REKAPITULASI
RENCANA ANGGARAN BIAYA

PEKERJAAN : PERENCANAAN PEMBANGUNAN JEMBATAN (PONDASI PANCANG)


DI LOKASI : SUNGAI BATANG TEMBESI, MUARA KETALO
PANJANG : 160 M'(Lebar Jalan 8.0 M')
TAHUN : 2023

Jumlah Harga
No. Divisi Uraian Pekerjaan
(Rupiah)

1 Umum 1,807,700,000.00
2 Drainase -
3 Pekerjaan Tanah 24,730,720.00
4 Pelebaran Perkerasan dan Bahu Jalan -
5 Pekerasan Berbutir -
6 Perkerasan Aspal -
7 Struktur 57,792,125,615.12
8 Pengembalian Kondisi dan Pekerjaan Minor 370,000,000.00
9 Pekerjaan Harian & Lain Lain 6,000,000.00

(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 60,000,556,335.12
(B) Total Harga Pekerjaan 60,000,000,000.00
(C) Pajak Pertambahan Nilai ( PPN ) = 11% x (B) 6,600,000,000.00
(D) JUMLAH TOTAL HARGA PEKERJAAN = (B) + (C) 66,600,000,000.00
(E) JUMLAH (B) + (C) DIBULATKAN 66,600,000,000.00

Terbilang : Enam Puluh Enam Milyar Enam Ratus 0 0 Juta 0 0 0 0 0 Rupiah


RENCANA ANGGARAN BIAYA
( RAB )

PEKERJAAN : PERENCANAAN PEMBANGUNAN JEMBATAN (PONDASI PANCANG)


DI LOKASI : SUNGAI BATANG TEMBESI, MUARA KETALO
PANJANG : 160 M'(Lebar Jalan 8.0 M')
TAHUN : 2023

No. Mata Perkiraan Harga Jumlah


Uraian
Pembayaran Satuan Kuantitas Satuan Harga

(Rupiah) ( Rupiah )

a b c d e f=(dxe)

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 1,712,000,000.00 1,712,000,000.00
1.19 Keselamatan dan Kesehatan Kerja Ls 1.00 95,700,000.00 95,700,000.00

Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,807,700,000.00

DIVISI 3. PEKERJAAN TANAH


3.1.(1a) Galian Struktur dengan kedalaman 0-2 meter M3 193.50 56,800.00 10,990,800.00
3.1.(4) Galian Struktur dengan kedalaman 2 - 4 meter M3 241.90 56,800.00 13,739,920.00

Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 24,730,720.00

DIVISI 5. PERKERASAN BERBUTIR


5.1.(2) Lapis Pondasi Agregat Kelas B M3 - - -

Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) -

DIVISI 7. STRUKTUR
7.1 (5) a Beton Fc' 35 Mpa M3 1,119.00 3,200,000.00 3,580,800,000.00
7.1 (5) b Beton Fc' 30 Mpa M3 1,823.00 2,900,000.00 5,286,700,000.00
7.1 (6) Beton Fc' 10 Mpa M3 8.10 1,200,000.00 9,720,000.00
7.3 (3) Baja Tulangan Kg 397,350.00 20,575.00 8,175,476,250.00
7.4 (1) a Penyediaan Pipa Baja diameter 4 inchi (Skoor Fender) Kg 6,226.00 32,900.00 204,835,400.00
7.4 (3) a Pengadaan Struktur Jembatan Girder Baja Panjang 40 m Kg 396,735.90 32,000.00 12,695,548,800.00
7.5 (1) Pemasangan jembatan Girder Baja Kg 396,735.90 10,000.00 3,967,359,000.00
7.5 (2) Pengangkutan Bahan Jembatan Kg 396,735.90 4,600.00 1,824,985,140.00
7.6 (8) a Penyediaan Tiang Pancang Baja Diameter 300 mm dengan tebal 10 mm M1 576.00 1,500,000.00 864,000,000.00
7.6 (8) b Penyediaan Tiang Pancang Baja Diameter 400 mm dengan tebal 12 mm M1 270.00 2,100,000.00 567,000,000.00
7.6 (8) c Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm M1 294.00 3,650,000.00 1,073,100,000.00
7.6 (8) d Penyediaan Tiang Pancang Baja Diameter 800 mm dengan tebal 16 mm M1 2,016.00 6,100,000.00 12,297,600,000.00
7.6 (14) a Pemancangan Tiang Pancang Baja Diameter 300 mm (Fender) M1 576.00 517,000.00 297,792,000.00
7.6 (14) b Pemancangan Tiang Pancang Baja Diameter 400 mm M1 270.00 650,000.00 175,500,000.00
7.6 (14) c Pemancangan Tiang Pancang Baja Diameter 600 mm M1 294.00 890,000.00 261,660,000.00
7.6 (14) d Pemancangan Tiang Pancang Baja Diameter 800 mm M1 168.00 1,000,000.00 168,000,000.00
7.6 (19) a Pekerjaan Preboring Tiang Pancang Baja Dia. 800 mm M1 648.00 5,200,000.00 3,369,600,000.00
7.6 (19) a Pekerjaan Preboring Tiang Pancang Baja Dia. 300 mm M1 264.00 5,430,000.00 1,433,520,000.00
7.7 Pile Driving Analyzer (PDA) Test Titik 5.00 3,100,000.00 15,500,000.00
Pengujian Non-Destructive Test Ultrasonic Test (UT) - (10% Pengetesan) Kg 39,673.59 1,600.00 63,477,744.00
Complete Joint Penetration (CJP) Kg 396,735.90 2,500.00 991,839,750.00
7.6 (21) Tambahan Biaya bila tiang bor dikerjakan di air M1 681.00 -
7.6 (28) Pengujian keutuhan Tiang dengan Pile Intergrated Test (PIT) bh 54.00 3,050,000.00 164,700,000.00
7.11 (7) Sambungan Siar Muai Expansion M1 78.40 1,600,000.00 125,440,000.00
7.12 (2) Landasan elastomrtik karet alam berlapis baja bh 48.00 1,400,000.00 67,200,000.00
7.14 (1) Papan Nama Jembatan bh 1.00 860,000.00 860,000.00
7.16 (1) Dreck Drain bh 72.00 920,000.00 66,240,000.00
7.16 (3a) Pipa Drainase PVC dia. 150mm M1 168.00 259,949.59 43,671,531.12
Sewa Tongkang/Tugboat Ls 1.00 -

Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 57,792,125,615.12

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.1 Pengadaan dan Pemasangan Beam Guardrail M1 200.00 1,850,000.00 370,000,000.00

Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 370,000,000.00

DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN - LAIN


9.2 (3a) Rambu Jalan Tunggal bh 2.00 3,000,000.00 6,000,000.00

Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 6,000,000.00
Analisa EI-733
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 3.1.(4)
JENIS PEKERJAAN : Galian Struktur dengan kedalaman 2 - 4 meter
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Jurnal Best Price

1. Pekerja (L01) jam 0.0550 25,000.00 1,375.00 1170.90 1,170.90


2. Mandor (L03) jam 0.0050 34,000.00 170.00 129.99 129.99

JUMLAH HARGA TENAGA 1,545.00 1,300.88 1,300.88

B. BAHAN Jurnal Best Price

1. Urugan Pilihan (M57c) Kg 1.200 40,000.00 48,000.00 48,000.00


2. Bahan pengaman tebing g (M14) Kg 0.0200 35,000.00 700.00 700.00

JUMLAH HARGA BAHAN 48,700.00 48,700.00 48,700.00

C. PERALATAN Jurnal Best Price

1. Excavator E29 jam 0.0060 550,000.00 3,300.00 2553.52 2,255.61

JUMLAH HARGA PERALATAN 3,300.00 2,553.52 2,255.61

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 53,600.00 52,554.41 52,256.49


E. OVERHEAD & PROFIT 6.0 % x D 3,216.00 3153.26 3135.39
F. HARGA SATUAN PEKERJAAN ( D + E ) 56,800.00 55,707.67 55,391.88
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-716
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. :7.1 (6)
JENIS PEKERJAAN :Beton mutu sedang fc’= 30 Mpa
SATUAN PEMBAYARAN :M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Jurnal Best Price

1. Pekerja (L01) jam 3.2129 25,000.00 80,321.29 Rp68,398.39 68,398.39


2. Tukang (L02) jam 4.8193 28,000.00 134,939.76 Rp132,878.51 132,878.51
3. Mandor (L03) jam 0.4016 32,000.00 12,851.41 Rp10,440.85 10,440.85

JUMLAH HARGA TENAGA 228,112.45 211,717.75 211,717.75

B. BAHAN Jurnal Best Price

1. Semen Kg 500.0000 1,700.00 850,000.00 Rp720,000.00 720,000.00


2. Pasir beton (M01a) M3 0.5718 200,000.00 114,354.41 Rp206,409.72 114,354.41
3. Agregat Kasar (M03) M3 0.8080 600,000.00 484,795.86 Rp363,596.90 363,596.90
4. Kayu Perancah (M19) M3 0.4000 1,000,000.00 400,000.00 Rp914,000.00 400,000.00
5. Paku (M18) Kg 4.8000 30,000.00 144,000.00 Rp134,640.00 134,640.00
6. Air (M170) Ltr 190.5500 150.00 28,582.50 Rp19,055.00 19,055.00

JUMLAH HARGA BAHAN 2,021,732.78 2,357,701.61 1,751,646.31

C. PERALATAN Trinity Jurnal Best Price

1. Concrete Mixing Plant (E43) jam 0.0802 122,222.47 9,802.24 Rp9,802.24 9,802.24
2. Truck Mixer (E49) jam 0.8000 606,636.42 485,309.14 Rp485,309.14 485,309.14
3. Concrete Vibrator (E23) jam 0.4012 63,250.23 25,375.99 Rp25,375.99 25,375.99
4. Water Tank Truck jam 0.2146 355,599.14 76,321.12 Rp76,321.12 76,321.12
Pompa Long Boom Jam 0.05 948,488.94 47,424.45 Rp47,424.45 Rp47,424.45

Alat Bantu (E20) Ls 1.0000 125,000.00 125,000.00 - 125,000.00

JUMLAH HARGA PERALATAN 769,232.94 769,232.94 769,232.94

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,748,991.70 3,338,652.30 2,732,597.00


E. OVERHEAD & PROFIT 6% % x D 164,939.50 200,319.14 163,955.82
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,913,931.20 3,538,971.44 2,896,552.82
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-715
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. :7.1 (5)
JENIS PEKERJAAN :Beton mutu sedang fc’= 35 Mpa
SATUAN PEMBAYARAN :M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 3.2129 25,000.00 80,321.29 Rp68,398.39 68,398.39


2. Tukang (L02) jam 4.8193 28,000.00 134,939.76 Rp132,878.51 132,878.51
3. Mandor (L03) jam 0.4016 32,000.00 12,851.41 Rp10,440.85 10,440.85

JUMLAH HARGA TENAGA 228,112.45 211,717.75 211,717.75

B. BAHAN Trinity Jurnal Best Price

1. Semen Kg 550.0000 1,700.00 935,000.00 Rp792,000.00 792,000.00


2. Pasir beton (M01a) M3 0.5468 200,000.00 109,360.00 Rp197,394.80 109,360.00
3. Agregat Kasar (M03) M3 0.8061 600,000.00 483,660.00 Rp362,745.00 362,745.00
4. Kayu Perancah (M19) M3 0.4000 1,000,000.00 400,000.00 Rp914,000.00 400,000.00
5. Paku (M18) Kg 4.8000 30,000.00 144,000.00 Rp134,640.00 134,640.00
6. Air (M170) Ltr 190.5500 100.00 19,055.00 Rp2,791.56 2,791.56

JUMLAH HARGA BAHAN 2,091,075.00 2,403,571.36 1,801,536.56

C. PERALATAN Trinity Jurnal Best Price

1. Concrete Mixing Plant (E43) jam 0.3310 700,000.00 231,725.03 Rp40,460.01 40,460.01
2. Truck Mixer (E49) jam 0.5191 700,000.00 363,355.23 Rp314,892.16 314,892.16
3. Concrete Vibrator (E23) jam 0.3012 200,000.00 60,240.96 Rp19,051.27 19,051.27
4. Water Tank Truck jam 0.0382 425,000.00 16,214.86 Rp13,567.04 13,567.04
Pompa Long Boom Jam 0.2000 1,875,000.00 375,000.00 Rp189,697.79 189697.788

Alat Bantu (E20) Ls 1.0000 150,000.00 125,000.00 - 125,000.00

JUMLAH HARGA PERALATAN 1,171,536.08 702,668.27 702,668.27

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,021,855.72 3,317,957.37 2,715,922.57


E. OVERHEAD & PROFIT 6% % x D 181,311.34 199,077.44 162,955.35
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,203,167.06 3,517,034.82 2,878,877.93
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7110
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. :7.1 (10)
JENIS PEKERJAAN :Beton mutu sedang fc’= 10 Mpa
SATUAN PEMBAYARAN :M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 3.1343 25,000.00 78,356.31 Rp66,725.10 66,725.10


2. Tukang (L02) jam 4.8193 28,000.00 134,939.76 Rp132,878.51 132,878.51
3. Mandor (L03) jam 0.4016 32,000.00 12,851.41 Rp10,440.85 10,440.85

