Anda di halaman 1dari 24

GAMBAR RENCANA (SHOPDRAWING)

PEMBANGUNAN BARAK PEKERJA


LOKASI :JL. SRIWIJAYA RIDGE 2, KEL.BRAMBAKEN
DISTRIK SAMOFA KABUPATEN BIAK NUMFOR- PAPUA

GAMBAR TAMPAK DEPAN


Skala 1 : 150

GAMBAR RENCANA BANGUNAN BARAK PEKERJA


PERENCANA :
KONSULTAN PERENCANA

1 2 3 4 5 6 7 8 9
NAMA PEKERJAAN

A
PEMBANGUNAN GEDUNG
AREA BANGUNAN AREA BANGUNAN AREA BANGUNAN BARAK
MILIK ORANG MILIK ORANG MILIK ORANG AREA KERJA

A
K.M
+0.35
LOKASI:
1 2 3 4 5 6 6 5 4 3 2 1

300
7 7
8 8 JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
9 9
B 10
K.M 10 B
AREA KERJA AREA KERJA +0.35 DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

600
11 11
B 12
+0.40 +0.40
12

700
13
K.M 13

150
14
15 +0.35
14
15 SHOPDRAWING

300
16 16
17 17
18 18
DIAJUKAN

150
19 K.M 19
+0.35

C PEMILIK RUMAH

100
TERAS TERAS TERAS TERAS
+0.35 +0.35 +0.35 +0.35
D
JALAN TAPAK JALAN TAPAK
+0.30 +0.30

200 200
JIMMY C. R. KAPISSA
MENYETUJUI
400 400 400 400 400 400 400 400
KEPALA BIDANG CIPTA KARYA DINAS PUPR
3200 KABUPATEN BIAK NUMFOR

DENAH BARAK LANTAI 1


Skala 1 : 175
A

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
1 2 3 4 5 6 7 8 9
A KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

250
1 2 3 4 5 6 6 5 4 3 2 1

7
8
7
8
FRANS P.F WATIMENA,SE
9 K. TIDUR K. TIDUR K. TIDUR K. TIDUR K. TIDUR K. TIDUR K. TIDUR K. TIDUR 9 NIP. 19810223 200605 1 001

500
B 10
+3.90 +3.90 +3.90 +3.90 +3.90 +3.90 +3.90 +3.90 10 B
11 11
B AHLI

650
12 12
13 13

250
14 14
15
16
15
16
ARSITEK STRUKTUR DRAFTER
17 17
18 18
19 19

150
BALKON BALKON BALKON BALKON
C +3.90 +3.90 +3.90 +3.90

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING
400 400 400 400 400 400 400 400

3200
GAMBAR DENAH RENCANA
DENAH BARAK LANTAI 2 GEDUNG BARAK LT.1 & 2
Skala 1 : 175

A
SKALA TAHUN NO.DWG JUMLAH

1:175 2023 001 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH

JIMMY C. R. KAPISSA
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

FRANS P.F WATIMENA,SE


NIP. 19810223 200605 1 001

AHLI
GAMBAR TAMPAK DEPAN ARSITEK STRUKTUR DRAFTER
Skala 1 : 150

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

GAMBAR TAMPAK DEPAN


GEDUNG BARAK KERJA

SKALA TAHUN NO.DWG JUMLAH

1:150 2023 002 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH

JIMMY C. R. KAPISSA
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

FRANS P.F WATIMENA,SE


NIP. 19810223 200605 1 001

AHLI
ARSITEK STRUKTUR DRAFTER

GAMBAR TAMPAK BELAKANG


Skala 1 : 150

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

GAMBAR TAMPAK BELAKANG


GEDUNG BARAK KERJA

SKALA TAHUN NO.DWG JUMLAH

1:150 2023 003 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH

JIMMY C. R. KAPISSA
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

FRANS P.F WATIMENA,SE


NIP. 19810223 200605 1 001

AHLI
ARSITEK STRUKTUR DRAFTER

TAMPAK SAMPING KANAN TAMPAK SAMPING KIRI


Skala 1 : 100 Skala 1 : 100

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

GAMBAR TAMPAK
SAMPING KIRI & KANAN

SKALA TAHUN NO.DWG JUMLAH

1:100 2023 004 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN
A B C D
PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

ELV. LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

KUDA-KUDA I
+ 9.56
SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH

DINDING KAYU

25°
KUDA-KUDA II
+ 6.90
JIMMY C. R. KAPISSA
+ 6.29
RING BALOK KAYU 10/10 MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
LANTAI KABIN KAYU tb.2cm
KABUPATEN BIAK NUMFOR

K. TIDUR
+4.19
+ 4.00
+ 3.90 KUDA-KUDA II

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

+ 1.90 MENGETAHUI
HANDLLE TANGGA
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
GROUND RUANG KABUPATEN BIAK NUMFOR

