Anda di halaman 1dari 6

PEMERINTAH KABUPATEN GARUT

KECAMATAN PANGATIKAN
DESA CITANGTU
Jalan Ciamana No….. Pangatikan Garut – 44183

DESA : CITANGTU NO RAB


KECAMATAN : PANGATIKAN BIDANG : PELAKSANAAN PEMBANGUNAN
KABUPATEN : GARUT KEGIATAN : PENINGKATAN JALAN USAHA TANI + 253 M (R
PROVINSI : JAWA BARAT : PEMBANGUNAN DRAINASE ± 750 M (Rp.969.2
: PEMBANGUNAN TPT JALAN ± 176 M (Rp.218.7
LOKASI KEGIATAN : Kp.Citangtu

NO URAIAN VOLUME SATUAN HARGA SATUAN (Rp) JUMLAH (Rp)

A. PENINGKATAN JALAN USAHA TANI ± 253 M


I BAHAN
1 Sirtu 72 M3 200,000 14,400,000
2 Papan 3/20 4 M3 1,500,000 6,000,000
3 Kaso 5/7 1 M3 1,500,000 1,500,000
4 Paku Campur 48 Kg 20,000 960,000
5 Plastik/Alas Beton 1341 Kg 5,000 6,705,000
6 Semen 1240 Zak 79,000 97,960,000
7 Pasir Beton 131 M3 350,000 45,850,000
8 Split 2/3 144 M3 425,000 61,200,000
9 Tanah urug 106 M3 100,000 10,600,000
10 Ember 4 Buah 25,000 100,000
11 Benang 2 Pack 5,000 10,000
12 Papan Proyek 1 Buah 250,000 250,000
JUMLAH 245,535,000
II ALAT-ALAT
1 Sewa Molen 64 Hari 250,000 16,000,000
JUMLAH II 16,000,000
III UPAH
1 Pekerja 298 HOK 90,000 26,820,000
2 Tukang 45 HOK 100,000 4,500,000
JUMLAH III 31,320,000
IV LAIN-LAIN
1 Honor TPK 1 Ls 300,000 300,000
JUMLAH IV 300,000
JUMLAH BELANJA A I+II+III+IV 293,155,000

Mengetahui Citangtu, 03 Maret 2022


Kepala Desa Citangtu Pelaksana Kegiatan
BARLAH KOKO KOMARUDIN

B. PEMBANGUNAN DRAINASE ± 750 M


I BAHAN
1 Buis Beton D 40 736 M3 135,000 99,360,000
2 Papan 3/20 9 M3 1,500,000 13,500,000
3 Kaso 5/7 2 M3 1,500,000 3,000,000
4 Paku Campur 161 Kg 20,000 3,220,000
5 Kawat 4357 Kg 5,000 21,785,000
6 Semen 4253 Zak 79,000 335,987,000
7 Pasir Beton 439 M3 350,000 153,650,000
8 Split 2/3 468 M3 425,000 198,900,000
9 Tanah Urug 342 M3 100,000 34,200,000
10 Ember 20 Buah 25,000 500,000
11 Benang 5 Pack 5,000 25,000
12 Papan proyek 1 Buah 250,000 250,000
JUMLAH I 864,377,000
II ALAT-ALAT
1 Cangkul 2 Buah 125,000 250,000
2 Sekop 2 Buah 125,000 250,000
3 Artco 2 Buah 650,000 1,300,000
JUMLAH II 1,800,000
III UPAH
1 Pekerja 971 HOK 90,000 87,390,000
2 Tukang 147 HOK 100,000 14,700,000
JUMLAH III 102,090,000
IV LAIN-LAIN
1 Honor TPK 1 Ls 975,000 975,000
JUMLAH IV 975,000
JUMLAH BELANJA B I+II+III+IV 969,242,000

C. PEMBANGUNAN TPT ± 176 M


I BAHAN
1 Batu Belah 216 M3 225,000 48,600,000
2 Pasir Pasang 148 M3 250,000 37,000,000
3 Semen 587 Zak 79,000 46,373,000
4 Pipa Paralon 9 Buah 50,000 450,000
5 Cat Tembok 2 Pell 175,000 350,000
6 Kuas 2 Buah 15,000 30,000
JUMLAH I 132,803,000
II UPAH
1 Pekerja 704 HOK 90,000 63,360,000
2 Tukang 223 HOK 100,000 22,300,000
JUMLAH II 85,660,000
III LAIN-LAIN
1 Honor TPK 1 Ls 300,000 300,000
JUMLAH 300,000
UT

PEMBANGUNAN
JALAN USAHA TANI + 253 M (Rp.293.155.000,-)
N DRAINASE ± 750 M (Rp.969.242.000,-)
N TPT JALAN ± 176 M (Rp.218.763.000,-)
B. PEMBANGUNAN DRAINASE ± 750 M
I BAHAN
1 Buis Beton D 40 736 M3 135,000 99,360,000
2 Papan 3/20 9 M3 1,500,000 13,500,000
3 Kaso 5/7 2 M3 1,500,000 3,000,000
4 Paku Campur 161 Kg 20,000 3,220,000
5 Kawat 4357 Kg 5,000 21,785,000
6 Semen 4253 Zak 79,000 335,987,000
7 Pasir Beton 439 M3 350,000 153,650,000
8 Split 2/3 468 M3 425,000 198,900,000
9 Tanah Urug 342 M3 100,000 34,200,000
10 Ember 20 Buah 25,000 500,000
11 Benang 5 Pack 5,000 25,000
12 Papan proyek 1 Buah 250,000 250,000
JUMLAH I 864,377,000
II ALAT-ALAT
1 Cangkul 2 Buah 125,000 250,000
2 Sekop 2 Buah 125,000 250,000
3 Artco 2 Buah 650,000 1,300,000
JUMLAH II 1,800,000
III UPAH
1 Pekerja 971 HOK 90,000 87,390,000
2 Tukang 147 HOK 100,000 14,700,000
JUMLAH III 102,090,000
IV LAIN-LAIN
1 Honor TPK 1 Ls 975,000 975,000
JUMLAH IV 975,000
JUMLAH BELANJA B I+II+III+IV 969,242,000

Mengetahui Citangtu, 03 Maret 2022


Kepala Desa Citangtu Pelaksana Kegiatan

BARLAH KOKO KOMARUDIN


C. PEMBANGUNAN TPT ± 176 M
I BAHAN
1 Batu Belah 216 M3 225,000 48,600,000
2 Pasir Pasang 148 M3 250,000 37,000,000
3 Semen 587 Zak 79,000 46,373,000
4 Pipa Paralon 9 Buah 50,000 450,000
5 Cat Tembok 2 Pell 175,000 350,000
6 Kuas 2 Buah 15,000 30,000
JUMLAH I 132,803,000
II UPAH
1 Pekerja 704 HOK 90,000 63,360,000
2 Tukang 223 HOK 100,000 22,300,000
JUMLAH II 85,660,000
III LAIN-LAIN
1 Honor TPK 1 Ls 300,000 300,000
JUMLAH 300,000