JUMLAH HARGA TENAGA 226,147.48 210,044.46 210,044.46

B. BAHAN Trinity Jurnal Best Price

1. Semen Kg 241.3900 1,700.00 410,363.00 Rp347,601.60 347,601.60


2. Pasir beton (M01a) M3 0.3607 200,000.00 72,140.00 Rp130,212.70 72,140.00
3. Agregat Kasar (M03) M3 0.5490 600,000.00 329,400.00 Rp247,050.00 247,050.00
4. Paku (M18) Kg 0.4000 30,000.00 12,000.00 Rp11,220.00 11,220.00
5. Air (M170) Ltr 190.5500 100.00 19,055.00 Rp2,791.56 2,791.56

JUMLAH HARGA BAHAN 842,958.00 738,875.86 680,803.16

C. PERALATAN Trinity Jurnal Best Price

1. Concrete Mixer (E43) jam 0.1147 500,000.00 57,350.00 Rp14,018.92 14,018.92


2 Water Tank Truck jam 0.0291 425,000.00 12,367.50 Rp10,347.93 10,347.93
Alat Bantu (E20) Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 69,717.50 24,366.85 24,366.85

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,138,822.98 973,287.17 915,214.47


E. OVERHEAD & PROFIT 6% % x D 68,329.38 58,397.23 54,912.87
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,207,152.36 1,031,684.40 970,127.33
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-733
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.3 (3)
JENIS PEKERJAAN : Baja Tulangan U 32 Ulir
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.1050 20,000.00 2,100.00 2,235.35 2,235.35

JUMLAH HARGA TENAGA 2,100.00 2,235.35 4,110.30

B. BAHAN Trinity Jurnal Best Price

1. Besi Tulangan (M57c) Kg 1.100 13,600.00 14,960.00 22,990.00 14,960.00


2. Kawat Beton (M14) Kg 0.0200 35,000.00 700.00 625.00 625.00

JUMLAH HARGA BAHAN 15,660.00 23,615.00 15,585.00

C. PERALATAN Trinity Jurnal Best Price

1. Alat Bantu E29 jam 1.0500 1,600.00 1,680.00 1,680.00 1,680.00

JUMLAH HARGA PERALATAN 1,680.00 1,680.00 1,680.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 19,500.00 27,530.35 21,375.30


E. OVERHEAD & PROFIT 6.0 % x D 1,170.00 1,651.82 1,282.52
F. HARGA SATUAN PEKERJAAN ( D + E ) 20,600.00 29,182.17 22,657.81
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-768d

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (8) d
JENIS PEKERJAAN :Penyediaan Tiang Pancang Baja Diameter 800 mm dengan tebal 16 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.5833 25,000.00 14,583.33 12,418.58 Rp12,418.58


2. Tukang (L02) jam 0.1944 28,000.00 5,444.44 5,361.28 Rp5,361.28
3. Mandor (L03) jam 0.0543 32,000.00 1,736.19 1,410.53 Rp1,410.53

JUMLAH HARGA TENAGA 21,763.97 19,190.39 Rp19,190.39

B. BAHAN Trinity Jurnal Best Price

1. Pipa baja M52 Kg 314.39 15,150.00 4,763,008.50 8,802,920.00 4,763,008.50


2. Plat Baja M48 Kg 0.4487 23,000.00 10,319.43 12,562.78 10,319.43

JUMLAH HARGA BAHAN 4,773,327.93 8,815,482.78 4,773,327.93

C. PERALATAN Trinity Jurnal Best Price

1. Trailer E29 jam 0.3664 2,050,000.00 751,185.94 158,476.82 158,476.82


2. Crane E07 jam 0.0335 600,000.00 20,080.32 19,212.61 19,212.61
3. Welding Set E32 jam 0.5234 100,000.00 52,343.12 34,977.81 34,977.81
4 Alat Bantu Ls 1.0000 150000.00 150,000.00 150,000.00

JUMLAH HARGA PERALATAN 973,609.38 362,667.24 362,667.24

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5,768,800.00 9,197,340.41 5,155,185.56


E. OVERHEAD & PROFIT 6.0 % x D 346,128.00 551,840.42 309,311.13
G. HARGA SATUAN PEKERJAAN ( D + E ) 6,114,900.00 9,749,180.84 5,464,496.69
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volu
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-768a
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (8) a
JENIS PEKERJAAN :Penyediaan Tiang Pancang Baja Diameter 300 mm dengan tebal 10 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.5833 25,000.00 14,583.33 12,418.58 Rp12,418.58


2. Tukang (L02) jam 0.1944 28,000.00 5,444.44 5,361.28 Rp5,361.28
3. Mandor (L03) jam 0.0543 32,000.00 1,736.19 1,410.53 Rp1,410.53

JUMLAH HARGA TENAGA 21,763.97 19,190.39 Rp19,190.39

B. BAHAN Trinity Jurnal Best Price

1. Pipa baja M52 Kg 71.514 15,000.00 1,072,710.00 2,002,392.00 Rp2,910,301.83


2. Plat Baja M48 Kg 0.4487 23,000.00 10,319.43 12,562.78 Rp10,319.43

JUMLAH HARGA BAHAN 1,083,029.43 2,014,954.78 Rp2,920,621.26

C. PERALATAN Trinity Jurnal Best Price

1. Trailer E29 jam 0.1000 2,000,000.00 200,000.00 43,248.61 Rp43,248.61


2. Crane E07 jam 0.0335 656,370.13 21,966.87 19,212.61 Rp19,212.61
3. Welding Set E32 jam 0.5234 116,337.61 60,894.73 34,977.81 Rp34,977.81
4 Alat Bantu Ls 1.0000 75,000.00 75,000.00 75,000.00

JUMLAH HARGA PERALATAN 357,861.61 172,439.03 172,439.03

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,462,700.00 2,206,584.20 3,112,250.68


E. OVERHEAD & PROFIT 6.0 % x D 87,762.00 132,395.05 186,735.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,550,462.00 2,338,979.25 3,298,985.72
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-768c
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (8) c
JENIS PEKERJAAN :Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.5833 25,000.00 14,583.33 12,418.58 Rp12,418.58


2. Tukang (L02) jam 0.1944 28,000.00 5,444.44 5,361.28 Rp5,361.28
3. Mandor (L03) jam 0.0543 32,000.00 1,736.19 1,410.53 Rp1,410.53

