TIME SCHEDULE

PEKERJAAN : PEMBANGUNAN GEDUNG PEMERINTAHAN DAN PEMERINTAHAN DAERAH , SURABAYA


LOKASI : Jl. JIMERTO no. , JIMERTO - SURABAYA 0.023 -
WAKTU : 8 SEPTEMBER 2014 - 7 DESEMBER 2014

`
SEPTEMBER OKTOBER NOVEMBER DESEMBER
No URAIAN BOBOT (%)
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M - 10 M - 11 M - 12 M - 13
08 S/D 14 15 S/D 21 22 S/D 28 29 S/D 05 06 S/D 12 13 S/D 19 20 S/D 26 27 S/D 02 03 S/D 09 10 S/D 16 17 S/D 23 24 S/D 30 01 S/D 07

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004
B Pengukuran UITZET 0.023 0.023

II PEKERJAAN PASANGAN
A Pasangan ACP
1 Pasangan ACP tampak depan 53.916 6.740 6.740 6.740 6.740 6.740 6.740 6.740 6.740
2 Pasangan ACP tampak samping timur 8.479 2.120 2.120 2.120 2.120
3 Pasangan ACP tampak samping barat 8.479 2.120 2.120 2.120 2.120

B PASANGAN GYPSUM
Selasar Belakanh Pasangan ACP
1 Pemasangan Partisi Single GRC Board 244 x 122 3,5 mm 0.711 0.237 0.237 0.237
Selasar Belakanh Pasangan ACP
2 Pemngecatan Exterior Weathershield 0.357 0.119 0.119 0.119

C PASANGAN LOWFRAY
PASANGAN LOWFRAY AREA GEDUNG
1 Lowfray type 1 1.013 0.507 0.507
2 Lowfray type 2 0.727 0.364 0.364
3 Lowfray type 3 0.227 0.227
4 Lowfray type 4 0.532 0.266 0.266
5 Lowfray type 5 0.261 0.261
7 Lowfray type 6 0.520 0.260 0.260
8 Lowfray type 7 0.150 0.150
9 Lowfray type 8 0.139 0.139
10 Lowfray type 9 0.169 0.169
11 Lowfray type 10 0.205 0.205
12 Lowfray type 11 0.320 0.160 0.160
13 Lowfray type 12 0.145 0.145
14 Lowfray type 13 0.326 0.163 0.163
15 Lowfray type 14 0.124 0.124
16 Lowfray type 15 0.360 0.180 0.180
17 Lowfray type 16 0.115 0.115
18 Lowfray type 17 0.154 0.154
19 Lowfray type 18 0.095 0.095
20 Lowfray type 19 0.205 0.205
21 Lowfray type 20 0.266 0.266
22 Lowfray type 21 0.109 0.109
23 Lowfray type 22 3.625 1.208 1.208 1.208

D PASANGAN Kaca clear tampered 12mm finish sanblast 4.524 4.524

E Pasang Kusen untuk Clear Tempered 12 mm 2.966 2.966

F Pasangan Letter
1 Pemasangan Huruf 'K' 0.195 0.195
2 Pemasangan Huruf 'A' 0.553 0.553
3 Pemasangan Huruf 'N' 0.205 0.205
4 Pemasangan Huruf 'T' 0.236 0.236
5 Pemasangan Huruf 'O' 0.171 0.171
6 Pemasangan Huruf 'R' 0.293 0.293
7 Pemasangan Huruf 'P' 0.077 Rencana Awal 0.077
8 Pemasangan Huruf 'E' 0.174 0.174
9 Pemasangan Huruf 'M' 0.116 0.116
10 Pemasangan Huruf 'I' 0.064 0.064
11 Pemasangan Huruf 'H' 0.089 0.089
12 Pemasangan Huruf 'S' 0.081 0.081
13 Pemasangan Huruf 'U' 0.082 0.082
14 Pemasangan Huruf 'B' 0.094 0.094
15 Pemasangan Huruf 'Y' 0.075 0.075

