Rab Interior Klinik
Rab Interior Klinik
HARGA SATUAN
No URAIAN PEKERJAAN VOLUME SAT ANALISA JUMLAH (Rp)
Upah Material
1 2 3 4 5 6 7 8
B PEKERJAAN TANAH
I PEKERJAAN TANAH
1 Galian Sloof Uk. 15x20 cm
a Galian Tanah 0.77 m³ A.2.3.1.1 87,175.00 67,447.30
b Mengurug Kembali Tanah Galian 0.26 m³ A.1.1.T.14a 45,650.00 11,773.14
C PEKERJAAN STRUKTUR
II PEKERJAAN SLOOF
1 Sloof Beton Bertulang Uk. 15x20 cm
a Bekisting 14.18 m² A.4.1.1.21 99,156.20 46,456.67 2,065,445.71
b Pembesian Ulir 4D10 86.19 kg A.4.1.1.17 1,961.30 14,387.94 1,409,206.94
d Pembesian Polos Ø8-100 mm 54.52 kg A.4.1.1.17a 1,961.30 12,533.07 790,195.79
c Cor Beton K300 0.77 m³ A.4.1.1.10 240,883.50 908,420.34 889,216.38
II PEKERJAAN PINTU
1 Pintu Geser 1.00 Ls Dihitung Survey
Sub Total II -
IV PEKERJAAN PLAFOND
1 Rangka Plafon Furing 5.60 m² PLL. SUPL 6.1 35,000.00 48,522.18 467,724.20
2 Plafond Gypsum 5.60 m² A.4.5.1.7 19,910.00 43,065.00 352,660.00
V PEKERJAAN PENGECATAN
1 Pengecatan Dinding 35.45 m² A.4.7.1.10 12,809.50 34,179.64 1,665,952.97
2 Pengecatan Plafond 5.60 m² A.4.7.1.10 12,809.50 34,179.64 263,139.18
VI PEKERJAAN SANITARY
1 Wastafel TOTO 1.00 unit A.5.1.1.5 375,320.00 2,411,956.25 2,787,276.25
2 Kaca Cermin t= 5mm 1.21 m² A.4.6.2.20 35,168.10 237,600.00 330,049.40
D PEKERJAAN MEP
I PEKERJAAN ELEKTRIKAL
1 Kabel Saklar 10.00 m' Dihitung 5,250.00 17,500.00 227,500.00
2 Saklar Triple 2.00 bh Dihitung 95,000.00 190,000.00
3 Stop Kontak 2.00 bh 75,000.00 150,000.00
4 LED Tube 1200 mm 18 W 1.00 bh Dihitung 295,000.00 295,000.00
5 Lampu DL 2.00 bh Dihitung 50,000.00 100,000.00
II PEKERJAAN PLUMBING
1 Pipa
Sub Total II
E PEKERJAAN INTERIOR
1 Kursi Putar 1.00 Ls Dihitung 1,100,000.00 1,100,000.00
2 Kursi Stool Bulat 2.00 unit Dihitung 200,000.00 400,000.00
3 Meja Kerja 1.00 Ls Dihitung 2,000,000.00 2,000,000.00
4 Lemari Rak Susun 1.00 Ls Dihitung Survey
5 Pembuatan Neon Signage 1.00 Ls Dihitung 300,000.00 1,700,000.00 2,000,000.00
6 Lampu Neon Kuning 11.80 m' Dihitung 7,500.00 25,000.00 383,500.00