RENCANA ANGGARAN BIAYA STRUKTUR

HARGA SATUAN
No URAIAN PEKERJAAN VOLUME SAT ANALISA JUMLAH (Rp)
Upah Material
1 2 3 4 5 6 7 8

A PEKERJAAN PEMBONGKARAN GEDUNG LAMA


1 Pekerjaan Pembongkaran + Jasa Angkut 1.00 Ls Taksir 1,500,000.00 1,500,000.00

Jumlah Pekerjaan Pembongkaran 1,500,000.00

B PEKERJAAN TANAH
I PEKERJAAN TANAH
1 Galian Sloof Uk. 15x20 cm
a Galian Tanah 0.77 m³ A.2.3.1.1 87,175.00 67,447.30
b Mengurug Kembali Tanah Galian 0.26 m³ A.1.1.T.14a 45,650.00 11,773.14

Sub Total I 79,220.43


Jumlah Pekerjaan Tanah 79,220.43

C PEKERJAAN STRUKTUR
II PEKERJAAN SLOOF
1 Sloof Beton Bertulang Uk. 15x20 cm
a Bekisting 14.18 m² A.4.1.1.21 99,156.20 46,456.67 2,065,445.71
b Pembesian Ulir 4D10 86.19 kg A.4.1.1.17 1,961.30 14,387.94 1,409,206.94
d Pembesian Polos Ø8-100 mm 54.52 kg A.4.1.1.17a 1,961.30 12,533.07 790,195.79
c Cor Beton K300 0.77 m³ A.4.1.1.10 240,883.50 908,420.34 889,216.38

Sub Total IV 5,154,064.82

III PEKERJAAN KOLOM


1 Kolom Tipe-KP Uk. 15x15 cm
a Bekisting 18.63 m² A.4.1.1.22 131,406.00 96,348.33 4,243,063.23
b Pembesian Ulir 4D10 85.41 kg A.4.1.1.17 1,961.30 14,387.94 1,396,311.71
c Pembesian Polos Ø8-100 mm 53.67 kg A.4.1.1.17a 1,961.30 12,533.07 777,848.98
d Cor Beton K300 0.70 m³ A.4.1.1.10 240,883.50 908,420.34 802,932.39

Sub Total V 7,220,156.32

IV PEKERJAAN RING BALOK


1 Balok Beton Bertulang Uk. 15x20 cm
a Bekisting 14.18 m² A.4.1.1.23 131,406.00 99,208.33 3,271,149.01
b Pembesian Ulir 4D10 63.91 kg A.4.1.1.17 1,961.30 14,387.94 1,044,916.67
c Pembesian Polos Ø8-100 mm 55.02 kg A.4.1.1.17a 1,961.30 12,533.07 797,512.42
d Cor Beton K300 0.77 m³ A.4.1.1.10 240,883.50 908,420.34 889,216.38

Sub Total VI 6,002,794.48

V PEKERJAAN PLAT BETON


1 Cor Beton K300 2.94 m³ A.4.1.1.10 240,883.50 908,420.34 3,376,654.67

Sub Total VII 3,376,654.67

VI PEKERJAAN TANGGA BETON


1 Bekesting 6.15 m2 A.4.1.1.24 125,852.10 207,882.50 2,051,052.76
2 Pembesian Polos 10mm 132.40 kg A.4.1.1.17a 1,961.30 12,533.07 1,919,066.66
3 Cor Beton K300 1.30 m3 A.4.1.1.10 240,883.50 908,420.34 1,496,393.59

Sub Total VI 5,466,513.01

Jumlah Pekerjaan Struktur 27,220,183.29


D PEKERJAAN ARSITEKTUR
I PEKERJAAN DINDING
1 Pemasangan Dinding 1/2 Bata Camp. 1PC : 4 PP 17.73 m² A.4.4.1.9 51,755.00 65,388.13 2,076,596.18
2 Plester 1PC : 4PP 35.45 m² A.4.4.2.4 57,205.50 11,715.00 2,443,507.41
3 Acian 35.45 m² A.4.4.2.27 38,137.00 4,468.75 1,510,544.26

Sub Total I 6,030,647.84

II PEKERJAAN PINTU
1 Pintu Geser 1.00 Ls Dihitung Survey

Sub Total II -

III PEKERJAAN PENUTUP LANTAI & DINDING


1 Acian Lantai 29.38 m² A.4.4.2.27 38,137.00 4,468.75 1,251,756.94

Sub Total III 1,251,756.94

IV PEKERJAAN PLAFOND
1 Rangka Plafon Furing 5.60 m² PLL. SUPL 6.1 35,000.00 48,522.18 467,724.20
2 Plafond Gypsum 5.60 m² A.4.5.1.7 19,910.00 43,065.00 352,660.00

Sub Total IV 820,384.20

V PEKERJAAN PENGECATAN
1 Pengecatan Dinding 35.45 m² A.4.7.1.10 12,809.50 34,179.64 1,665,952.97
2 Pengecatan Plafond 5.60 m² A.4.7.1.10 12,809.50 34,179.64 263,139.18

Sub Total V 1,929,092.15

VI PEKERJAAN SANITARY
1 Wastafel TOTO 1.00 unit A.5.1.1.5 375,320.00 2,411,956.25 2,787,276.25
2 Kaca Cermin t= 5mm 1.21 m² A.4.6.2.20 35,168.10 237,600.00 330,049.40

Sub Total VI 3,117,325.65

Jumlah Pekerjaan Arsitektur 13,149,206.78

D PEKERJAAN MEP
I PEKERJAAN ELEKTRIKAL
1 Kabel Saklar 10.00 m' Dihitung 5,250.00 17,500.00 227,500.00
2 Saklar Triple 2.00 bh Dihitung 95,000.00 190,000.00
3 Stop Kontak 2.00 bh 75,000.00 150,000.00
4 LED Tube 1200 mm 18 W 1.00 bh Dihitung 295,000.00 295,000.00
5 Lampu DL 2.00 bh Dihitung 50,000.00 100,000.00

Sub Total I 962,500.00

II PEKERJAAN PLUMBING
1 Pipa

Sub Total II

Jumlah Pekerjaan MEP 962,500.00

E PEKERJAAN INTERIOR
1 Kursi Putar 1.00 Ls Dihitung 1,100,000.00 1,100,000.00
2 Kursi Stool Bulat 2.00 unit Dihitung 200,000.00 400,000.00
3 Meja Kerja 1.00 Ls Dihitung 2,000,000.00 2,000,000.00
4 Lemari Rak Susun 1.00 Ls Dihitung Survey
5 Pembuatan Neon Signage 1.00 Ls Dihitung 300,000.00 1,700,000.00 2,000,000.00
6 Lampu Neon Kuning 11.80 m' Dihitung 7,500.00 25,000.00 383,500.00

Jumlah Pekerjaan Interior 5,883,500.00

JUMLAH PEKERJAAN INTERIOR KLINIK 48,794,610.51