G Pasangan Besi Siku


1 Pemasangna Besi Siku Tampak Depan 1.138 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142
Besi siku 5x5
2 Pemasangna Besi Siku Tampak samping Timur 0.833 0.208 0.208 0.208 0.208
Besi siku 5x5
3 Pemasangna Besi Siku Tampak samping Barat 0.833 0.208 0.208 0.208 0.208
Besi siku 5x5

III PEKERJAAN FINISHING


Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 0.054 0.054 0.054 0.054 0.054 0.054

Tampak Belakang
B Pengecatan Dinding Lama Tampak Belakang 5.086
Reali 0.848 0.848 0.848 0.848 0.848 0.848
sasi
`
JUMLAH 100 M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15
RENCANA MINGGUAN 0.004 0.027 0.199 6.939 7.786 9.410 10.005 12.980 14.971 21.443 13.904 2.332 0.004 0.000 0.000
KUMULATIF 0.004 0.030 0.229 7.168 14.955 24.365 34.371 47.350 62.322 83.765 97.669 100.000 100.00 100.00 100.00
REALISASI MINGGUAN 0.004 0.023 -0.027 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
KUMULATIF 0.004 0.03
DEVIASI MINGGUAN 0.000 0.00 -0.229 -7.168 -14.955 -24.365 -34.371 -47.350 -62.322 -83.765 -97.669 -100.00 -100.00 -100.00 -100.00
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 2
PERIODE : 15 SEPTEMBER 2014 - 21 SEPTEMBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.0184 0.0129 0.0313 0.0000 0.0000 0.0000

B Pengukuran UITZET 0.023 0.0093 0.0139 0.0232 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.028 0.027 0.054 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - -
- - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - -
2 Lowfray type 2 0.727 - - - -
3 Lowfray type 3 0.227 - - - -
4 Lowfray type 4 0.532 - - - -
5 Lowfray type 5 0.261 - - - -
6 Lowfray type 6 0.520 - - - -
7 Lowfray type 7 0.150 - - - -
8 Lowfray type 8 0.139 - - - -
9 Lowfray type 9 0.165 - - - -
10 Lowfray type 10 0.205 - - - -
11 Lowfray type 11 0.320 - - - -
12 Lowfray type 12 0.145 - - - -
13 Lowfray type 13 0.326 - - - -
14 Lowfray type 14 0.124 - - - -
15 Lowfray type 15 0.360 - - - -
16 Lowfray type 16 0.115 - - - -
17 Lowfray type 17 0.154 - - - -
18 Lowfray type 18 0.095 - - - -
19 Lowfray type 19 0.205 - - - -
20 Lowfray type 20 0.266 - - - -
21 Lowfray type 21 0.109 - - - -
22 Lowfray type 22 3.625 - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 2 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 - - - - - -
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 - - - - - -
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 - - - - - -
Besi siku 5x5
2.805 0.00 0.00 0.00 0.00 0.00 0.00
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 - - - - - -
- - - -
Tampak Belakang - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 - - - - - -
5.407 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 100 0 0 0 0 0 0

Hal 3 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 2
PERIODE : 15 SEPTEMBER 2014 - 21 SEPTEMBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.028 0.027 0.054 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 0.000 0.000 0.000 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 0.000 0.000 0.000 0.000 0.000 0.000

JUMLAH 100 0.028 0.027 0.054 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 0.027 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 0.027 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : 0.000 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 4 dari 22
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 3
PERIODE : 22 SEPTEMBER 2014 - 28 SEPTEMBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.0313 0.0161 0.0474 0.0000 0.0000 0.0000

