Anda di halaman 1dari 1

REKAPITULASI

BACK UP DATA VOLUME


PROGRAM : PENGELOLAAN PENDIDIKAN
PEKERJAAN : REHAB TOTAL SDN 026 PENAJAM
LOKASI : SDN 026 PENAJAM
TAHUN ANGGARAN : 2023

NO URAIAN PEKERJAAN SAT VOL REALISASI VOL RENCANA SISA VOLUME


1 2 3 4
I PEKERJAAN PERSIAPAN
1 Pasang papan nama proyek LS 1.000 1.000
2 Memasang bowplank M1 161.000 161.000
3 Pasang pagar pengaman dari seng setinggi 2m M1 48.180 168.000 -119.820
4 Pembongkaran dan pembersihan lokasi M2 417.450 647.450 -230.000

II PEKERJAAN BETON (LANTAI 1)


1 -Pile Cap 1 (PC1)
Beton fc 8,3 Mpa (K100) lantai kerja M3 13.338 13.851 -0.513
Beton fc 21,7 Mpa + Pompa Beton M3 80.028 83.106 -3.078
2 -Pile Cap 2 (PC2)
3 Beton fc 8,3 Mpa (K100) lantai kerja M3 0.288 0.288
4 Beton fc 21,7 Mpa + Pompa Beton M3 1.728 1.728
5 Kolom Pedestal (40x40) M3 7.800 8.424 -0.624
6 Kolom Pedestal (40X60) M3 0.624 0.624
7 Sloop (40 X 80) M3 34.880 34.880
8 Sloop (25 X 80) M3 52.590 59.820 -7.230
9 Sloop (25 X 60) M3 1.200 1.695 -0.495
10 Sloop (15 X 20) M3 1.395 1.929 -0.534
11 Sloop (15 X 60) M3 6.651
12 Cor Lantai 1 ( tebal 10 cm) M3 48.910 97.390 -48.480
13 Retening Wall M3 52.920 88.200 -35.280
14 Kolom (40 X 40) M3 50.560 50.560
15 Kolom (15 X 15) M3 1.080 -1.080
16 Kolom (10 X 10) M3 1.280 -1.280
17 Kolom (40 X 60) M3 3.840 -3.840
18 Balok Latai (10 X 10) M3 1.137 -1.137
19 Balok Tandon (20 x 30) M3 1.485 -1.485
20 Plat Tandon (Tebal 12) M3 3.593 -3.593
21 Balok (30 x 70) M3 3.593 -3.593
22 Balok (25 x 50) M3
23 Balok 20 x 35) M3
24 Balok (15 x 60) M3
25 Balok (15 x 20) M3 2.024 -2.024
26 Balok (15 x 30) M3
27 Tangga M3 12.402 -12.402
28 Kanopi L1 dan L2 M3 6.091 -6.091
29 Box Culvert M3 19.110 -19.110
30 Cor Parkiran dan Lapangan Upacara M3 108.020 -108.020

III PEKERJAAN BETON (LANTAI 2)


1 Plat Lantai (Tebal 12 ) M3 123.165 -123.165
2 Kolom (30 x 30) M3 25.492 -25.492
3 Kolom (15 X 15) M3 1.048 -1.048
4 Kolom (10 x 10) M3 0.466 -0.466
5 Kolom (40 x 60) M3 1.920 -1.920
6 Balok Latei (10 x 10) M3 1.137 -1.137
7 Balok Tandon (20 x 30) M3 1.485 -1.485
8 Plat Tandon (Tebal 12) M3 3.593 -3.593
9 Ring Balk (20 x 20) M3 23.760 -23.760

JUMLAH TOTAL 346.261 794.865 43.56%