+ 0.40
± 0.00

- 0.70 PAS. BATA ROLAG


FRANS P.F WATIMENA,SE
- 1.15 NIP. 19810223 200605 1 001

URUGAN PASIR tb. 5cm AHLI


PONDASI BATU KALI 60x60
RABAT BETON tb. 12cm ARSITEK STRUKTUR DRAFTER
PONDASI FOOT PLAT FP 80x80
SPESI FINISHING LANTAI tb. 3cm
LANTAI KERJA tb. 10cm
FINISHING LANTAI KABIN PLESTER

250 250 150 ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK


300 300 TITTLE DRAWING
650

GAMBAR
T. POTONGAN A-A TAMPAK POTONGAN A-A
Skala 1 : 100

SKALA TAHUN NO.DWG JUMLAH

1:100 2023 005 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH
PAPAN RUTER
ELV.
1 2 3 4 5 6 7 8 9
KUDA-KUDA 1/2 SEGITIGA
IKATAN ANGIN uk.5/10
+ 9.56

GORDING uk.5/10
JIMMY C. R. KAPISSA
MENYETUJUI
LISPLANK
+ 6.90
KEPALA BIDANG CIPTA KARYA DINAS PUPR
DINDING KAYU KABUPATEN BIAK NUMFOR
+ 6.29
RING BALOK KAYU 10/10 KOLOM KAYU uk. 10/10
LANTAI KABIN KAYU tb.2cm

+ 4.00
+ 3.90
BALOK LATIUW BL 15x20cm
ELV. Plafond ELV. Plafond ELV. Plafond ELV. Plafond
+2.93 +2.93 +2.93 +2.93
ELV. Plafond
+3.40
+ 2.65 TANGGA KAYU
KOLOM 20x25
BALOK PENGAPIT 5/10 BALOK B1 15x30cm YAN SARTHEIS KARUBABA, S.T.
BALOK GELAGAR 5/7 NIP. 19790606 200909 1 003
GROUND R. KERJA R. KERJA R. KERJA R. KERJA R. KERJA R. KERJA R. KERJA TOILET
+ 0.40
+0.40 +0.40 +0.40 +0.40 +0.40 +0.40 +0.40 +0.35 MENGETAHUI
± 0.00
PAS. 1/2 BATA
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
- 0.70 RUANG KABUPATEN BIAK NUMFOR
PAS. BATA TRASHRAM 1:3 PS
- 1.15
URUGAN TANAH
SLOOF SL 15x25 cm
TANAH ASLI PONDASI BATU KALI 60x60
PONDASI FOOT PLAT FP 80x80
URUGAN PASIR tb. 5cm
LANTAI KERJA tb. 10cm
RABAT BETON tb. 12cm
SPESI FINISHING LANTAI tb. 3cm
FINISHING LANTAI KABIN PLESTER FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001

400 400 400 400 400 400 400 400 AHLI


3200 ARSITEK STRUKTUR DRAFTER

T. POTONGAN B-B
Skala 1 : 175

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

GAMBAR
TAMPAK POTONGAN B-B

SKALA TAHUN NO.DWG JUMLAH

1:175 2023 006 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN
1 2 3 4 5 6 7 8 9
PEMBANGUNAN GEDUNG
BARAK
AREA BANGUNAN AREA BANGUNAN AREA BANGUNAN
AREA KERJA
MILIK ORANG MILIK ORANG MILIK ORANG

LOKASI:
A
FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80
80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

300
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
FP 80 FP 80 FP 80
80x80x30 80x80x30 80x80x30

600
B SHOPDRAWING

700
150
DIAJUKAN

300
FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 FP 80 PEMILIK RUMAH

150
80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30 80x80x30

100
D

JIMMY C. R. KAPISSA

200
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
400 400 400 400 400 400 400 400 KABUPATEN BIAK NUMFOR
FP 80
3200 QTY: 23

DENAH RENCANA FOOTPLAT 80


Skala 1 : 175

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003
TUL.ATAS FP

MENGETAHUI
40

Ø12- 150mm 20

KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN


80

2
Ø16- 180mm

RUANG KABUPATEN BIAK NUMFOR

25
TUL.BAWAH FP
Ø10- 150mm

4 - Ø16

DET. KOLOM FP 80
2 T. ATAS FP 80

25 20

GROUND
+ 0.40
Ø10- 150mm FRANS P.F WATIMENA,SE
4 - Ø16
NIP. 19810223 200605 1 001

130
Ø12- 150mm
AHLI
5

- 0.60
- 0.65
ARSITEK STRUKTUR DRAFTER
20

30

- 0.85
- 0.90 Ø16- 180mm
5

TAMPAK POTONGAN
80

TAMPAK SAMPING

DET.STRUCTURE FOOTPLAT FP 80 ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK


CODE FOOTPLAT FP 80
QTY 023 TITTLE DRAWING
DIMENSION 800x800x300
SYMBOL

FP 80 GAMBAR DENAH RENCANA


QTY: 23
FOOTPLAT FP-80

DETAIL STRUKTUR FOOTPLAT FP80


Skala 1 : 70 SKALA TAHUN NO.DWG JUMLAH

1:175 2023 007 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

TUL.ATAS FP NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK

40
Ø12- 150mm 20 AREA KERJA

80

2
LOKASI:

Ø16- 180mm
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

25
TUL.BAWAH FP DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
Ø10- 150mm

4 - Ø16 SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH

2 DET. KOLOM FP 80
Skala 1 : 20

TAMPAK ATAS FP 80
Skala 1 : 20 JIMMY C. R. KAPISSA
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

25 20

YAN SARTHEIS KARUBABA, S.T.


