Anda di halaman 1dari 1

BILL OF QUANTITY (BoQ)

PEKERJAAN MEZZANINE
TAHUN 2023

Unit Price TOTAL PRICE


NO URAIAN Spesifikasi SATUAN VOLUME
jasa material jasa material
No Description Specification Unit Volume
IDR IDR
01. Mezaanine

A Pekerjaan Persiapan
Mob Demob Pekerja 20 orang ls 1 10.000.000 - 10.000.000 -
Perancah Skaffolding m2 112 25.000 55.000 2.800.000 6.160.000

B Pondasi
1 Bor Pile kedalaman 4 m , diameter 40 cm titik 13 300.000 1.260.000 3.900.000 16.380.000
- beton mutu K300
- besi d-13; d-8

B Pile cap
1 Pile cap 2 (PC2) uk: 60x60x60 cm ttk 6 75.250 495.000 451.500 2.970.000
- beton
- besi d-13; d-8
2 Galian tanah & bekisting m3 6 75.000 198.000 450.000 1.188.000
3 Anchor A-325 dia 20mm L=50 cm buah 65 10.000 150.000 650.000 9.750.000

C Lantai beton 12 cm
1 Floordeck deck gelombang t: 0.75 mm m2 226 28.000 184.250 6.328.000 41.640.500
- cor beton K-250 m3 34 200.000 935.000 6.800.000 31.790.000
- wiremesh M 8 (1 layer) m2 240 10.000 85.000 2.400.000 20.400.000
- plastik cor & bekisting m2 240 5.000 5.000 1.200.000 1.200.000
- floorhardener 3 kg/m2, sika/fosroc m2 240 15.000 30.000 3.600.000 7.200.000
- epoxy 1.000 micron m2 240 75.000 200.000 18.000.000 48.000.000

2 Perbaikan lantai akibat Bor Pile titik 13 275.000 - 3.575.000 -

D CARGO LIFT
I STRUKTUR LIFT
1 Angkur dan Sikadur M-19
2 Lantai Beton Ls 1,0 5.000.000 37.500.000 5.000.000 37.500.000
3 - Portal HB 150
Unp 100
Pasangan Hebel + plester aci dan cat
Sloof
II LIFT
01. Chain Hoist Kapasitas 500 kg Tinggi angkat 8,5 Merk
meterPawell
380 V/3phase/50 Hz unit 1,0 10.000.000 65.000.000 10.000.000 65.000.000
02. Sangkar Lift Ukuran 1600 mm x 1600 mm x 2000 mm
lengkap dengan penggantung dan guide shoe set
pintu manual harmonika buka tengah
03. Rel K 13 Included braket
04. Panel control 2 lantai PLC system, tombol tiap lantai
05. Safety brake Pengaman lift jatuh

F Kolom
1 Kolom K1 WF 300 kg 1.263 7.000 20.000 8.841.000 25.260.000
2 Base plate & stiffener uk: 350x200mm Plat 16 mm kg 56 6.000 20.000 336.000 1.120.000
3 cat zincromate cat dasar ex-kansai kg 1.319 100 350 131.900 461.650
4 top coat kansai kg 1.319 100 400 131.900 527.600

G Balok
1 Balok B1 WF 300 kg 5.873 7.000 20.000 41.111.000 117.460.000
2 Balok B2 WF 250 kg 5.327 7.000 20.000 37.289.000 106.540.000
3 Railing keliling UNP 150 kg 237 7.000 20.000 1.657.320 4.735.200
Holo 40x40x1.2 mm kg 247 7.000 20.000 1.725.640 4.930.400
4 end plate & stiffener uk: 350x200mm plat 10 mm kg 86 6.000 20.000 516.000 1.720.000
5 baut uk: 3/5x21/2 inch bh 3.000 19.000 - -
6 cat zincromate cat dasar ex-kansai kg 11.683 100 350 1.168.328 4.089.148
7 top coat kansai kg 11.683 100 400 1.168.328 4.673.312
8 Pelat Lantai Plat Bordes 3,2 mm m2 174,20 125.000 698.000 21.775.000 121.591.600

H Tangga Baja
1 - Tangga set 1 4.250.000 13.750.000 4.250.000 13.750.000
- hand railing

TOTAL 195.255.916 696.037.410


TOTAL (jasa+material) 891.293.000

Note :
1. Plat beton luas 240m2 + Plat bordes 174,2 m2 = 414,2 m2
2. Harga Kargo Lift 2 Lantai Kap. 500 kg = Rp 117.500.000,-/set
3. Harga plat lantai (Beton dan Plat bordes) = Rp 1.868.163,-/m2