JUMLAH HARGA TENAGA 21,763.97 19,190.39 Rp19,190.39

B. BAHAN Trinity Jurnal Best Price

1. Pipa baja M52 Kg 174.001 18,100.00 3,149,417.38 4,872,026.88 Rp2,722,245.02


2. Plat Baja M48 Kg 0.4487 23,000.00 10,319.43 12,562.78 Rp10,319.43

JUMLAH HARGA BAHAN 3,159,736.80 4,884,589.66 Rp2,732,564.45

C. PERALATAN Trinity Jurnal Best Price

1. Trailer E29 jam 0.1000 2,050,000.00 205,000.00 43,248.61 Rp43,248.61


2. Crane E07 jam 0.0167 700,000.00 11,690.00 9,587.01 Rp9,587.01
3. Welding Set E32 jam 0.3897 120,000.00 46,758.80 26,038.45 Rp26,038.45

JUMLAH HARGA PERALATAN 263,448.80 78,874.07 Rp78,874.07

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,444,949.58 4,982,654.13 2,830,628.92


E. OVERHEAD & PROFIT 6.0 % x D 206,696.97 298,959.25 169,837.73
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,651,646.55 5,281,613.38 3,000,466.65
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-768b
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (8) b
JENIS PEKERJAAN :Penyediaan Tiang Pancang Baja Diameter 400 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.5833 25,000.00 14,583.33 12,418.58 Rp12,418.58


2. Tukang (L02) jam 0.1944 28,000.00 5,444.44 5,361.28 Rp5,361.28
3. Mandor (L03) jam 0.0543 32,000.00 1,736.19 1,410.53 Rp1,410.53

JUMLAH HARGA TENAGA 21,763.97 19,190.39 Rp19,190.39

B. BAHAN Trinity Jurnal Best Price

1. Pipa baja M52 Kg 123.310 14,350.00 1,769,498.50 3,452,680.00 Rp1,849,650.00


2. Plat Baja M48 Kg 0.2111 23,000.00 4,855.30 5,910.80 Rp4,855.30

JUMLAH HARGA BAHAN 1,774,353.80 3,458,590.80 Rp1,854,505.30

C. PERALATAN Trinity Jurnal Best Price

1. Trailer E29 jam 0.0870 2,050,000.00 178,350.00 37,626.29 Rp37,626.29


2. Crane E07 jam 0.0167 600,000.00 10,020.00 9,587.01 Rp9,587.01
3. Welding Set E32 jam 0.0167 115,000.00 1,920.50 1,115.96 Rp1,115.96
4 Alat Bantu Ls 1.0000 - 0.00

JUMLAH HARGA PERALATAN 190,290.50 48,329.27 Rp48,329.27

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + 1,986,500.00 3,526,110.46 1,922,024.96


E. OVERHEAD & PROFIT 6.0 % x D 119,190.00 211,566.63 115,321.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,105,700.00 3,737,677.09 2,037,346.46
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7614d

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (14) d
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 800 mm
SATUAN PEMBAYARAN :M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 3.0120 25,000.00 75,301.20 64,123.49 Rp64,123.49


2. Tukang (L02) jam 1.0040 28,000.00 28,112.45 27,683.02 Rp27,683.02
3. Mandor (L03) jam 0.5020 32,000.00 16,064.26 13,051.06 Rp13,051.06

JUMLAH HARGA TENAGA 119,477.91 104,857.58 104,857.58

B. BAHAN Trinity Jurnal Best Price

1. Kawat Las Doz 0.7500 70,000.00 52,500.00 12,000.00 Rp12,000.00


2. Oxygen Tabung 0.5000 290,000.00 145,000.00 57,375.00 Rp57,375.00
3. Assetiline Tabung 0.5000 500,000.00 250,000.00 114,750.00 Rp114,750.00

JUMLAH HARGA BAHAN 447,500.00 184,125.00 184,125.00

C. PERALATAN Trinity Jurnal Best Price

1. Pile Driver Hammer E30 jam 0.5000 300,000.00 150,000.00 75,847.42 75,847.42
2 Crane Jam 0.6018 350,000.00 210,637.71 345,489.61 210,637.71
3 Alat Bantu Ls 1.0000 50,000.00 50,000.00 50,000.00

JUMLAH HARGA PERALATAN 410,637.71 471,337.02 336,485.13

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 977,615.63 760,319.60 625,467.70


E. OVERHEAD & PROFIT 6% x D 58,656.94 45,619.18 37,528.06
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,036,272.56 805,938.77 662,995.77
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7614c

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (14) a
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 600 mm
SATUAN PEMBAYARAN :M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 3.0120 25,000.00 75,301.20 64,123.49 Rp64,123.49


2. Tukang (L02) jam 1.0040 31,250.00 31,375.50 27,683.02 Rp27,683.02
3. Mandor (L03) jam 0.5020 34,375.00 17,256.53 13,051.06 Rp13,051.06

JUMLAH HARGA TENAGA 123,933.23 104,857.58 104,857.58

B. BAHAN Trinity Jurnal Best Price

1. Kawat Las Doz 0.7500 70,000.00 52,500.00 12,000.00 Rp12,000.00


2. Oxygen Tabung 0.5000 290,000.00 145,000.00 57,375.00 Rp57,375.00
3. Assetiline Tabung 0.5000 500,000.00 250,000.00 114,750.00 Rp114,750.00

JUMLAH HARGA BAHAN 447,500.00 184,125.00 184,125.00

C. PERALATAN Trinity Jurnal Best Price

1. Pile Driver Hammer E30 jam 0.5075 350,000.00 177,627.88 76,986.37 76,986.37
2 Crane Jam 0.1991 500,000.00 99,550.00 114,297.88 99,550.00
3 Alat Bantu Ls 1.0000 50,000.00 50,000.00 50,000.00

JUMLAH HARGA PERALATAN 327,177.88 241,284.25 226,536.37

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 898,611.11 530,266.83 515,518.95


E. OVERHEAD & PROFIT 6% x D 53,916.67 31,816.01 30,931.14
F. HARGA SATUAN PEKERJAAN ( D + E ) 952,527.78 562,082.84 546,450.09
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7614a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (14) a
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 300 mm
SATUAN PEMBAYARAN :M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 2.0000 25,000.00 50,000.00 42,578.00 Rp42,578.00


2. Tukang (L02) jam 1.0040 31,250.00 31,375.50 27,683.02 Rp27,683.02
3. Mandor (L03) jam 0.5020 34,375.00 17,256.53 13,051.06 Rp13,051.06

JUMLAH HARGA TENAGA 98,632.03 83,312.08 83,312.08

B. BAHAN Trinity Jurnal Best Price

1. Kawat Las Doz 0.5000 70,000.00 35,000.00 8,000.00 Rp8,000.00


2. Oxygen Tabung 0.3000 290,000.00 87,000.00 34,425.00 Rp34,425.00
3. Assetiline Tabung 0.3000 500,000.00 150,000.00 68,850.00 Rp68,850.00

