REKAPITULASI
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
Total Harga
No. Uraian Pekerjaan HOOK
7x12+ 6x10+
I PEKERJAAN PERSIAPAN - -
II PEKERJAAN TANAH & PONDASI - -
III PEKERJAAN STRUKTUR - -
IV PEKERJAAN KAP / KUDA - KUDA + ATAP 9,568,260 7,138,385
V PEKERJAAN PASANGAN DAN PLESTERAN - -
VI PEKERJAAN PINTU DAN JENDELA 57,629,074 47,709,513
VII PEKERJAAN PLAFOND - -
VIII PEKERJAAN PENGECATAN - -
IX PEKERJAAN FINISHING LANTAI DAN DINDING - -
X PEKERJAAN LISTRIK - -
XI PEKERJAAN SANITARY & PLUMBING - -
XII PEKERJAAN LAIN-LAIN - -
XIII PEKERJAAN CANOPY - -
Note :
• Kontrak Lumpsum Fixed Price
• Harga sudah termasuk Jasa & PPh
• Harga sudah termasuk PPN
PARAMOUNT INTERPRISE INTERNATIONAL
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
I PEKERJAAN PERSIAPAN.
1 Pekerjaan pembersihan m2 84.00 60.00 - -
2 Gudang bahan ls 1.00 1.00 - -
3 Air kerja/Listrik kerja ls 1.00 1.00 - -
4 As built drawing ls 1.00 1.00 - -
5 Keamanan Proyek ls 1.00 1.00 - -
6 Pagar Proyek sementara, spandek tinggi 2,4 M Spandek finish cat Biru m' 22.00 19.00 - -
7 Surveyor beserta alat ls 1.00 1.00 include include include
========= =========
Sub.Total I - -
Page 2 of 7
PARAMOUNT INTERPRISE INTERNATIONAL
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
A Type 7x12+
Tampak depan - -
Lantai Dasar
1 Profilan 150 mm
• Samping kanan, kiri dan atas PJ1 m' 6.50 - -
• Samping kanan, kiri dan atas J2 m' 6.40 - -
• Samping kanan, kiri dan atas J1 m' 6.70 - -
2 Penebalan bata ringan, t = 20 cm di atas canopy Elv. + 3,00 m2 2.06 - -
3 Penebalan bata ringan, t = 10 cm di atas canopy Elv. + 3,00 m2 1.23 - -
4 Profilan 465 mm
• Batas lantai dasar dan lantai atas (Elv. +3,40) m' 9.39 - -
Lantai Atas
1 Profilan 150 mm
• Samping kanan, kiri dan atas J3 m' 6.90 - -
2 Penebalan bata ringan, t = 10 cm (Di atas canopy Elv. +6,60) m2 2.10 - -
3 Profilan 250mm kotak tinggi 2.60 m + Topping & Kaki bh 2.00 - -
Tampak samping - -
Lantai Dasar
1 Profilan 150 mm
• Samping kanan, kiri dan atas J2 m' 12.80 - -
• Samping kanan, kiri dan atas J3 m' 6.90 - -
• Samping kanan, kiri dan atas P2 m' 6.40 - -
2 Penebalan bata ringan, t = 30 cm di atas canopy Elv. + 3,00 m2 2.71 - -
3 Penebalan bata ringan, t = 10 cm di atas canopy Elv. + 3,00 m2 0.88 - -
4 Profilan 465 mm
• Batas lantai dasar dan lantai atas (Elv. +3,40) m' 10.23 - -
Lantai Atas
1 Penebalan bata ringan (As 10/B-G) m2 17.70 - -
2 Penebalan bata ringan, t = 10 cm (Di atas canopy Elv. +6,45) m2 3.00 - -
3 Profilan 150 mm
• Samping kanan, kiri dan atas J3 m' 6.90 - -
• Samping kanan, kiri dan atas PJ3 m' 6.90 - -
4 Railling Balkon, Tempered Glass t = 12 mm, m' 8.90 - -
+ bracket supported dan hand railing pipa dia. 2" finish cat
5 Railling tangga besi hollow 20x20x1,5mm, tiang hollow 40x40x2mm m' 6.00 - -
+ dinabolt dan hand railing kayu kamper 50/70 mm finish cat
Page 3 of 7
PARAMOUNT INTERPRISE INTERNATIONAL
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
Lantai Atas
1 Penebalan bata ringan, t = 15 cm (As B) m2 8.40 -
2 Penebalan bata ringan, t = 10 cm (Di atas canopy Elv. +6,45) m2 1.76 -
3 Profilan 250mm kotak tinggi 2.60 m + Topping & Kaki bh 2.00 -
4 Profilan 150 mm