GROUND NIP. 19790606 200909 1 003

+ 0.40 MENGETAHUI
Ø10- 150mm KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

4 - Ø16

130
FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001

AHLI
Ø12- 150mm ARSITEK STRUKTUR DRAFTER

5
- 0.60
- 0.65

20

30
- 0.85
- 0.90 Ø16- 180mm
ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

5
TITTLE DRAWING

TAMPAK POTONGAN DETAIL PONDASI


Skala 1 : 20 80
FOOTPLAT FP 80

TAMPAK SAMPING
Skala 1 : 20 SKALA TAHUN NO.DWG JUMLAH

1:20 2023 008 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

1 2 3 4 5 6 7 8 9 PEMBANGUNAN GEDUNG
BARAK
AREA KERJA
AREA BANGUNAN AREA BANGUNAN AREA BANGUNAN
SLOOF SL 15x25 cm
MILIK ORANG MILIK ORANG MILIK ORANG
LOKASI:
A
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

300
80
SHOPDRAWING

600
B 60

700
DIAJUKAN

150
30

300
PEMILIK RUMAH

150
C

100
D
PAS. BATU GUNUNG
PAS. ANSTAMPENG tb.15cm JIMMY C. R. KAPISSA
PAS. BATA ROLAG
15x30x9cm MENYETUJUI
200 200 KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR
400 400 400 400 400 400 400 400

3200

DENAH RENCANA PONDASI BATU GUNUNG


Skala 1 : 175

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
60 KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR
30
KOLOM K1 20/25
FINISHING PAS. KERAMIK uk.40x40

SLOOF SL 15/25 SPESI tb.3cm


+ 0.15
PASIR URUG tb.5cm RABAT BETON tb.10cm FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001
PAS. BATA ROLAG
60

GROUND AHLI
85

PERMUKAAN TANAH ASLI


+ 0.40
+ 0.20
ARSITEK STRUKTUR DRAFTER
15

±0.00
5
5

80 - 0.45 TANAH URUG


ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
- 0.70
PAS. BATU GUNUNG
TITTLE DRAWING
DET. UKURAN PONDASI B. GUNUNG
Skala 1 : 35 PLAT LANTAI KERJA tb.5cm PAS. BATU KOSONG tb20 cm

GAMBAR DENAH RENCANA


PAS. PASIR URUG tb.5cm
PONDASI BATU GUNUNG
& DETAILNYA

DETAIL PONDASI BATU GUNUNG SKALA TAHUN NO.DWG JUMLAH


Skala 1 : 35

1:175 2023 009 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

1 2 3 4 5 6 7 8 9
NAMA PEKERJAAN

SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL


PEMBANGUNAN GEDUNG
A BARAK
ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40
SLOOF SL AREA KERJA
ELV. +0.40

300
LOKASI:

SLOOF SL

SLOOF SL

SLOOF SL

SLOOF SL

SLOOF SL

SLOOF SL

SLOOF SL
ELV. +0.40

ELV. +0.40

ELV. +0.40

ELV. +0.40

ELV. +0.40

ELV. +0.40

ELV. +0.40
SLOOF SL

600
B JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

700
ELV. +0.40

150
SLOOF SL

DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA


ELV. +0.40

300
SHOPDRAWING

150
SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL SLOOF SL
C DIAJUKAN

100
ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40 ELV. +0.40
PEMILIK RUMAH
D

200 200

400 400 400 400 400 400 400 400 JIMMY C. R. KAPISSA
3200 MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR
DENAH RENCANA SLOOF SL 15/25
Skala 1 : 150

1/4 1/2 1/4


TUMPUAN LAPANGAN TUMPUAN
2 3 TUL. ATAS 2 - Ø12
BEUGEL Ø8- 150 BEUGEL Ø8- 200 YAN SARTHEIS KARUBABA, S.T.
NIP. 19790606 200909 1 003
GROUND
+ 0.40 MENGETAHUI

25
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

1 - Ø12
TUL. BAWAH 2 - Ø12

100 200 100


FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001
400
AHLI
DIMENSION 150x250mm ARSITEK STRUKTUR DRAFTER
POSITION TUMPUAN LAPANGAN TUMPUAN DET. POTONGAN SLOOF AS A BENTANG (2 - 3)
Skala 1 : 30
MUTU BETON 15
K175
25