B Pengukuran UITZET 0.023 0.0232 0.0162 0.0394 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.054 0.032 0.087 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - -
- - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - -
2 Lowfray type 2 0.727 - - - -
3 Lowfray type 3 0.227 - - - -
4 Lowfray type 4 0.532 - - - -
5 Lowfray type 5 0.261 - - - -
6 Lowfray type 6 0.520 - - - -
7 Lowfray type 7 0.150 - - - -
8 Lowfray type 8 0.139 - - - -
9 Lowfray type 9 0.165 - - - -
10 Lowfray type 10 0.205 - - - -
11 Lowfray type 11 0.320 - - - -
12 Lowfray type 12 0.145 - - - -
13 Lowfray type 13 0.326 - - - -
14 Lowfray type 14 0.124 - - - -
15 Lowfray type 15 0.360 - - - -
16 Lowfray type 16 0.115 - - - -
17 Lowfray type 17 0.154 - - - -
18 Lowfray type 18 0.095 - - - -
19 Lowfray type 19 0.205 - - - -
20 Lowfray type 20 0.266 - - - -
21 Lowfray type 21 0.109 - - - -
22 Lowfray type 22 3.625 - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 5 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 - - - - - -
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 - - - - - -
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 - - - - - -
Besi siku 5x5
2.805 0.00 0.00 0.00 0.00 0.00 0.00
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 - 0.1123 0.1123 - 0.0004 0.0004
- - - -
Tampak Belakang - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 - - - - - -
5.407 0.00 0.11 0.11 0.00 0.00 0.00

JUMLAH 100 0 0 0 0 0 0

Hal 6 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 3
PERIODE : 22 SEPTEMBER 2014 - 28 SEPTEMBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.054 0.032 0.087 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 0.000 0.000 0.000 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 0.000 0.112 0.112 0.000 0.000 0.000

JUMLAH 100 0.054 0.145 0.199 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 0.199 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 0.145 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : -0.054 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 7 dari 22
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 4
PERIODE : 29 SEPTEMBER 2014 - 5 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.0474 0.0184 0.0658 0.0000 0.0000 0.0000

B Pengukuran UITZET 0.023 0.0394 0.0174 0.0567 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.087 0.036 0.123 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - -
- - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - -
2 Lowfray type 2 0.727 - - - -
3 Lowfray type 3 0.227 - - - -
4 Lowfray type 4 0.532 - - - -
5 Lowfray type 5 0.261 - - - -
6 Lowfray type 6 0.520 - - - -
7 Lowfray type 7 0.150 - - - -
8 Lowfray type 8 0.139 - - - -
9 Lowfray type 9 0.165 - - - -
10 Lowfray type 10 0.205 - - - -
11 Lowfray type 11 0.320 - - - -
12 Lowfray type 12 0.145 - - - -
13 Lowfray type 13 0.326 - - - -
14 Lowfray type 14 0.124 - - - -
15 Lowfray type 15 0.360 - - - -
16 Lowfray type 16 0.115 - - - -
17 Lowfray type 17 0.154 - - - -
18 Lowfray type 18 0.095 - - - -
19 Lowfray type 19 0.205 - - - -
20 Lowfray type 20 0.266 - - - -
21 Lowfray type 21 0.109 - - - -
22 Lowfray type 22 3.625 - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 8 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 - - - - - -
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 - - - - - -
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 - - - - - -
Besi siku 5x5
2.805 0.00 0.00 0.00 0.00 0.00 0.00
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 - 0.1605 0.1605 - 0.0005 0.0005
- - - -
Tampak Belakang - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 - 2.5429 2.5429 - 0.1293 0.1293
5.407 0.00 2.70 2.70 0.00 0.13 0.13

JUMLAH 100 0 3 3 0 0 0

Hal 9 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 4
PERIODE : 29 SEPTEMBER 2014 - 5 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.087 0.036 0.123 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 0.000 0.000 0.000 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 0.000 2.703 2.703 0.000 0.000 0.000

JUMLAH 100 0.087 2.739 2.826 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 6.939 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 2.739 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : -4.200 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 10 dari 22
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 5
PERIODE : 6 OKTOBER 2014 - 12 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.0658 0.0276 0.0934 0.0000 0.0000 0.0000