JUMLAH HARGA BAHAN 272,000.00 111,275.00 111,275.00

C. PERALATAN Trinity Jurnal Best Price

1. Pile Driver Hammer E30 jam 0.1900 350,000.00 66,500.00 28,822.02 28,822.02
2 Crane Jam 0.0896 500,000.00 44,812.42 51,451.17 44,812.42
3 Alat Bantu Ls 0.8000 50,000.00 40,000.00 40,000.00

JUMLAH HARGA PERALATAN 151,312.42 120,273.19 113,634.43

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 521,944.44 314,860.27 308,221.52


E. OVERHEAD & PROFIT 6% x D 31,316.67 18,891.62 18,493.29
F. HARGA SATUAN PEKERJAAN ( D + E ) 553,261.11 333,751.89 326,714.81
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7614c

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : OPSI 1 - PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (14) a
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 400 mm
SATUAN PEMBAYARAN :M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 3.0120 25,000.00 75,301.20 64,123.49 Rp64,123.49


2. Tukang (L02) jam 1.0040 31,250.00 31,375.50 27,683.02 Rp27,683.02
3. Mandor (L03) jam 0.5020 34,375.00 17,256.53 13,051.06 Rp13,051.06

JUMLAH HARGA TENAGA 123,933.23 104,857.58 104,857.58

B. BAHAN Trinity Jurnal Best Price

1. Kawat Las Doz 0.5000 70,000.00 35,000.00 8,000.00 Rp8,000.00


2. Oxygen Tabung 0.3000 290,000.00 87,000.00 34,425.00 Rp34,425.00
3. Assetiline Tabung 0.3000 500,000.00 150,000.00 68,850.00 Rp68,850.00

JUMLAH HARGA BAHAN 272,000.00 111,275.00 111,275.00

C. PERALATAN Trinity Jurnal Best Price

1. Pile Driver Hammer E30 jam 0.4000 350,000.00 140,000.00 60,677.93 60,677.93
2 Crane Jam 0.1517 500,000.00 75,826.03 87,059.30 75,826.03
3 Alat Bantu Ls 1.0000 50,000.00 50,000.00 50,000.00

JUMLAH HARGA PERALATAN 265,826.03 197,737.24 186,503.96

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 661,759.26 413,869.81 402,636.53


E. OVERHEAD & PROFIT 6% x D 39,705.56 24,832.19 24,158.19
F. HARGA SATUAN PEKERJAAN ( D + E ) 701,464.81 438,702.00 426,794.73
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7117

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.11 (7)
JENIS PEKERJAAN : Sambungan Siar Muai Tpe Karet
SATUAN PEMBAYARAN :M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 4.2700 25,000.00 106,750.00 90,904.03 Rp90,904.03


2. Tukang (L02) jam 1.7100 31,250.00 53,437.50 47,148.62 Rp47,148.62
3. Mandor (L03) jam 0.8500 34,375.00 29,218.75 22,098.05 Rp22,098.05

JUMLAH HARGA TENAGA 189,406.25 160,150.70 160,150.70

B. BAHAN Trinity Jurnal Best Price

1. Sambungan Siar Muai Tipe Karet Kg 36.8900 30,000.00 1,106,700.00 2,264,308.20 1,106,700.00
(Preformed T-Shape)

JUMLAH HARGA BAHAN 1,106,700.00 2,264,308.20 1,106,700.00

C. PERALATAN Trinity Jurnal Best Price

1. Welding Set E30 jam 1.0294 350,000.00 360,282.64 68,787.30 68,787.30


2. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 360,282.64 68,787.30 68,787.30

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,656,388.89 2,493,246.20 1,335,638.00


E. OVERHEAD & PROFIT 6% x D 99,383.33 149,594.77 80,138.28
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,755,772.22 2,642,840.97 1,415,776.28
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7117

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.12 (2)
JENIS PEKERJAAN : Landasan Elastomerik Karet Alam Berlapis Baja
SATUAN PEMBAYARAN : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 2.3300 25,000.00 58,250.00 49,603.37 Rp49,603.37


2. Tukang (L02) jam 0.7773 31,250.00 24,291.46 21,432.68 Rp21,432.68
3. Mandor (L03) jam 0.5833 34,375.00 20,051.13 15,164.61 Rp15,164.61

JUMLAH HARGA TENAGA 102,592.59 86,200.66 86,200.66

B. BAHAN Trinity Jurnal Best Price

1. Elastomer Bearing Pad Kg 1.0000 1,160,000.00 1,160,000.00 1,160,000.00


(45 x 280 x 350)

JUMLAH HARGA BAHAN 1,160,000.00 1,160,000.00

C. PERALATAN Trinity Jurnal Best Price

1. Alat Bantu Ls 1.0000 150,000.00 150,000.00 150,000.00

JUMLAH HARGA PERALATAN 150,000.00 150,000.00 150,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,412,592.59 1,396,200.66 1,396,200.66


E. OVERHEAD & PROFIT 6% x D 84,755.56 83,772.04 83,772.04
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,497,348.15 1,479,972.70 1,479,972.70
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7141

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.14 (1)
JENIS PEKERJAAN : Papan Nama Jembatan
SATUAN PEMBAYARAN : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 4.6700 25,000.00 116,750.00 99,419.63 Rp99,419.63


2. Tukang (L02) jam 2.3300 31,250.00 72,812.50 64,243.44 Rp64,243.44
3. Mandor (L03) jam 2.3300 34,375.00 80,093.75 60,574.66 Rp60,574.66

JUMLAH HARGA TENAGA 269,656.25 224,237.73 Rp224,237.73

B. BAHAN Trinity Jurnal Best Price

1. Marmer m2 0.7500 450,000.00 337,500.00 337,500.00 337,500.00


2. Adukan Semen m3 0.8885 70,000.00 62,195.60 62,195.60

JUMLAH HARGA BAHAN 399,695.60 399,695.60

C. PERALATAN Trinity Jurnal Best Price

1. Alat Bantu Ls 1.0000 200,000.00 200,000.00 200,000.00

JUMLAH HARGA PERALATAN 200,000.00 200,000.00 200,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 869,351.85 823,933.33 823,933.33


E. OVERHEAD & PROFIT 6% x D 52,161.11 49,436.00 49,436.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 921,512.96 873,369.33 873,369.33
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7161

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.16 (1)
JENIS PEKERJAAN : Deck Drain
SATUAN PEMBAYARAN : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.3500 25,000.00 8,750.00 7,451.15 Rp7,451.15


2. Tukang (L02) jam 0.3500 31,250.00 10,937.50 9,650.30 Rp9,650.30
3. Mandor (L03) jam 0.3500 34,375.00 12,031.25 9,099.20 Rp9,099.20