SLOOF SL ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK


2

15/25 TITTLE DRAWING

TUL. ATAS 2- Ø12 3- Ø12 2- Ø12 GAMBAR DENAH RENCANA


TUL. BAWAH 3- Ø12 2- Ø12 3- Ø12 SLOOF SL LT.1
TUL. PINGGANG - & DETAILNYA
BEGEL Ø8 - 150 Ø8 - 200 Ø8 - 150
SKALA TAHUN NO.DWG JUMLAH
DETAIL. PENAMPANG SLOOF SL 15/25
Skala 1 : 30
1:150 2023 010 022
CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
1 2 3 4 5 6 7 8 9 BARAK
AREA KERJA
K1 K1 K1 K1 K1 K1 K1 K1 K1 K1
20x25 20x25 20x25 20x25 20x25 20x25 20x25 20x25 20x25 20x25
A LOKASI:
K2 K2
15x15 15x15 JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

300
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
K1 K1 K1
20x25 20x25 20x25
SHOPDRAWING

600
B

700
150
K2 K2 DIAJUKAN
15x15 15x15

300
PEMILIK RUMAH

150
K1 K1 K1 K1 K1 K1 K1 K1 K1 K1
20x25 20x25 20x25 20x25 20x25 20x25 20x25 20x25 20x25 20x25
C

100
D
JIMMY C. R. KAPISSA
MENYETUJUI
200 200
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR
400 400 400 400 400 400 400 400

3200

DENAH RENCANA KOLOM LT.1


Skala 1 : 150 K1 20/25 TOP EELV. +3.90
K2 15/15 TOP EELV. +3.90 YAN SARTHEIS KARUBABA, S.T.
NIP. 19790606 200909 1 003

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

FRANS P.F WATIMENA,SE


NIP. 19810223 200605 1 001
DIMENSION 350x350mm
DIMENSION 150x150mm NAME KOLOM K1 20/25 AHLI
NAME KOLOM K2 15/15 MUTU BETON ARSITEK STRUKTUR DRAFTER
MUTU BETON K175
K175 15 20

K
2

25
K

2
15

15/15
ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
20/25 TITTLE DRAWING
TULANGAN 4 - Ø12
BEGEL Ø8 - 150 TULANGAN 4 - Ø16
BEGEL Ø10 - 150 GAMBAR DENAH RENCANA
KOLOM LT.1
DETAIL. KOLOM K2
Skala 1 : 25 DETAIL. KOLOM K1 & DETAILNYA
Skala 1 : 25

SKALA TAHUN NO.DWG JUMLAH

1:150 2023 011 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

4 5 6 7 8 9 NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA
BL 15x20
A LOKASI:
ELV. +2.00

BL 15x20

BL 15x20
ELV. +2.00

ELV. +2.00
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

300
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING
BL 15x20

600
DIAJUKAN
B

700
ELV. +2.00 PEMILIK RUMAH

150
BL 15x20

BL 15x20
ELV. +2.00

ELV. +2.00

300
150
JIMMY C. R. KAPISSA
BL 15x20
C MENYETUJUI

100
ELV. +2.00 KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR
D

200 200
SYMBOL YAN SARTHEIS KARUBABA, S.T.
NIP. 19790606 200909 1 003
400 400 400 400 400 BL 15x20 MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
BALOK LATIUW TOP ELV. +2.00 RUANG KABUPATEN BIAK NUMFOR

DENAH RENCANA BALOK BL LT.1


Skala 1 : 100

FRANS P.F WATIMENA,SE


NIP. 19810223 200605 1 001
DIMENSION 150x200mm
NAME BALOK LATIUW BL AHLI
MUTU BETON ARSITEK STRUKTUR DRAFTER
K175 15

BL
3
15/20 ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
20

TITTLE DRAWING

GAMBAR DENAH RENCANA


TULANGAN 4 - Ø12 BALOK BL LT.1
BEGEL Ø8 - 150 & DETAILNYA

SKALA TAHUN NO.DWG JUMLAH


DETAIL BALOK BL 15/20
Skala 1 : 20 1:100 2023 012 022
CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

1 2 3 4 5 6 7 8 9 PEMBANGUNAN GEDUNG
BARAK
AREA KERJA
BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1
A
ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90
LOKASI:
BALOK B1

ELV. +3.90

300
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

BALOK B1

BALOK B1

BALOK B1

BALOK B1

BALOK B1

BALOK B1

BALOK B1
ELV. +3.90

ELV. +3.90

ELV. +3.90

ELV. +3.90

ELV. +3.90

ELV. +3.90

ELV. +3.90
BALOK B1

600
B
SHOPDRAWING

700
ELV. +3.90

150
BALOK B1

ELV. +3.90

DIAJUKAN

300
150
PEMILIK RUMAH
BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1 BALOK B1
C

100
ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90 ELV. +3.90

JIMMY C. R. KAPISSA
200 200 MENYETUJUI
SYMBOL
400 400 400 400 400 400 400 400 KEPALA BIDANG CIPTA KARYA DINAS PUPR
BL 15x20 KABUPATEN BIAK NUMFOR
3200 BALOK LATIUW TOP ELV. +3.90

DENAH RENCANA BALOK B1 15/30


Skala 1 : 150

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

DIMENSION 150x300mm
POSITION TUMPUAN LAPANGAN TUMPUAN
MUTU BETON 15
K175
FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001