• Samping kanan, kiri dan atas J2 m' 6.30 -
Tampak samping
Lantai Dasar
1 Profilan 150 mm
• Samping kanan, kiri dan atas J1 m' 6.90 -
• Samping kanan, kiri dan atas P2 m' 6.60 -
2 Penebalan bata ringan, t = 30 cm di atas canopy Elv. + 3,00 m2 2.49 -
3 Penebalan bata ringan, t = 20 cm di atas canopy Elv. + 3,00 m2 0.70 -
4 Profilan 400 mm
• Batas lantai dasar dan lantai atas (Elv. +3,40) m' 9.13 -
Lantai Atas
1 Penebalan bata ringan (As 10/B-E) m2 8.25 -
2 Penebalan bata ringan, t = 10 cm (Di atas canopy Elv. +6,45) m2 1.76 -
3 Profilan 150 mm
• Samping kanan, kiri dan atas J3 m' 5.93 -
• Samping kanan, kiri dan atas P2 m' 6.60 -
4 Railling Balkon, Tempered Glass t = 12 mm, m' 8.90 -
+ bracket supported dan hand railing pipa dia. 2" finish cat
5 Railling tangga besi hollow 20x20x1,5mm, tiang hollow 40x40x2mm m' 6.00 -
+ dinabolt dan hand railing kayu kamper 50/70 mm finish cat
========= =========
Sub.Total V - -
VI PEKERJAAN PINTU DAN JENDELA , (uk.& spek sesuai gbr, incld finishing)
A Type 7x12+
Alumunium by kontraktor
Lantai 1
1 Kusen P1, uk.1.0x2.4 M Ex. YKK Fility unit 1.00 677,556 677,556 -
2 Kusen dan pintu P2, uk.0.9x2.4 M Ex. YKK Fility unit 1.00 3,569,170 3,569,170 -
3 Kusen P3, uk.0.9x2.4 M Ex. YKK Fility unit 1.00 665,874 665,874 -
4 Kusen P4, uk.0.75x2.4 M Ex. YKK Fility unit 1.00 648,351 648,351 -
5 Kusen, pintu dan jendela PJ1, uk. 0.9x2.4 M + 0.5x1.35 M Ex. YKK Fility unit 1.00 4,561,744 4,561,744 -
6 Kusen dan jendela J1, uk. 1.2x2.3 M Ex. YKK Fility unit 1.00 3,101,063 3,101,063 -
7 Kusen dan jendela J2, uk. 0.7x2.3 M Ex. YKK Fility unit 3.00 2,060,190 6,180,570 -
8 Kusen dan jendela J3, uk. 1.35x2.3 M Ex. YKK Fility unit 1.00 3,253,958 3,253,958 -
9 Bouvenlight BV1, uk. 0.5x0.6 M Ex. YKK Fility unit 1.00 677,292 677,292 -
Lantai 2
1 Kusen P3/P3', uk.0.9x2.4 M Ex. YKK Fility unit 3.00 665,874 1,997,622 -
2 Kusen P4, uk.0.75x2.4 M Ex. YKK Fility unit 2.00 648,351 1,296,703 -
3 Kusen, pintu dan jendela PJ2, uk. 0.9x2.4 M + 0.5x2.3 M+ 0.5x2.3 M Ex. YKK Fility unit 1.00 4,792,546 4,792,546 -
4 Kusen, pintu dan jendela PJ3, uk. 0.9x2.4 M + 0.5x2.3 M Ex. YKK Fility unit 1.00 4,180,858 4,180,858 -
5 Kusen dan jendela J3, uk. 1.35x2.3 M Ex. YKK Fility unit 2.00 3,253,958 6,507,917 -
6 Kusen dan jendela J4, uk. 0.6x1.7 M Ex. YKK Fility unit 1.00 737,986 737,986 -
7 Bouvenlight BV2, uk. 0.5x0.7 M Ex. YKK Fility unit 1.00 735,064 735,064 -
B Type 6x10+
Alumunium by kontraktor
Lantai 1
1 Kusen P1, uk.1.0x2.4 M Ex. YKK Fility unit 1.00 677,556 677,556
2 Kusen dan pintu P2, uk.0.9x2.4 M Ex. YKK Fility unit 1.00 3,569,170 3,569,170
3 Kusen dan pintu P3, uk.0.8x2.4 M Ex. YKK Fility unit 1.00 3,481,456 3,481,456
4 Kusen P4, uk.0.9x2.4 M Ex. YKK Fility unit 1.00 665,874 665,874
5 Kusen P5, uk.0.75x2.4 M Ex. YKK Fility unit 1.00 648,351 - 648,351
6 Kusen dan jendela J1, uk. 1.2x2.3 M Ex. YKK Fility unit 2.00 3,101,063 6,202,126
7 Kusen dan jendela J2, uk. 0.6x2.3 M Ex. YKK Fility unit 1.00 1,990,164 1,990,164
Lantai 2
Page 4 of 7
PARAMOUNT INTERPRISE INTERNATIONAL
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
========= =========
Sub.Total VI 57,629,074 47,709,513
X PEKERJAAN LISTRIK.