B Pengukuran UITZET 0.023 0.0567 0.0197 0.0764 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.123 0.047 0.170 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - - -
- - - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - - -
2 Lowfray type 2 0.727 - - - - -
3 Lowfray type 3 0.227 - - - - -
4 Lowfray type 4 0.532 - - - - -
5 Lowfray type 5 0.261 - - - - -
6 Lowfray type 6 0.520 - - - - -
7 Lowfray type 7 0.150 - - - - -
8 Lowfray type 8 0.139 - - - - -
9 Lowfray type 9 0.165 - - - - -
10 Lowfray type 10 0.205 - - - - -
11 Lowfray type 11 0.320 - - - - -
12 Lowfray type 12 0.145 - - - - -
13 Lowfray type 13 0.326 - - - - -
14 Lowfray type 14 0.124 - - - - -
15 Lowfray type 15 0.360 - - - - -
16 Lowfray type 16 0.115 - - - - -
17 Lowfray type 17 0.154 - - - - -
18 Lowfray type 18 0.095 - - - - -
19 Lowfray type 19 0.205 - - - - -
20 Lowfray type 20 0.266 - - - - -
21 Lowfray type 21 0.109 - - - - -
22 Lowfray type 22 3.625 - - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 11 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 - 0.1138 0.1138 - 0.0013 0.0013
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 - 0.0833 0.0833 - 0.0007 0.0007
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 - - - - - -
Besi siku 5x5
2.805 0.00 0.20 0.20 0.00 0.00 0.00
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 0.1605 0.2086 0.3691 0.0005 0.0007 0.0012
- - - - -
Tampak Belakang - - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 2.5429 3.0515 5.5945 0.1293 0.1552 0.2845
5.407 2.70 3.26 5.96 0.13 0.16 0.29

JUMLAH 100 3 4 6 0 0 0

Hal 12 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 5
PERIODE : 6 OKTOBER 2014 - 12 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.123 0.047 0.170 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 0.000 0.197 0.197 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 2.703 3.260 5.964 0.000 0.000 0.000

JUMLAH 100 2.826 3.505 6.330 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 7.786 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 3.505 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : -4.282 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 13 dari 22
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 6
PERIODE : 13 OKTOBER 2014 - 19 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.0934 0.0368 0.1302 0.0000 0.0000 0.0001

B Pengukuran UITZET 0.023 0.0764 0.0208 0.0972 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.170 0.058 0.227 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - - -
- - - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - - -
2 Lowfray type 2 0.727 - - - - -
3 Lowfray type 3 0.227 - - - - -
4 Lowfray type 4 0.532 - - - - -
5 Lowfray type 5 0.261 - - - - -
6 Lowfray type 6 0.520 - - - - -
7 Lowfray type 7 0.150 - - - - -
8 Lowfray type 8 0.139 - - - - -
9 Lowfray type 9 0.165 - - - - -
10 Lowfray type 10 0.205 - - - - -
11 Lowfray type 11 0.320 - - - - -
12 Lowfray type 12 0.145 - - - - -
13 Lowfray type 13 0.326 - - - - -
14 Lowfray type 14 0.124 - - - - -
15 Lowfray type 15 0.360 - - - - -
16 Lowfray type 16 0.115 - - - - -
17 Lowfray type 17 0.154 - - - - -
18 Lowfray type 18 0.095 - - - - -
19 Lowfray type 19 0.205 - - - - -
20 Lowfray type 20 0.266 - - - - -
21 Lowfray type 21 0.109 - - - - -
22 Lowfray type 22 3.625 - - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 14 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 0.1138 0.3414 0.4553 0.0013 0.0039 0.0052
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 0.0833 0.2500 0.3334 0.0007 0.0021 0.0028
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 - 0.2500 0.2500 - 0.0021 0.0021
Besi siku 5x5
2.805 0.20 0.84 1.04 0.00 0.00 0.00
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 0.3691 0.2568 0.6259 0.0012 0.0008 0.0020
- - - - -
Tampak Belakang - - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 5.5945 4.0687 9.6631 0.2845 0.2069 0.4915
5.407 5.96 4.33 10.29 0.29 0.21 0.49