BALOK B1 AHLI
30

2
ARSITEK STRUKTUR DRAFTER
15/30
TUL. ATAS 2- Ø16 3- Ø16 2- Ø16
TUL. BAWAH 3- Ø16 2- Ø16 3- Ø16
TUL. PINGGANG -
BEGEL ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
Ø10 - 150 Ø10 - 200 Ø10 - 150
TITTLE DRAWING
DETAIL. BALOK B1
Skala 1 : 30

GAMBAR DENAH RENCANA


BALOK B1
& DETAILNYA

SKALA TAHUN NO.DWG JUMLAH

1:150 2023 013 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

1 2 3 4 5 6 7 8 9

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
A
BARAK
AREA KERJA

250

500
LOKASI:
B

650
250
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING

150
C
DIAJUKAN
D PEMILIK RUMAH

SAMBUNGAN JEPIT POJOK "1"

400 400 400 400 400 400 400 400


JIMMY C. R. KAPISSA
3200
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
DENAH BALOK LANTAI PENGAPIT KOLOM BW1 5/10, Lenght 3meters TOP ELV. +4.00 KABUPATEN BIAK NUMFOR
Skala 1 : 150
Wood Class 2

SAMBUNGAN PENGAPIT SIMP. EMPAT

SAMBUNGAN PENGAPIT SIMP. TIGA


YAN SARTHEIS KARUBABA, S.T.
NIP. 19790606 200909 1 003
SAMBUNGAN PENGAPIT POJOK 1
MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

BALOK KAYU PENGAPIT KOLOM


ARAH SAMB. SUMBU Y
KOLOM BALOK KAYU 10/10 FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001

AHLI
SAMB. BIBIR MIRING BERKAIT ARSITEK STRUKTUR DRAFTER

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

BALOK KAYU PENGAPIT KOLOM


ARAH SAMB. SUMBU X GAMBAR DENAH RENCANA
BALOK KAYU PENGAPIT
KOLOM BALOK
SAMBUNGAN JEPIT SIMP EMPAT

SAMBUNGAN JEPIT SIMP. TIGA TAMPAK PROYEKSI DIMITRI SKALA TAHUN NO.DWG JUMLAH
Skala 1 : 150
1:150 2023 014 022
SAMBUNGAN JEPIT POJOK "1"
CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

5 KOLOM BALOK KAYU 10/10


SHOPDRAWING
SAMB. BIBIR MIRING BERKAIT 4 DIAJUKAN
PEMILIK RUMAH
3

2 A

JIMMY C. R. KAPISSA
B
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
SAMBUNGAN PENGAPIT SIMP EMPAT KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

SAMBUNGAN PENGAPIT SIMP. TIGA BALOK KAYU PENGAPIT KOLOM uk. 5/10

FRANS P.F WATIMENA,SE


SAMBUNGAN PENGAPIT POJOK "1" NIP. 19810223 200605 1 001

AHLI
DETAIL BAGIAN-BAGIAN BALOK PENGAPIT ARSITEK STRUKTUR DRAFTER
Skala 1 : 150

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

RENCANA SAMBUNGAN BALOK


PENGEPIT KOLOM BALOK

SKALA TAHUN NO.DWG JUMLAH

1:100 2023 015 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA
1 BALOK PENGAPIT 5/10
ARAH SUMB. Y

KOLOM BALOK 10/10


2x MUR-BAUT BAJA
M10-L 25mm NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
KOLOM KAYU 10/10 BARAK

5
7,5
AREA KERJA
KOLOM KAYU 10/10

20

20
10
5
LOKASI:

7,5

5
BALOK PENGAPIT 5/10 JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
ARAH SUMB.X DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
D BALOK PENGAPIT 5/10
ARAH SUMB. X

BALOK PENGAPIT 5/10


SHOPDRAWING
ARAH SUMB.Y
DIAJUKAN
"A" 7,5 5 7,5
PEMILIK RUMAH
20 PROYEKSI DIMITRI 1
Skala 1 : 35

DETAIL "A"
TAMPAK ATAS Skala 1 : 10
Skala 1 : 20

JIMMY C. R. KAPISSA
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

2x MUR-BAUT BAJA
M10-L 25mm
BALOK PENGAPIT 5/10
+ 4.00 ARAH SUMB.X
2x MUR-BAUT BAJA
BALOK PENGAPIT 5/10
M10-L 25mm ARAH SUMB.Y
2,5
5

"B" 2x MUR-BAUT BAJA


10

YAN SARTHEIS KARUBABA, S.T.