1 Inst.penerangan (NYM 2x2.5 mm)+conduit Fitting Downlight 18W Ex. Eterna titik 18.00 14.00 - -
2 Inst.penerangan (NYM 2x2.5 mm)+conduit Fitting Outbow 18W Ex. Eterna titik 1.00 1.00 - -
3 Inst.penerangan (NYM 2x2.5 mm)+conduit Fitting Baret 18W Ex. Eterna titik 5.00 5.00 - -
4 Inst.penerangan (NYM 2x2.5 mm)+conduit Lampu taman 18W Ex. Eterna titik 1.00 2.00 - -
5 Inst.stop kontak dinding+pompa (NYM 3x2.5 mm) Ex. Eterna titik 17.00 13.00 - -
6 Instalasi stop kontak WH+AC (NYM 3x2.5 mm) Ex. Eterna titik 7.00 6.00 - -
7 Instalasi exhaust fan+conduit Ex. Eterna titik 1.00 1.00 - -
8 Saklar tunggal Ex. Schneider C Vivace bh 7.00 9.00 - -
9 Saklar seri Ex. Schneider C Vivace bh 7.00 4.00 - -
10 Saklar hotel Ex. Schneider C Vivace bh 1.00 2.00 - -
11 Outlet stop kontak Ex. Schneider C Vivace bh 17.00 13.00 - -
12 Outlet stop kontak AC + water heater Ex. Schneider C Vivace bh 7.00 6.00 - -
13 Panel listrik (Hager isi 10 group, MCB, Lt.1) Ex. Hager bh 1.00 1.00 - -
Page 5 of 7
PARAMOUNT INTERPRISE INTERNATIONAL
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
B Pekerjaan sanitary
Lantai Dasar
KM/WC Tamu :
1 Closed duduk Ex. Toto CW 421 J / SW 420 JP bh 1.00 1.00 - -
2 Jet washer / shower spray Ex. Toto TX 403 SB bh 1.00 1.00 - -
3 Shower set Ex. Toto TX 433 SD bh 1.00 1.00 - -
4 Wastafel termasuk kran & accessories Ex. Toto LW 240 CJ bh 1.00 1.00 - -
5 Floor drain dia 3" Ex. Toto TX 1 BN bh 1.00 1.00 - -
6 Kaca cermin uk.60x90 cm bh 1.00 1.00 - -
Dapur : -
1 Kitchent sink stainless steel 1 lubang Ex. Royal, SB 57 bh 1.00 1.00 - -
2 Kran sink Ex. Toto T 30 AR13V7N bh 1.00 1.00 - -
Taman Samping : -
1 Kran dinding taman Ex. Toto T 26-13 bh 1.00 1.00 - -
R. Jemur : -
1 Kran dinding Ex. Toto T 26-13 bh 1.00 - - -
2 Floor drain dia 3" Ex. Toto TX 1 BN bh 1.00 - - -
Carport : -
1 Kran dinding Ex. Toto T 26-13 bh 1.00 1.00 - -
-
Lantai Atas -
KM/WC KT. Utama : -
1 Closed duduk Ex. Toto CW 421 J / SW 420 JP bh 1.00 1.00 - -
2 Jet washer / shower spray Ex. Toto TX 403 SB bh 1.00 1.00 - -
3 Shower set Ex. Toto TX 433 SD bh 1.00 1.00 - -
4 Wastafel termasuk kran & accessories Ex. Toto LW 240 CJ bh 1.00 1.00 - -
5 Floor drain dia 3" Ex. Toto TX 1 BN bh 1.00 1.00 - -
6 Kaca cermin uk.60x90 cm bh 1.00 1.00 - -
KM/WC KT. Anak : -
1 Closed duduk Ex. Toto CW 421 J / SW 420 JP bh 1.00 1.00 - -
2 Jet washer / shower spray Ex. Toto TX 403 SB bh 1.00 1.00 - -
3 Shower set Ex. Toto TX 433 SD bh 1.00 1.00 - -
4 Wastafel termasuk kran & accessories Ex. Toto LW 240 CJ bh 1.00 - - -
5 Floor drain dia 3" Ex. Toto TX 1 BN bh 1.00 1.00 - -
6 Kaca cermin uk.60x90 cm bh 1.00 - - -
Lain-lain -
1 Roof drain 3" cast iron + corong komplit Ex. Kharisma bh 4.00 3.00 - -
2 Floor drain 3" (area balkon) Ex. Toto TX 403 SB bh 2.00 2.00 - -
3 Bak kontrol uk. 66x66 cm, pas. bata diplester tutup plat beton&grill bh 2.00 2.00 - -
4 FCO Ex. Kharisma bh 1.00 1.00 - -
5 Bioseptictank kap.1000 Ltr / sesuai gambar, Ex. Mitra Sarana Jaya unit 1.00 1.00 - -
6 Sumur Resapan Dia.100 cm unit 1.00 1.00 - -
Page 6 of 7
PARAMOUNT INTERPRISE INTERNATIONAL
RAB OE (Gambar Forcon 15 September 2022)
Proyek : Rumah Tinggal Elista Uk. 7 x 12+ M HOOK (KUSKOVO/02)
: Rumah Tinggal Elista Uk. 6 x 10+ M HOOK (ARBATH/17)
Lokasi : Cluster Elista Village, Paramount Land
Page 7 of 7