JUMLAH 100 6 5 12 0 0 0

Hal 15 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 6
PERIODE : 13 OKTOBER 2014 - 19 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.170 0.058 0.227 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 0.197 0.842 1.039 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 5.964 4.325 10.289 0.000 0.000 0.000

JUMLAH 100 6.330 5.225 11.555 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 9.410 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 5.225 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : -4.186 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 16 dari 22
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 7
PERIODE : 20 OKTOBER 2014 - 26 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.1302 0.0368 0.1670 0.0001 0.0000 0.0001

B Pengukuran UITZET 0.023 0.0972 0.0208 0.1181 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.227 0.058 0.285 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - - -
- - - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - - -
2 Lowfray type 2 0.727 - - - - -
3 Lowfray type 3 0.227 - - - - -
4 Lowfray type 4 0.532 - - - - -
5 Lowfray type 5 0.261 - - - - -
6 Lowfray type 6 0.520 - - - - -
7 Lowfray type 7 0.150 - - - - -
8 Lowfray type 8 0.139 - - - - -
9 Lowfray type 9 0.165 - - - - -
10 Lowfray type 10 0.205 - - - - -
11 Lowfray type 11 0.320 - - - - -
12 Lowfray type 12 0.145 - - - - -
13 Lowfray type 13 0.326 - - - - -
14 Lowfray type 14 0.124 - - - - -
15 Lowfray type 15 0.360 - - - - -
16 Lowfray type 16 0.115 - - - - -
17 Lowfray type 17 0.154 - - - - -
18 Lowfray type 18 0.095 - - - - -
19 Lowfray type 19 0.205 - - - - -
20 Lowfray type 20 0.266 - - - - -
21 Lowfray type 21 0.109 - - - - -
22 Lowfray type 22 3.625 - - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 17 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 0.4553 0.3983 0.8536 0.0052 0.0045 0.0097
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 0.3334 0.2917 0.6251 0.0028 0.0024 0.0052
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 0.2500 0.2500 0.5001 0.0021 0.0021 0.0042
Besi siku 5x5
2.805 1.04 0.94 1.98 0.00 0.00 0.00
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 0.6259 0.2728 0.8987 0.0020 0.0009 0.0029
- - - - -
Tampak Belakang - - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 9.6631 4.3230 13.9861 0.4915 0.2199 0.7113
5.407 10.29 4.60 14.88 0.49 0.22 0.71

JUMLAH 100 12 6 17 0 0 1

Hal 18 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 7
PERIODE : 20 OKTOBER 2014 - 26 OKTOBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.227 0.058 0.285 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 1.039 0.940 1.979 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 10.289 4.596 14.885 0.000 0.000 0.000

JUMLAH 100 11.555 5.594 17.149 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 10.006 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 5.594 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : -4.412 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 19 dari 22
DETAIL PROGRESS FISIK PEKERJAAN
PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO
LOKASI : Jl. JIMERTO , Kota Surabaya
Kontraktor Pelaksana : PT. RUDY JAYA
Konsultan Pengawas : CV. CAHAYA MANDIRI
MINGGU KE- : 8
PERIODE : 27 OKTOBER 2014 - 02 NOVEMBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%) (%)
(%) INI (%) (%) (%)

I PEKERJAAN PERSIAPAN
A Pembersihan Lapangan Ringan 0.046 0.1670 0.0368 0.2038 0.0001 0.0000 0.0001