5

M10-L 25mm NIP. 19790606 200909 1 003


BALOK PENGAPIT 5/10
ARAH SUMB. Y
2,5 2,5 BALOK PENGAPIT 5/10
ARAH SUMB. X MENGETAHUI
TAMPAK DEPAN
Skala 1 : 20 KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
5 10 5
RUANG KABUPATEN BIAK NUMFOR
20

KOLOM KAYU 10/10


DETAIL "B"
Skala 1 : 15 2x MUR-BAUT BAJA
M10-L 25mm
FRANS P.F WATIMENA,SE
10 NIP. 19810223 200605 1 001
KOLOM BALOK 10/10 AHLI
ARSITEK STRUKTUR DRAFTER
2x MUR-BAUT BAJA
M10-L 25mm KOLOM K1 20/25
BALOK B1 15/30
"C" BALOK PENGAPIT 5/10
ARAH SUMB. X
10

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK


5
10

TITTLE DRAWING
5

BALOK PENGAPIT 5/10


2,5

ARAH SUMB. Y

2x MUR-BAUT BAJA
20 M10-L 25mm 2,5 2,5
PROYEKSI DIMITRI 2 DETAIL SAMBUNGAN
Skala 1 : 150 PENGAPIT POJOK 1
TAMPAK SAMPING KIRI
Skala 1 : 20 5 10 5
20
SKALA TAHUN NO.DWG JUMLAH
DETAIL "C"
Skala 1 : 10
1:30 2023 016 022
CODE DRAW: ARS A3
KONSULTAN PERENCANA
BALOK PENGAPIT 5/10
ARAH SUMB. Y
2x MUR-BAUT BAJA
M10-L 25mm
KOLOM BALOK 10/10
NAMA PEKERJAAN
1
PEMBANGUNAN GEDUNG

5
7,5
BARAK
AREA KERJA

20

20
10
5
BALOK PENGAPIT 5/10
ARAH SUMB.Y
KOLOM KAYU 10/10

7,5

5
LOKASI:
KOLOM KAYU 10/10 BALOK PENGAPIT 5/10
ARAH SUMB. X JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
BALOK PENGAPIT 5/10
B ARAH SUMB.X
SHOPDRAWING
7,5 5 7,5
"A" BALOK PENGAPIT 5/10 DIAJUKAN
BALOK PENGAPIT 5/10 20
ARAH SUMB.X ARAH SUMB.Y PEMILIK RUMAH

TAMPAK ATAS DETAIL "A"


Skala 1 : 10
Skala 1 : 30
+ 6.90

PROYEKSI DIMITRI 1
Skala 1 : 30
JIMMY C. R. KAPISSA
MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR

10
5
KABUPATEN BIAK NUMFOR
BALOK PENGAPIT 5/10
+ 4.00
ARAH SUMB.X

2x MUR-BAUT BAJA
"B"
M10-L 25mm
10
TAMPAK DEPAN
Skala 1 : 30 BALOK PENGAPIT 5/10
KOLOM KAYU 10/10 YAN SARTHEIS KARUBABA, S.T.
ARAH SUMB.Y
NIP. 19790606 200909 1 003

2x MUR-BAUT BAJA MENGETAHUI


M10-L 25mm 2x MUR-BAUT BAJA
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
2,5

M10-L 25mm
RUANG KABUPATEN BIAK NUMFOR
5
10
5

KOLOM KAYU 10/10


BALOK PENGAPIT 5/10 2,5 2,5 BALOK PENGAPIT 5/10
ARAH SUMB. Y ARAH SUMB. X FRANS P.F WATIMENA,SE
TUL. STRUKTUR B1 NIP. 19810223 200605 1 001

5 5 AHLI
20 ARSITEK STRUKTUR DRAFTER

DETAIL "B"
Skala 1 : 10

KOLOM BALOK 10/10


BALOK PENGAPIT 5/10
10 BALOK PENGAPIT 5/10
ARAH SUMB. X
ARAH SUMB. Y
ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
BALOK B1 15/30
TITTLE DRAWING
5
10
5

"C"
KOLOM K1 20/25
2,5

DETAIL SAMBUNGAN
10

2x MUR-BAUT BAJA
2,5 2,5 M10-L 25mm PENGAPIT SIMP. TIGA

20
5 10 5
PROYEKSI DIMITRI 2
20 Skala 1 : 30 SKALA TAHUN NO.DWG JUMLAH
TAMPAK SAMPING KIRI
Skala 1 : 20
DETAIL "C" 1:30 2023 017 022
Skala 1 : 10

CODE DRAW: ARS A3


KONSULTAN PERENCANA

4 BALOK PENGAPIT 5/10 KOLOM KAYU 10/10


ARAH SUMB.Y
NAMA PEKERJAAN
BALOK PENGAPIT 5/10
ARAH SUMB.X
PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
KOLOM KAYU 10/10
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
SAMB. BIBIR MIRING BERKAIT
SHOPDRAWING
B PROYEKSI DIMITRI 1
Skala 1 : 30 DIAJUKAN
PEMILIK RUMAH

"A" BALOK PENGAPIT 5/10


ARAH SUMB.X
SAMB. BIBIR MIRING BERKAIT

2x MUR-BAUT BAJA
JIMMY C. R. KAPISSA
M10-L 25mm MENYETUJUI
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

