MONITORING APROVAL SHOP DRAWING

PEKERJAAN PENGADAAN DAN PEMASANGAN PEMBANGKIT LISTRIK TENAG


DI BANDAR UDARA INTERNASIONAL I GUSTI NGURAH RA

NO LIST GAMBAR NOMOR GAMBAR REVISI

1 Layout / Grid Map Pemasangan PLTS 155 KWP

A. MLCP DOMESTIK
1 Layout Penempatan PV Module, Kabel Tray & Inverter
2 PV Array PLTS Gedung Parkir Domestik
3 Detail PV Mounting Atap Dak Beton Gedung Parkir Domestik
4 Single Line Diagram PLTS Gedung Parkir Domestik
5 Single Line Diagram Panel Proteksi
6 Single Line Diagram LVMDP Perubahan

B. MLCP INTERNASIONAL
1 Layout Penempatan PV Module, Kabel Tray & Inverter
2 Drawing Base Frame PV Mounting
3 PV Array PLTS Gedung Parkir Internasional
4 Detail PV Mounting Atap Dak Beton Gedung Parkir Internasional
5 Single Line Diagram PLTS Gedung Parkir Internasional
6 Single Line Diagram Panel Proteksi
7 Single Line Diagram LVMDP Perubahan
C. TOLL GATE
- TIMUR (PLTS 2,7 kWp)
1 Layout Penempatan PV Module, Inverter & Panel Proteksi
2 PV Mounting Toll Gate Timur
3 Single Line Diagram PLTS Toll Gate
4 Single Line Diagram Panel Proteksi
5 Single Line Diagram Panel Perubahan
- BARAT
1 Layout Penempatan PV Module, Inverter & Panel Proteksi
2 PV Mounting Toll Gate Barat
3 Single Line Diagram PLTS Toll Gate
4 Single Line Diagram Panel Proteksi
5 Single Line Diagram Panel Perubahan