Ign.Agung Budi Prasetyo .S Iwan


Project Koordinator Subkon/Pemborong
PEKERJAAN PERSIAPAN BANGUNAN : PERSIAPAN DIREKSI KIT LBR :
Tanggal : MANDOR : KODIR
SISA PROGRESS KOMULATIF MINGGU LALU MINGGU INI
NO ITEM PEKERJAAN SAT VOL HARGA TOTAL S/D SEKARANG S/D SEKARANG TGL : 15 April 2021 TGL : 22 April 2020
VOL Rp VOL Rp VOL Rp VOL Rp
A PERSIAPAN Unit 1
1 Kantor ( Office,Safety,Logistik ) & Konsultan (ukr. 6 x 18 )
Termasuk :
Lantai 1
- Pembersihan lahan & perataan tanah m2 96 3,000 288,000 - - 96 288,000 96 288,000 -
- Pasang Bouwplank m' 48 2,000 96,000 - - 48 96,000 - - 48 96,000
- Tanggulan keliling office T.40 m' 17.6 15,000 264,000 - - 18 264,000 11 165,000 7 99,000
- Lantai Multiplex Bawah m2 52.8 15,000 792,000 - - 53 792,000 25 375,000 28 417,000
- Karpet Plastik m2 34.8 2,000 69,600 35 69,600 - - - - -
- Dinding Keliling Bawah Multiplek m2 71.64 15,000 1,074,600 - - 72 1,074,600 45 675,000 27 399,600
- Plafond Ruang Metting m2 34.8 15,000 522,000 35 522,000 - 35 522,000
- Cat Dinding m2 106.4 5,000 532,200 106 532,200 - -
- Rabat Beton Teras Site Mix m2 27 8,000 216,000 - - 27 216,000 - - 27 216,000
- Dudukan Ac Unit 2 50,000 100,000 2 100,000 - -
- Pintu Unit 3 125,000 375,000 3 375,000 - 3 375,000
- Meja Metting Unit 1 250,000 250,000 1 250,000 - 1 250,000
- White Board Unit 1 25,000 25,000 1 25,000 - 1 25,000
- Kursi Panjang Unit 2 75,000 150,000 2 150,000 - 1 75,000
Lantai 2
- Plat Lantai Multiplex Atas m2 96 15,000 1,440,000 82 1,230,000 14 210,000 - - 14 210,000
- Plat Lantai Balkon Multiplex Atas m2 14 15,000 210,000 14 210,000
- Dinding Keliling Atas Grc m2 132 15,000 1,980,000 120 1,800,000 12 180,000 - - 12 180,000
- Karpet Plastik m2 96 2,000 192,000 96 192,000 - - - - -
- Ralling Balkon m' 48 15,000 720,000 48 720,000 - - - - -
- Plafond m2 96 15,000 1,440,000 96 1,440,000 - - - - -
- Cat Plafond m2 96 5,000 480,000 96 480,000 - - - - -
- Cat Dinding m2 132 5,000 660,000 132 660,000 - - - - -
- Jendela unt 3 50,000 150,000 - - 3 150,000 - - 3 150,000
- Pintu unt 3 125,000 375,000 - - 3 375,000 - - 3 375,000
PEKERJAAN PERSIAPAN BANGUNAN : PERSIAPAN DIREKSI KIT LBR :
Tanggal : MANDOR : KODIR
SISA PROGRESS KOMULATIF MINGGU LALU MINGGU INI
NO ITEM PEKERJAAN SAT VOL HARGA TOTAL S/D SEKARANG S/D SEKARANG TGL : 15 April 2021 TGL : 22 April 2020
VOL Rp VOL Rp VOL Rp VOL Rp
- Dudukan AC unit 3 50,000 150,000 1 50,000 2 100,000 - - 2 100,000
- Erection rangka Baja & Atap Unit 1 4,500,000 4,500,000 1 4,500,000 - - - - -
- Meja Kerja Unit 1 250,000 250,000 1 250,000 - - - - -
- White board Unit 2 25,000 50,000 2 50,000 - - - - -
- Kursi Panjang unit 2 75,000 150,000 2 150,000 - - - - -
- Tangga Unit 1 250,000 250,000 1 250,000 - - - - -
2 Toilet & Kamar mandi 2 unit - - - - - - -
- Dinding Multiplek m2 21 15,000 315,000 21 315,000 - - - - -
- Pasangan Bata m2 13.5 18,000 243,000 14 243,000 - - - - -
- Plasteran m2 54 16,000 864,000 54 864,000 - - - - -
- Keramik Dinding m2 13.5 37,500 506,250 14 506,250 - - - - -
- Keramik Lantai m2 4.5 35,000 157,500 5 157,500 - - - - -
- Floor Drain titik 2 15,000 30,000 2 30,000 - - - - -
- Tanggulan & Closet Unit 2 150,000 300,000 2 300,000 - - - - -
- Pipa air bersih 3/4 m' 33 3,500 115,500 33 115,500 - - - - -
- Pipa Air Kotor m' 33 5,000 165,000 33 165,000 - - - - -
- Kran Air unt 4 5,000 20,000 4 20,000 - - - - -
- Septiktank Unit 1 1,500,000 1,500,000 1 750,000 1 750,000 1 750,000 -
Total : 21,967,650 17,472,050 4,495,600 2,253,000 3,489,600
Retensi 5% : (1,098,383) (873,603) (224,780) (112,650) (174,480)
Dibayarkan : 20,869,268 16,598,448 4,270,820 2,140,350 3,315,120

Disetujui Oleh Diperiksa Oleh Dibuat Oleh Diajukan Oleh

Amin Slamet Sujono Wijiyanto Turmudy Kodir


Project Manager Site Manager Cost Control Quantity Surveyor Pelaksana Mandor
PEKERJAAN PERSIAPAN BANGUNAN : PERSIAPAN DIREKSI KIT LBR :
Tanggal : MANDOR : KODIR
SISA PROGRESS KOMULATIF MINGGU LALU MINGGU INI
NO ITEM PEKERJAAN SAT VOL HARGA TOTAL S/D SEKARANG S/D SEKARANG TGL : 15 April 2021 TGL : 22 April 2020
VOL Rp VOL Rp VOL Rp VOL Rp
Kepada Yth
Bagian Keuangan
PT.Bhineka Ciptabahana Pura
Jakarta

RISALAH PEMBAYARAN OPNAME MANDOR


NOMOR SURAT :

1 Nama proyek : INDOGROSIR - TANGERANG - BANTEN

Nama mandor : KODIR

Surat Perjanjian Kontrak Mandor :

Pekerjaan : PEKERJAAN DIREKSI KIT

Nilai kontrak : Rp. 21,052,250

Nilai Progress Hasil Opname : Rp. 3,489,600

Periode : s/d 2019

Dikurangi Retensi : 3,489,600 x 5% Rp. (174,480)

Dikurangi Kasbon : Rp.

Dikurangi Kasbon : Rp.

Dikurangi Kasbon :

Dikurangi Kasbon :
TOTAL Rp. 3,315,120

DIBULATKAN Rp. 3,315,000


Risalah ini digunakan untuk membayar sebesar
Terbilang :

Tangerang ,22 April 2021


Diperiksa & Disetujui Yang membuat Risalah

Amin Slamet Pasujiyono Turmudy


Project Manager Site Manager Supervisor

Mengetahui & Menyetujui Mengetahui & Setuju dibayar

Ign.Agung Budi Prasetyo .S Kodir


Project Koordinator Subkon/Pemborong
21,052,250