B Pengukuran UITZET 0.023 0.1181 0.0208 0.1389 0.0000 0.0000 0.0000


- - - - - -
- - - - - -
0.069 0.285 0.058 0.343 0.000 0.000 0.00
II PEKERJAAN PASANGAN -
A Pasangan ACP
1 Pemasangan ACP tampak depan 53.916 - - - - -
2 Pemasangan ACP tampak samping timur 8.479 - - - - -
3 Pemasangan ACP tampak samping barat 8.479 - - - - -
70.874 0.00 0.00 0.00 0.00 - -
B PASANGAN GYPSUM
Selasar Belakang Pasangan ACP - - - - - -
1 Pemasangan Partisi Singgle GRC Board 244 x 122 3,5 mm 0.711 - - - - -
- - - - - -
Selasar Belakang Pasangan ACP
2 Pengecatan Exterior Weathershield 0.357 - - - - -
1.069 0.00 0.00 0.00 0.00 0.00 0.00
C Pasangan Lowfray -
Pemasangan Lowfray Area Gedug
1 Lowfray type 1 1.013 - - - - -
2 Lowfray type 2 0.727 - - - - -
3 Lowfray type 3 0.227 - - - - -
4 Lowfray type 4 0.532 - - - - -
5 Lowfray type 5 0.261 - - - - -
6 Lowfray type 6 0.520 - - - - -
7 Lowfray type 7 0.150 - - - - -
8 Lowfray type 8 0.139 - - - - -
9 Lowfray type 9 0.165 - - - - -
10 Lowfray type 10 0.205 - - - - -
11 Lowfray type 11 0.320 - - - - -
12 Lowfray type 12 0.145 - - - - -
13 Lowfray type 13 0.326 - - - - -
14 Lowfray type 14 0.124 - - - - -
15 Lowfray type 15 0.360 - - - - -
16 Lowfray type 16 0.115 - - - - -
17 Lowfray type 17 0.154 - - - - -
18 Lowfray type 18 0.095 - - - - -
19 Lowfray type 19 0.205 - - - - -
20 Lowfray type 20 0.266 - - - - -
21 Lowfray type 21 0.109 - - - - -
22 Lowfray type 22 3.625 - - - - -
9.781 0.00 0.00 0.00 0.00 0.00 0.00

Hal 20 dari 22
% KEMAJUAN PEKERJAAN % BOBOT FISIK

BOBOT S/D MINGGU S/D S/D MINGGU S/D MINGGU


NO. URAIAN PEKERJAAN MINGGU INI MINGGU INI
(%) LALU MINGGU LALU INI
(%)
(%) (%)
(%)
INI (%) (%)

D Pasangan kaca clear tempered 12mm finish Sanblast -


Pasangan kaca clear tempered 12mm finish Sanblast 4.524 - - - - - -

4.524 - - - - - -
E Pasangan Kusen untuk Clear Tempered 12 mm
1 Pasangan Kusen untuk Clear Tempered 12 mm 2.97 - - - - - -
2.966 0.00 0.00 0.00 0.00 0.00 0.00
F Pasangan Letter -
1 Pemasangan huruf "K" 0.195 - - - - - -
2 Pemasangan huruf "A" 0.553 - - - - - -
3 Pemasangan huruf "N" 0.205 - - - - - -
4 Pemasangan huruf "T" 0.236 - - - - - -
5 Pemasangan huruf "O" 0.171 - - - - - -
6 Pemasangan huruf "R" 0.293 - - - - - -
7 Pemasangan huruf "P" 0.077 - - - - - -
8 Pemasangan huruf "E" 0.174 - - - - - -
9 Pemasangan huruf "M" 0.116 - - - - - -
10 Pemasangan huruf "I" 0.064 - - - - - -
11 Pemasangan huruf "H" 0.089 - - - - - -
12 Pemasangan huruf "S" 0.081 - - - - - -
13 Pemasangan huruf "U" 0.082 - - - - - -
14 Pemasangan huruf "B" 0.094 - - - - - -
15 Pemasangan huruf "Y" 0.075 - - - - - -
2.505 0.00 0.00 0.00 0.00 0.00 0.00
G Pasangan Besi Siku
1 Pemasangan Besi Siku Tampak Depan 1.138 0.8536 0.4325 1.2861 0.0097 0.0049 0.0146
Besi siku 5x5
2 Pemasangan Besi Siku Tampak Samping Timur 0.833 0.6251 0.2917 0.9168 0.0052 0.0024 0.0076
Besi siku 5x5
3 Pemasanagan Besi Siku Tmpak Samping Barat 0.833 0.5001 0.2917 0.7918 0.0042 0.0024 0.0066
Besi siku 5x5
2.805 1.98 1.02 2.99 0.00 0.00 0.01
III PEKERJAAN FINISHING -
Tampak Belakang
A Pengerokan Dinding Lama Tampak Belakang 0.321 0.8987 0.2889 1.1875 0.0029 0.0009 0.0038
- - - - -
Tampak Belakang - - - - -
B Pengecatan Dinding Lama Tampak Belakang 5.086 13.9861 4.5773 18.5634 0.7113 0.2328 0.9441
5.407 14.88 4.87 19.75 0.71 0.23 0.95

