B BETON
1 Beton Pondasi 27,94 m3 Taksir 2 5.037.048,50 140.714.986,90
2 Beton Sloof 30x60 44,75 m3 Taksir 3 5.617.590,00 251.375.917,32
3 Beton Lantai (+0,00) tebal 15cm tanpa Pembesian 91,80 m3 4.1.1.10 1.298.873,25 119.236.564,35
4 KP 426,00 m 4.1.1.35 111.854,75 47.650.123,50
5 RB 308,30 m 4.1.1.36 145.003,50 44.704.579,05
6 Beton Meja wastafel 1,00 Ls - 4.000.000,00 4.000.000,00
7 Beton Plat lantai t=12cm (+3,14) 37,28 m3 Taksir 7 4.751.308,50 177.115.667,27
HALAMAN PARKIR
8 Bekisting Beton Jalan t=20cm 30,00 m2 4.1.1.20 223.629,00 6.708.870,00
Beton Halaman parkir (+0,00)(616m2) t=20cm tanpa
9 123,00 m3 4.1.1.10 1.298.873,25 159.761.409,75
pembesian
10 Penyiraman 1,00 Ls - 2.000.000,00 2.000.000,00
11 Sewa Pompa Beton 1,00 Ls - 15.000.000,00 15.000.000,00
C BAJA
1 Angker besi Ǿ22 P=60cm 72,00 bh - 350.000,00 25.200.000,00
2 Kolom Baja HWF 300x300x10x15 tinggi 8,2m 9249,60 kg 4.2.1.2 37.295,50 344.968.456,80
3 Kolom Baja HWF 200x200x8x12 tinggi 2,85m 1707,15 kg 4.2.1.2 37.295,50 63.669.012,83
4 Kolom Baja HWF 200x200x8x12 tinggi 6,05m 3623,95 kg 4.2.1.2 37.295,50 135.157.027,23
5 Beam IWF 250x125x6x9 (+3m) 6070,50 kg 4.2.1.2 37.295,50 226.402.332,75
6 Beam IWF 250x125x6x9 (+6,11m) 2419,92 kg 4.2.1.2 37.295,50 90.252.002,04
7 Mur Baut Ǿ 16 P=10cm (+3,00) 740,00 bh - 100.000,00 74.000.000,00
8 Mur Baut Ǿ 16 P=10cm (+6,06) 340,00 bh - 100.000,00 34.000.000,00
9 Besi holo 50.50.2.8 dudukan plat bondek 1054,80 kg 4.2.1.2 37.295,50 39.339.293,40
10 Plat bondek 0,75x1m bekisting plat beton 1863,86 kg 4.2.1.2 37.295,50 69.513.665,22
11 Rafter 250x125x6x9 4615,00 kg 4.2.1.2 37.295,50 172.118.732,50
12 Ikatan Angin Ǿ 10 148,00 kg 4.2.1.2 37.295,50 5.519.734,00
13 Trekstang Ǿ 10 333,00 bh 4.2.1.2 37.295,50 12.419.401,50
14 jarum keras 20,00 bh - 500.000,00 10.000.000,00
15 CNP 150.50.20.3,2 6157,67 kg - 37.295,50 229.653.257,17
16 Pas Atap galvalum 0,35 756,00 m2 4.5.2.41 172.224,00 130.201.344,00
17 Pengecatan besi 993,27 m2 4.7.1.16 45.841,88 45.533.359,18
18 Listplank 2x20 dobel 111,00 m1 - 149.672,50 16.613.647,50
19 Nok Atap 31,50 m1 4.5.2.40 67.522,25 2.126.950,88
BALKON + TANGGA TERLUAR KELILING (+3,3 DAN +6,5)
21 IWF 200.100.5,5.8 dudukan UNP 100.50.5 1874,56 kg 4.2.1.2 37.295,50 69.912.652,48
22 IWF 250.125.6.9 Kupingan dudukan IWF 200 710,00 kg 4.2.1.2 37.295,50 26.479.805,00
23 UNP 100.50.5 dudukan plat kembang 2819,74 kg 4.2.1.2 37.295,50 105.163.662,90
24 Plat Kembang 4,2mm 1884,11 kg 4.2.1.2 37.295,50 70.268.943,64
25 Pipa besi 2 inci 2456,49 kg 4.2.1.2 37.295,50 91.615.888,53
26 Besi Holo 40.40.2 tangga 150,00 kg 4.2.1.2 37.295,50 5.594.325,00