JUMLAH HARGA TENAGA 31,718.75 26,200.65 26,200.65

B. BAHAN Trinity Jurnal Best Price

1. Deck Drain Baja Unit 1.0000 650,000.00 650,000.00 550,000.00 550,000.00


2. Baja Tulangan (Angkur) Penggantung Kg 0.5000 20,000.00 10,000.00 10,450.00 10,000.00

JUMLAH HARGA BAHAN 660,000.00 560,450.00 560,000.00

C. PERALATAN Trinity Jurnal Best Price

1. Alat Bantu Ls 1.2155 200,000.00 243,096.06 243,096.06

JUMLAH HARGA PERALATAN 243,096.06 243,096.06 243,096.06

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 934,814.81 829,746.71 829,296.71


E. OVERHEAD & PROFIT 6% x D 56,088.89 49,784.80 49,757.80
F. HARGA SATUAN PEKERJAAN ( D + E ) 990,903.70 879,531.52 879,054.52
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7162

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.16 (2a)
JENIS PEKERJAAN : Pipa Drainase Baja Dia. 150 mm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 1.4000 25,000.00 35,000.00 29,804.60 Rp29,804.60


2. Tukang (L02) jam 0.3500 31,250.00 10,937.50 9,650.30 Rp9,650.30
3. Mandor (L03) jam 0.1167 34,375.00 4,011.56 3,033.93 Rp3,033.93

JUMLAH HARGA TENAGA 49,949.06 42,488.83 Rp42,488.83

B. BAHAN Trinity Jurnal Best Price

1. Pipa Baja Dia 150 mm batang/m' 0.3300 400,000.00 132,000.00 132,000.00 132,000.00
2. Baja Tulangan (ankur) Kg 1.0000 15,000.00 15,000.00 20,900.00 15,000.00
3. Lem PVC Kg 0.5000 60,000.00 30,000.00 22,500.00 22,500.00

JUMLAH HARGA BAHAN 177,000.00 175,400.00 169,500.00

C. PERALATAN Trinity Jurnal Best Price

1. Welding Set Ls 0.1754 200,000.00 35,087.97 11,723.61 11,723.61


2. Alat Bantu Ls 1.0000 - 0.00

JUMLAH HARGA PERALATAN 35,087.97 11,723.61 11,723.61

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 262,037.04 229,612.44 223,712.44


E. OVERHEAD & PROFIT 6% x D 15,722.22 13,776.75 13,422.75
F. HARGA SATUAN PEKERJAAN ( D + E ) 277,759.26 243,389.19 237,135.19
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-921

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 9.2.(1)
JENIS PEKERJAAN : Marka Jalan Termoplastik
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.6000 25,000.00 15,000.00 12,773.40 Rp12,773.40


2. Tukang (L02) jam 0.0750 31,250.00 2,343.75 2,067.92 Rp2,067.92
3. Mandor (L03) jam 0.0750 34,375.00 2,578.13 1,949.83 Rp1,949.83

JUMLAH HARGA TENAGA 19,921.88 16,791.15 Rp16,791.15

B. BAHAN Trinity Jurnal Best Price

1. Cat Marka Thermoplastic batang/m' 1.6704 150,000.00 250,557.01 143,652.69 Rp143,652.69


2. Glass Bead Kg 0.4635 160,000.00 74,160.00 13,256.10 Rp13,256.10

JUMLAH HARGA BAHAN 324,717.01 156,908.79 Rp156,908.79

C. PERALATAN Trinity Jurnal Best Price

1. Compressor Jam 0.0750 200,000.00 15,000.00 12,134.42 12,134.42


2. Dump Truck Jam 0.0750 290,000.00 21,750.00 29,717.93 21,750.00
3. Thermoplastic spreading machine Jam 0.0750 300,000.00 22,500.00 7,382.08 7,382.08
4. Alat Bantu Ls 1.0000 50,000.00 50,000.00 50,000.00

JUMLAH HARGA PERALATAN 109,250.00 99,234.43 91,266.50

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 453,888.89 272,934.36 264,966.44


E. OVERHEAD & PROFIT 6% x D 27,233.33 16,376.06 15,897.99
F. HARGA SATUAN PEKERJAAN ( D + E ) 481,122.22 289,310.42 280,864.42
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-793a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 9.2.(3a)
JENIS PEKERJAAN : Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
SATUAN PEMBAYARAN : Buah

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 0.9740 25,000.00 24,350.00 20,735.49 Rp20,735.49


2. Tukang (L02) jam 0.1299 31,250.00 4,059.37 3,581.64 Rp3,581.64
3. Mandor (L03) jam 0.0640 34,375.00 2,200.00 1,663.85 Rp1,663.85

JUMLAH HARGA TENAGA 30,609.38 25,980.98 Rp25,980.98

B. BAHAN Trinity Jurnal Best Price

1. Pelat Rambu Buah 1.0000 250,000.00 250,000.00 379,500.00 250,000.00


2. Pipa Galvanis Dia. 5" Batang 1.0000 2,750,000.00 2,750,000.00 1,170,000.00 1,170,000.00
Beton Fc 20 Mpa M3 0.0160 1,800,000.00 28,800.00 41,361.70 28,800.00

JUMLAH HARGA BAHAN 3,028,800.00 1,590,861.70 1,448,800.00

C. PERALATAN Trinity Jurnal Best Price

1. Dump Truck Jam 0.0846 700,000.00 59,201.74 33,511.48 33,511.48


2. Alat Bantu Jam 1.0000 200,000.00 200,000.00 200,000.00

JUMLAH HARGA PERALATAN 259,201.74 233,511.48 233,511.48

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,318,611.11 1,850,354.16 1,708,292.46


E. OVERHEAD & PROFIT 6% x D 199,116.67 111,021.25 102,497.55
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,517,727.78 1,961,375.41 1,810,790.01
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7619

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (19a)
JENIS PEKERJAAN : Pekerjaan Preboring Dia. 800 mm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 5.0000 25,000.00 125,000.00 106,445.00 Rp106,445.00


2. Tukang (L02) jam 1.5800 31,250.00 49,375.00 43,564.22 Rp43,564.22
3. Mandor (L03) jam 1.1900 34,375.00 40,906.25 30,937.27 Rp30,937.27

JUMLAH HARGA TENAGA 215,281.25 180,946.49 Rp180,946.49

B. BAHAN Trinity Jurnal Best Price

1. Beton Memadat Sendiri fc 20 MPa M3 1.1300 150,000.00 169,500.00 0.00 Rp169,500.00


2. Memasukan Besi Tulangan Kg 116.6670 1,500.00 175,000.50 0.00 Rp175,000.50
3. Pengeboran m' 2.1838 1,700,000.00 3,712,497.81 742,499.56 742,499.56

