Monitoring Approval Shop Drawing PLTS
Monitoring Approval Shop Drawing PLTS
A. MLCP DOMESTIK
1 Layout Penempatan PV Module, Kabel Tray & Inverter
2 PV Array PLTS Gedung Parkir Domestik
3 Detail PV Mounting Atap Dak Beton Gedung Parkir Domestik
4 Single Line Diagram PLTS Gedung Parkir Domestik
5 Single Line Diagram Panel Proteksi
6 Single Line Diagram LVMDP Perubahan
B. MLCP INTERNASIONAL
1 Layout Penempatan PV Module, Kabel Tray & Inverter
2 Drawing Base Frame PV Mounting
3 PV Array PLTS Gedung Parkir Internasional
4 Detail PV Mounting Atap Dak Beton Gedung Parkir Internasional
5 Single Line Diagram PLTS Gedung Parkir Internasional
6 Single Line Diagram Panel Proteksi
7 Single Line Diagram LVMDP Perubahan
C. TOLL GATE
- TIMUR (PLTS 2,7 kWp)
1 Layout Penempatan PV Module, Inverter & Panel Proteksi
2 PV Mounting Toll Gate Timur
3 Single Line Diagram PLTS Toll Gate
4 Single Line Diagram Panel Proteksi
5 Single Line Diagram Panel Perubahan
- BARAT
1 Layout Penempatan PV Module, Inverter & Panel Proteksi
2 PV Mounting Toll Gate Barat
3 Single Line Diagram PLTS Toll Gate
4 Single Line Diagram Panel Proteksi
5 Single Line Diagram Panel Perubahan
SHOP DRAWING
NGKIT LISTRIK TENAGA SURYA (PLTS) 155 KWP
L I GUSTI NGURAH RAI - BALI
√
√