27 Pengecatan besi 419,99 m2 4.7.1.16 45.841,88 19.253.037,40
BALKON + TANGGA DALAM KELILING (+3,1)
27 IWF 250.125.6.9 Kupingan dudukan IWF 200 745,50 kg 4.2.1.2 37.295,50 27.803.795,25
28 UNP 100.50.5 dudukan plat kembang 719,36 kg 4.2.1.2 37.295,50 26.828.890,88
29 Plat Kembang 4,2mm 600,83 kg 4.2.1.2 37.295,50 22.408.379,58
30 Pipa besi 2 inci 626,69 kg 4.2.1.2 37.295,50 23.372.642,30
31 Besi Holo 40.40.2 tangga 150,00 kg 4.2.1.2 37.295,50 5.594.325,00
32 Pengecatan besi 114,80 m2 4.7.1.16 45.841,88 5.262.647,25
D LISTRIK
1 Box Panel Listrik Lantai 1 1,00 bh - 20.000.000,00 20.000.000,00
2 Box panel Listrik lantai 2 1,00 bh - 10.000.000,00 10.000.000,00
LANTAI 1
3 Instalasi Titik lampu 81,00 titik Taksir 2 314.366,25 25.463.666,25
4 Saklar tunggal 17,00 bh Taksir 5 46.097,70 783.660,90
5 Saklar Ganda 23,00 bh Taksir 6 57.097,70 1.313.247,10
6 Lampu TL LED 2x16 RM Recessed Mounted (Acrilic) 25,00 bh - 900.000,00 22.500.000,00
7 Lampu Panel RC091V LED 365/865 PSU 22,00 bh - 1.000.000,00 22.000.000,00
8 Lampu SL Led 22 watt 34,00 bh 500.000,00 17.000.000,00
9 Instalasi titik stop kontak 51,00 titik Taksir 1 314.366,25 16.032.678,75
10 Stop kontak tunggal 51,00 bh Taksir 4 53.797,70 2.743.682,70
LANTAI 2
11 Instalasi Titik lampu 21,00 titik Taksir 2 314.366,25 6.601.691,25
12 Saklar tunggal 18,00 bh Taksir 5 46.097,70 829.758,60
13 Saklar Ganda 1,00 bh Taksir 6 57.097,70 57.097,70
14 Lampu SL Led 22 watt 21,00 bh - 500.000,00 10.500.000,00
15 Instalasi titik stop kontak 11,00 titik Taksir 1 314.366,25 3.458.028,75
16 Stop kontak tunggal 11,00 bh Taksir 4 53.797,70 591.774,70
E SANITASI
1 Pek. Wastafel 2,00 Unit - 2.045.835,00 4.091.670,00
2 Pek. Kran Washtafel 2,00 buah - 450.000,00 900.000,00
3 Pek pipa PVC tipe AW Ø 1" 6,00 m' 5.1.1.27 35.201,50 211.209,00
4 Pek pipa PVC tipe AW Ø 1/2" 40,00 m' 5.1.1.25 26.836,69 1.073.467,50
5 Pek pipa PVC tipe AW Ø 3" 30,00 m' 5.1.1.31 119.780,41 3.593.412,19
6 Pek pipa PVC tipe AW Ø 4" 30,00 m' 5.1.1.32 173.391,25 5.201.737,50
7 Klosed Duduk 4,00 unit - 3.655.201,00 14.620.804,00
8 Jet Washer 4,00 unit - 800.000,00 3.200.000,00
9 Urinoir 2,00 unit 5.1.1.4 4.993.846,00 9.987.692,00
10 Sekat Urinoir 2,00 bh - 2.000.000,00 4.000.000,00
11 Floordrain stainless 6,00 bh 5.1.1.14 337.956,25 2.027.737,50
12 Shower + Kran air 3,00 bh - 1.200.000,00 3.600.000,00
13 Kran air biasa 3,00 bh 5.1.1.19 131.344,38 394.033,13
14 Tedmon 1m3 1,00 bh 5.1.1.10 1.831.432,50 1.831.432,50
15 Torn tedmon tinggi 1,5m + dudukan 1,00 Ls - 10.000.000,00 10.000.000,00
I CAT
1 Pekerjaan Cat dinding Kw 3 1710,50 m2 4.7.1.10.a 31.725,63 54.266.681,56