JUMLAH HARGA BAHAN 1,087,000.06 1,087,000.06 1,087,000.06

C. PERALATAN Trinity Jurnal Best Price

1. Welding Set Jam 0.2000 200,000.00 40,000.00 40,000.00 Rp40,000.00


2. Concrete Pump Jam 0.9950 2,500,000.00 2,487,442.66 2,487,442.66 Rp2,487,442.66
3. Mob-Demob Borepile Ls 1.0000 500,000.00 500,000.00 Rp500,000.00

JUMLAH HARGA PERALATAN 3,027,442.66 3,027,442.66 Rp3,027,442.66

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 4,329,723.97 4,295,389.22 4,295,389.22


E. OVERHEAD & PROFIT 6% x D 259,783.44 2,577.23 2,577.23
F. HARGA SATUAN PEKERJAAN ( D + E ) 4,589,507.41 4,297,966.45 4,297,966.45
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7619b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (19b)
JENIS PEKERJAAN : Pekerjaan Preboring Dia. 300 mm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Pekerja (L01) jam 5.0000 25,000.00 125,000.00 106,445.00 Rp106,445.00


2. Tukang (L02) jam 0.5823 31,250.00 18,196.88 16,055.34 Rp16,055.34
3. Mandor (L03) jam 0.1941 34,375.00 6,672.19 5,046.16 Rp5,046.16

JUMLAH HARGA TENAGA 149,869.06 127,546.50 Rp127,546.50

B. BAHAN Trinity Jurnal Best Price

1. Beton Memadat Sendiri fc 20 MPa M3 0.8475 150,000.00 127,125.00 0.00 Rp127,125.00


2. Memasukan Besi Tulangan Kg 87.5000 1,500.00 131,250.00 0.00 Rp131,250.00
3. Pengeboran m' 1.5653 1,700,000.00 2,660,988.76 532,197.75 Rp532,197.75

JUMLAH HARGA BAHAN 2,919,363.76 790,572.75 790,572.75

C. PERALATAN Trinity Jurnal Best Price

1. Welding Set Jam 0.2000 200,000.00 40,000.00 40,000.00 Rp40,000.00


2. Concrete Pump Jam 0.7462 2,500,000.00 1,865,581.99 1,865,581.99 Rp1,865,581.99
3. Mob-Demob Borepile Ls 1.0000 500,000.00 500,000.00 Rp500,000.00

JUMLAH HARGA PERALATAN 2,405,581.99 2,405,581.99 Rp2,405,581.99

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5,474,814.81 3,323,701.25 3,323,701.25


E. OVERHEAD & PROFIT 6% x D 328,488.89 1,994.22 1,994.22
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,803,303.70 3,325,695.47 3,325,695.47
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-77

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.7
JENIS PEKERJAAN :Pile Driving Analyzer (PDA) Test
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA Trinity Jurnal Best Price

1. Upah Tenaga Ahli (L01) Titik 2.0000 750,000.00 1,500,000.00 Rp750,000.00 Rp750,000.00

JUMLAH HARGA TENAGA 1,500,000.00 750,000.00

B. BAHAN Trinity Jurnal Best Price

1. PDA Test Ls 1.1000 10,000,000.00 11,000,000.00 Rp3,500,000 Rp3,500,000

JUMLAH HARGA BAHAN 11,000,000.00 3,500,000.00

C. PERALATAN Trinity Jurnal Best Price

1. Akomodasi Ls 1.0000 3,000,000.00 3,000,000.00 Rp4,950,000 3,000,000.00


2. Alat Bantu Ls 1.0000 500,000.00 500,000.00 500,000.00

JUMLAH HARGA PERALATAN 3,500,000.00 5,450,000.00 3,500,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 16,000,000.00 9,700,000.00 7,750,000.00


E. OVERHEAD & PROFIT 6% x D 960,000.00 582,000.00 465,000.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 16,960,000.00 10,282,000.00 8,215,000.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-7628

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : PERENCANAAN PEMBANGUNAN JEMBATAN GIRDER BAJA ( KOMPOSIT )


NAMA PAKET

KABUPATEN
ITEM PEMBAYARAN NO. : 7.6 (28)
JENIS PEKERJAAN :Pengujian Keutuhan Tiang dengan Pile Intergrated Test (PIT)
SATUAN PEMBAYARAN : Titik

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Upah Tenaga Ahli (L01) Titik 1.0000 750,000.00 750,000.00

JUMLAH HARGA TENAGA 750,000.00

B. BAHAN

1. PDA Test Ls 1.1000 1,500,000.00 1,650,000.00

JUMLAH HARGA BAHAN 1,650,000.00

C. PERALATAN

1. Akomodasi Ls 0.0598 3,000,000.00 179,537.04


2. Alat Bantu Ls 1.0000 500,000.00 500,000.00

JUMLAH HARGA PERALATAN 679,537.04

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,079,537.04


E. OVERHEAD & PROFIT 6% x D 184,772.22
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,264,309.26
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
PEKERJAAN : PERENCANAAN PEMBANGUNAN JEMBATAN (PONDASI PANCANG)
DI LOKASI : SUNGAI BATANG TEMBESI, MUARA KETALO
PANJANG : 160 M'(Lebar Jalan 8.0 M')
TAHUN : 2023

No. Mata
Pembayaran
Satuan Bobot (%) Hari M-1 M-2 M-3 M-4 M-5 M-6 M-7
W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 W-11 W-12 W-13 W-14 W-15 W-16 W-17 W-18 W-19 W-20 W-21 W-22 W-23 W-24 W-25 W-26
a c

DIVISI 1. UMUM
1.2 Mobilisasi LS 2.827% 450.00 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456%
1.19 Keselamatam dan Kesehatan Kerja LS 0.158% 450.00 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025%

DIVISI 3. PEKERJAAN TANAH


3.1.3 Galian Struktur dengan kedalaman 0 - 2 meter M3 0.018% 21.00 0.0060% 0.0060% 0.0060%
3.2.2 Galian Struktur dengan kedalaman 2 - 4 meter M3 0.023% 21.00 0.0076% 0.0076% 0.0076%
3.3.(1) Penyiapan Badan Jalan M2 0.000%