JUMLAH 100 17 6 23 1 0 1

Hal 21 dari 22
REKAP PROGRESS FISIK PEKERJAAN

PROYEK : Pembangunan Gedung Type B PEMBANGUNAN GEDUNG JIMERTO


LOKASI : Jl. JIMERTO , Kota Surabaya
MINGGU KE- : 8
PERIODE : 27 OKTOBER 2014 - 02 NOVEMBER 2014

% KEMAJUAN PEKERJAAN % BOBOT FISIK


BOBOT S/D MINGGU S/D MINGGU
NO. URAIAN PEKERJAAN MINGGU INI S/D MINGGU INI MINGGU INI S/D MINGGU INI
(%) LALU LALU
(%)
(%) (%) (%)
(%) (%)

I PEKERJAAN PERSIAPAN 0.069 0.285 0.058 0.343 0.000 0.000 0.00

II PEKERJAAN PASANGAN 70.874 0.000 0.000 0.000 0.000 0.000 0.000

III PASANGAN GYPSUM 1.069 0.000 0.000 0.000 0.000 0.000 0.000

IV Pasangan Lowfray 9.781 0.000 0.000 0.000 0.000 0.000 0.000

V Pasangan kaca clear tempered 12mm finish Sanblast 4.524 0.000 0.000 0.000 0.000 0.000 0.000

VI Pasangan Kusen untuk Clear Tempered 12 mm 2.966 0.000 0.000 0.000 0.000 0.000 0.000

VII Pasangan Letter 2.505

VIII Pasangan Besi Siku 2.805 1.979 1.016 2.995 0.000 0.000 0.000

IX PEKERJAAN FINISHING 5.407 14.885 4.866 19.751 0.000 0.000 0.000

JUMLAH 100 17.149 5.940 23.088 0.000 0.000 0.000

PROGRES RENCANA MINGGU INI : 12.980 PROGRES RENCANA KUMULATIF s/d MINGGU : 0.004
PROGRES REALISASI MINGGU INI : 5.940 PROGRES REALISASI KUMULATIF s/d MINGGU :
DEVIASI MINGGU INI : -7.040 DEVIASI KUMULATIF s/d MINGGU INI : -0.004

Surabaya, 24 September 2011 Menyetujui :


Dibuat Oleh : Kordinator Pengawas Menyetujui :
Konsultan Pengawas Tim Pengawas Pembangunan
CV. CAHAYA MANDIRI

BAGUS INDRAJAYA, ST Hariyanto. ST


Team Leader NIP. Subiyakto

Mengetahui :
Pejabat Pembuat Komitmen
Pembangunan dan Renovasi Gedung ITS

Ir. Imam Prayogo


NIP. 131 128 954

Hal 22 dari 22