TAMPAK ATAS BALOK PENGAPIT 5/10


ARAH SUMB.Y
Skala 1 : 30

2x MUR-BAUT BAJA
M10-L 25mm YAN SARTHEIS KARUBABA, S.T.
NIP. 19790606 200909 1 003

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

BALOK PENGAPIT 5/10


ARAH SUMB. Y

2x MUR-BAUT BAJA FRANS P.F WATIMENA,SE


M10-L 25mm KOLOM KAYU 10/10 NIP. 19810223 200605 1 001

TUL. STRUKTUR B1
AHLI
5

ARSITEK STRUKTUR DRAFTER


20
10
5

BALOK PENGAPIT 5/10


ARAH SUMB. X
ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

BALOK B1 15/30 TITTLE DRAWING


7,5 5 7,5
20
DETAIL SAMBUNGAN
DETAIL A KOLOM K1 20/25 PENGAPIT SIMP. EMPAT
Skala 1 : 10

SKALA TAHUN NO.DWG JUMLAH

PROYEKSI DIMITRI 2
1:30 2023 018 022
Skala 1 : 30
CODE DRAW: ARS A3
KONSULTAN PERENCANA
1 2 3 4 5 6 7 8 9

KW1 KW1 KW1 KW1 KW1 KW1 KW1 KW1 KW1 NAMA PEKERJAAN
10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10
A
PEMBANGUNAN GEDUNG
BARAK

250
KW1 KW1 KW1 KW1 KW1 KW1 KW1 KW1 KW1 AREA KERJA
10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10

500
B

650
LOKASI:

250
KW1 KW1 KW1 KW1 KW1 KW1 KW1 KW1 KW1
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

150
KW2 KW2 KW2 KW2 KW2 KW2 KW2 KW2 KW2
C 10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10 10/10 SHOPDRAWING
D DIAJUKAN
PEMILIK RUMAH

400 400 400 400 400 400 400 400

3200
JIMMY C. R. KAPISSA

DENAH KOLOM KAYU LT.2


MENYETUJUI
Skala 1 : 150
K1 10/10, Lenght 3meters TOP ELV. +6.90
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR
K1 10/10, Lenght 1,2meters TOP ELV. +4.90

YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003
1 2 3 4 5 6 7 8 9 MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR
50 50

250
FRANS P.F WATIMENA,SE
NIP. 19810223 200605 1 001

500
B AHLI

650
ARSITEK STRUKTUR DRAFTER

250
150
C
D ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING

400 400 400 400 400 400 400 400 GAMBAR DENAH RENCANA
BALOK KAYU JEPIT &
3200 KOLOM LT.2

DENAH BALOK GELAGAR LANTAI 2 uk. 5/7 BGW 5/7, Lenght 3meters TOP ELV. +4.07
Skala 1 : 150
SKALA TAHUN NO.DWG JUMLAH
Wood Class 1
1:150 2023 019 022
CODE DRAW: ARS A3
KONSULTAN PERENCANA
1 2 3 4 5 6 7 8 9

NAMA PEKERJAAN
RBW1 10/10 RBW1 10/10 RBW1 10/10 RBW1 10/10
A PEMBANGUNAN GEDUNG
ELV. +6.90 ELV. +6.90 ELV. +6.90 ELV. +6.90
BARAK

250
AREA KERJA
RBW1 10/10 RBW1 10/10 RBW1 10/10 RBW1 10/10

500
B ELV. +6.90 ELV. +6.90 ELV. +6.90 ELV. +6.90 LOKASI:

650
250
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
RBW1 10/10 RBW1 10/10 RBW1 10/10 RBW1 10/10 DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

ELV. +6.90 ELV. +6.90 ELV. +6.90 ELV. +6.90

150
C RBW1 10/10 RBW1 10/10 RBW1 10/10 RBW1 10/10 SHOPDRAWING
D ELV. +6.90 ELV. +6.90 ELV. +6.90 ELV. +6.90 DIAJUKAN
PEMILIK RUMAH

400 400 400 400 400 400 400 400

3200 JIMMY C. R. KAPISSA


MENYETUJUI
DENAH RING BALOK KAYU LT.2 RBW1 10/10, Lenght 3meters TOP ELV. +6.90 KEPALA BIDANG CIPTA KARYA DINAS PUPR
Skala 1 : 150 KABUPATEN BIAK NUMFOR
Wood Class 1

YAN SARTHEIS KARUBABA, S.T.


1 2 3 4 5 6 7 8 9 NIP. 19790606 200909 1 003
LISPLANK
BALOK NOK MENGETAHUI
IKATAN ANGIN
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

A
1 2 3 4 5 6 6 5 4 3 2 1

300
7 7
8 8
9 9

500
10 10 FRANS P.F WATIMENA,SE
11 11
B NIP. 19810223 200605 1 001

650
12 12
13 13
14 14
AHLI

200
15 15
KUDA-KUDA I 16 16
17 17 ARSITEK STRUKTUR DRAFTER
18 18
19 19

150
C
D
BALOK GORDING
KUDA-KUDA II ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
ATAP SPANDEK
TITTLE DRAWING
400 400 400 400 400 400 400 400

