RENCANA ANGGARAN BIAYA

Pekerjaan : Jembatan Akses Penghubung


Lokasi : Kec. Wonoayu Kab. Sidoarjo
Tahun Anggaran : 2023
HARGA SATUAN JUMLAH HARGA
NO URAIAN VOLUME SAT.
(Rp.) (Rp.)

A PEKERJAAN PENDAHULUAN
1 Pengukuran Dan Pemasangan Bouwplank 10.00 m' 117,855.10 1,178,551.00
2 Pek. Pembersihan Lapangan 100.00 m2 11,275.00 1,127,500.00
3 Pembuatan Gudang Bahan dan Peralatan 1.00 ls 2,250,000.00 2,250,000.00
4,556,051.00
B PEKERJAAN BANGUNAN BAWAH / PONDASI
1 Pek. Galian Tanah 14.31 m3 85,000.00 1,216,350.00
2 Pek. Pasir Urug t=15 cm 15.00 m3 204,600.00 3,069,000.00
3 Pek. Timbunan Tanah Oprid 26.77 m3 107,000.00 2,864,898.04
4 Pek. Timbunan Tanah kembali 4.29 m3 40,425.00 173,544.53
7,323,792.56
C.1 PEKERJAAN BANGUNAN ATAS STUKTUR
1 Pek. Pasangan Pond. Batu Kali 63.30 m3 1,012,337.86 64,080,986.36
2 Pek. Strous Dia. 30 cm 20.00 m' 550,000.00 11,000,000.00
3 Pek. Plat Beton K-400 20.00 m3 1,263,883.50 25,277,670.00
4 Pek. Pembesian Plat
b. Besi Dia. 13 mm 2,773.33 kg 14,614.45 40,530,741.33
5 Pek. Bekisting Plat 100.00 m2 125,400.00 12,540,000.00
Pek. Beton Girder
1 Pek. Beton Balok Girder K- 400 19.00 m3 1,263,883.50 24,013,786.50
2 Pek. Pembesian Balok Girder
a. Besi Dia. 25 mm 3,638.25 kg 14,614.45 53,171,022.71
b. Besi Dia. 13 mm 1,310.40 kg 14,614.45 19,150,775.28
3 Pek. Bekisting Balok 217.35 m2 275,572.00 59,895,574.20
Pek. Beton Kolom
1 Pek. Beton Kolom Elv. Uk. 0.12 x 0.12 m 0.13 m3 1,026,892.32 133,085.24
2 Pek. Pembesian kolom
a. Besi Dia. 13 mm 44.10 kg 14,614.45 644,438.79
b. Besi Dia. 10 mm 66.11 kg 14,614.45 966,125.15
3 Pek. Bekisting kolom 11.50 m2 344,217.50 3,958,501.25
Pek. Pasangan Batu Kali
1 Pek. Pasangan batu kali Parapet 1Ps : 4 Pc 8.80 m3 1,012,337.86 8,908,573.14
324,271,279.95
C.2 PEKERJAAN BANGUNAN ATAS ARSITEKTUR
1 Pek. Benangan Parapet 110.40 m1 22,250.64 2,456,470.97
2 Pek. Acian 63.76 m2 45,000.00 2,869,200.00
5,325,670.97
D PEKERJAAN PENGAMANAN
1 Pek. Pasangan Hand Railing Besi GI 3" 5.00 ljr 1,261,550.00 6,307,750.00

6,307,750.00
E PEKERJAAN LAIN-LAIN
1 Pek. Cat Dinding Parapet 63.76 m2 36,325.93 2,316,140.98

2,316,140.98