DIVISI 5. PERKERASAN BERBUTIR


5.1.2 Lapis Pondasi Agregat Kelas B M3 0.000%

DIVISI 7. STRUKTUR
7.1 (5) a Beton Fc' 35 Mpa M3 5.913% 112.00 0.370% 0.370% 0.370% 0.370% 0.370% 0.370% 0.370%
7.1 (5) b Beton Fc' 30 Mpa M3 8.729% 294.00 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078%
7.1 (6) Beton Fc' 10 Mpa M3 0.016% 14.00 0.0080% 0.0080%
7.3 (3) Baja Tulangan Kg 13.499% 294.00 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214%
7.4 (1) a Penyedia Pipa Baja Dia. 4" Kg 0.338% 133.00 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178% 0.0178%
7.4 (3) a Penyediaan Baja Struktur Jembatan Kg 20.963% 112.00 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102% 1.3102%
7.5 (1) Pemasangan Baja Struktur Jembatan Kg 6.551% 175.00 0.2620% 0.2620% 0.2620% 0.2620% 0.2620%
7.5 (2) Pengangkutan Bahan Jembatan Kg 3.013% 28.00 0.7534% 0.7534% 0.7534% 0.7534%
7.6 (8) a Penyediaan Tiang Pancang Baja Diameter 300 mm dengan tebal 10 mm M1 1.427% 56.00 0.178% 0.178% 0.178% 0.178% 0.178% 0.178% 0.178% 0.178%
7.6 (8) b Penyediaan Tiang Pancang Baja Diameter 400 mm dengan tebal 12 mm M1 0.936% 56.00 0.117% 0.117% 0.117% 0.117% 0.117% 0.117% 0.117% 0.117%
7.6 (8) c Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm M1 1.772% 56.00 0.2215% 0.2215% 0.2215% 0.2215% 0.2215% 0.2215% 0.2215% 0.2215%
7.6 (8) d Penyediaan Tiang Pancang Baja Diameter 800 mm dengan tebal 16 mm M1 20.306% 56.00 2.538% 2.538% 2.538% 2.538% 2.538% 2.538% 2.538% 2.538%
7.6 (14) a Pemancangan Tiang Pancang Baja Diameter 300 mm (Fender) M1 0.492% 63.00 0.0546% 0.0546% 0.0546% 0.0546% 0.0546% 0.0546% 0.0546% 0.0546% 0.0546%
7.6 (14) b Pemancangan Tiang Pancang Baja Diameter 400 mm M1 0.290% 49.00 0.0414% 0.0414% 0.0414% 0.0414% 0.0414% 0.0414% 0.0414%
7.6 (14) c Pemancangan Tiang Pancang Baja Diameter 600 mm M1 0.432% 49.00 0.0617% 0.0617% 0.0617% 0.0617% 0.0617% 0.0617% 0.0617%
7.6 (14) d Pemancangan Tiang Pancang Baja Diameter 800 mm M1 0.277% 133.00 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146% 0.0146%
7.6 (19) a Pekerjaan Preboring Tiang Pancang Baja Dia. 800 mm M1 6.491% 133.00 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416% 0.3416%
7.6 (19) a Pekerjaan Preboring Tiang Pancang Baja Dia. 300 mm M1 2.367% 133.00 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246% 0.1246%
7.7 Pile Driving Analyzer (PDA) Test Titik 0.026% 35.00
Pengujian Non-Destructive Test Ultrasonic Test (UT) - (10% Pengetesan) Kg 0.105% 112.00 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066% 0.0066%
Complete Joint Penetration (CJP) Kg 1.638% 112.00 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024% 0.1024%
7.6 (21) Tambahan Biaya bila tiang bor dikerjakan di air m'
7.6 (28) Pengujian keutuhan Tiang dengan Pile Intergrated Test (PIT) bh 0.272% 35.00
7.11 (7) Sambungan Siar Muai Expansion m 0.207% 7.00
7.12 (2) Landasan Elastomerik karet alam berlapis baja bh 0.111% 7.00
7.14 (1) Papan Nama Jembatan bh 0.001% 21.00
7.16 (1) Dreck Drain bh 0.109% 14.00
7.16 (3a) Pipa Drainase PVC dia. 150mm m' 0.072% 21.00
Sewa Tongkang/Tugboat ls 0.000%

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


8.4.(1) Pengadaan dan Pemasangan Beam Guardrail M1 0.611% 28.00

DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN LAIN


9.2 (3a) Rambu Jalan Tunggal bh 0.010% 21.00

100.000%

TOTAL PROGRESS PLAN 0.048% 3.674% 5.093% 5.093% 5.107% 5.107% 5.161% 5.148% 5.176% 2.619% 2.611% 2.611% 2.611% 2.611% 2.611% 2.495% 2.495% 3.248% 1.829% 2.199% 2.199% 1.708% 1.708% 1.708% 1.708% 1.708%
KOMULATIF PROGRESS PLAN 0.048% 3.722% 8.815% 13.908% 19.014% 24.121% 29.282% 34.430% 39.606% 42.225% 44.837% 47.448% 50.060% 52.671% 55.283% 57.778% 60.273% 63.521% 65.351% 67.549% 69.748% 71.456% 73.164% 74.871% 76.579% 78.286%

Dibuat Oleh;
PT. TRNITY GLOBAL PERSADA

( ENDANG NURHAENUDIN )
Project Director
PROJECT JEMBATAN PT. SAROLANGUN KETALO COAL
M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15
W-27 W-28 W-29 W-30 W-31 W-32 W-33 W-34 W-35 W-36 W-37 W-38 W-39 W-40 W-41 W-42 W-43 W-44 W-45 W-46 W-47 W-48 W-49 W-50 W-51 W-52 W-53 W-54 W-55 W-56 W-57 W-58 W-59 W-60 W-61 W-62

0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456% 0.0456%
0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025% 0.0025%

0.370% 0.370% 0.370% 0.370% 0.370% 0.370% 0.370% 0.370% 0.370%


0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078% 0.2078%

0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214% 0.3214%
0.0178% 0.0178%

0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620% 0.2620%

0.0146% 0.0146%
0.3416% 0.3416%
0.1246% 0.1246%
0.0051% 0.0051% 0.0051% 0.0051% 0.0051%

0.0544% 0.0544% 0.0544% 0.0544% 0.0544%


0.207%
0.1110%
0.00071% 0.00071%
0.0547% 0.0547%
0.0240% 0.0240% 0.0240%

0.1527% 0.1527% 0.1527% 0.1527%

0.0033% 0.0033% 0.0033%

1.767% 1.767% 1.268% 1.268% 1.268% 1.209% 1.209% 1.209% 1.209% 0.310% 0.310% 0.310% 0.310% 0.310% 0.310% 0.310% 0.310% 0.310% 0.310% 0.421% 0.785% 0.577% 0.577% 0.577% 0.577% 0.577% 0.632% 0.632% 0.049% 0.049% 0.072% 0.072% 0.225% 0.204% 0.204% 0.204%
80.053% 81.821% 83.089% 84.358% 85.626% 86.835% 88.044% 89.253% 90.462% 90.772% 91.082% 91.392% 91.703% 92.013% 92.323% 92.633% 92.943% 93.253% 93.564% 93.985% 94.769% 95.347% 95.924% 96.502% 97.079% 97.656% 98.288% 98.920% 98.969% 99.018% 99.090% 99.163% 99.387% 99.592% 99.796% 100.000%