3200 GAMBAR DENAH RENCANA


RING BALOK KAYU LT.2
DENAH RENCANA ATAP & RENC. ATAP
Skala 1 : 150

SKALA TAHUN NO.DWG JUMLAH

1:150 2023 020 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN

PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

PAPAN RUTER uk. 2x15cm


DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA
BUBUNGAN ATAP SPANDEK
BALOK NOK uk. 5/10cm
SHOPDRAWING

25°
PLAT PENGUNCI L=3cm, t= 5mm
+ 9.55
KAKI KUDA-KUDA KAYU 5/10 DIAJUKAN
BALOK GORDINNG 5/10
+ 9.11 PEMILIK RUMAH

TIANG KUDA-KUDA BALOK 5/10cm

BALOK GAPIT 5/10

BALOK SOKONG 5/10


KASO-KASO 4/6

IKATAN ANGIN 5/10cm ATAP SPANDEK


JIMMY C. R. KAPISSA
BALOK DATAR 5/10 MENYETUJUI
BEGEL SERONG
KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR
BALOK TEMBOK 5/10

15°
KUDA-KUDA I
+ 6.90 LISPLANK 2x20cm

BALOK PENGUNCI
BEGEL U L=5cm, t= 5mm

+ 6.30 YAN SARTHEIS KARUBABA, S.T.


NIP. 19790606 200909 1 003

MENGETAHUI
KUDA-KUDA II
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

FRANS P.F WATIMENA,SE


NIP. 19810223 200605 1 001

+ 3.90 AHLI
ARSITEK STRUKTUR DRAFTER

80 250 250 150 43 ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK

TITTLE DRAWING
500
KUDA KUDA
650 GEDUNG BARAK
KERJA

SKALA TAHUN NO.DWG JUMLAH

1:50 2023 021A 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

171
80 NAMA PEKERJAAN
80
PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

LOKASI:

88
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN

68
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

15°
SHOPDRAWING
DIAJUKAN
PEMILIK RUMAH

271

150 43 JIMMY C. R. KAPISSA


MENYETUJUI
150 KEPALA BIDANG CIPTA KARYA DINAS PUPR
KABUPATEN BIAK NUMFOR

DETAIL KUDA-KUDA 2
Skala 1 : 40
150
44

YAN SARTHEIS KARUBABA, S.T.


150 NIP. 19790606 200909 1 003
91

MENGETAHUI
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR
265

130

FRANS P.F WATIMENA,SE


25°

NIP. 19810223 200605 1 001

AHLI
ARSITEK STRUKTUR DRAFTER

ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK


250 250
TITTLE DRAWING

500 GAMBAR
DETAIL KUDA-KUDA
I & II
DETAIL KUDA-KUDA I
Skala 1 : 40
SKALA TAHUN NO.DWG JUMLAH

1:40 2023 021B 022


CODE DRAW: ARS A3
KONSULTAN PERENCANA

NAMA PEKERJAAN
630

120 30 30 30 30 30 30 30 30 30 30 30 30 150
PEMBANGUNAN GEDUNG
BARAK
AREA KERJA

17,5
LOKASI:
JL. SRIWIJAYA RIDGE 2 KEL.BRAMBAKEN
DISTRIK SAMOFA KAB. BIAK NUMFOR-PAPUA

SHOPDRAWING
120

DIAJUKAN
10
11
12
13
14
15
16
17
18
19
6

7
8
9
PEMILIK RUMAH
270
30 30 30 30 30

1 2 3 4 5

30
JIMMY C. R. KAPISSA
MENYETUJUI
DETAIL "A" KEPALA BIDANG CIPTA KARYA DINAS PUPR
Skala 1 : 25 KABUPATEN BIAK NUMFOR

TAMPAK ATAS
Skala 1 : 50

YAN SARTHEIS KARUBABA, S.T.


+ 4.62 NIP. 19790606 200909 1 003

MENGETAHUI

124
KEPALA DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG KABUPATEN BIAK NUMFOR

+ 3.50 + 3.85

17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5 17,5
+ 3.33 + 3.67,5

30
+ 3.50
+ 3.32,5
+ 3.15 FRANS P.F WATIMENA,SE
+ 2.97,5 NIP. 19810223 200605 1 001
+ 2.80
AHLI
+ 2.62,5
+ 2.45 ARSITEK STRUKTUR DRAFTER
+ 2.27,5
+ 2.10
DETAIL "A"
308

+ 1.92,5
+ 1.75
+ 1.23 + 1.57,5
+ 1.40
+ 1.22,5 + 1.22,5 ATIKAH B, S.Ars NOVIDY B ,ST. SATRIYO. BHK
17,5 17,5 17,5 17,5 17,5

+ 0.105 TITTLE DRAWING


+ 0.87,5
+ 0.70
+ 0.52,5
GROUND DETAIL TANGGA
+ 0.35 + 0.35 + 0.40
SEBELAH KIRI GEDUNG
BARAK KERJA
630 270
SKALA TAHUN NO.DWG JUMLAH
TAMPAK SAMPING TAMPAK DEPAN
Skala 1 : 50 Skala 1 : 50 1:50 2023 022 022
CODE DRAW: ARS A3

Anda mungkin juga menyukai