REKAPITULASI ANGGARAN BIAYA

Provinsi : Jawa Timur Jenis Kegiatan : Pembangunan Talud


Kabupaten : Situbondo Lokasi : Dusun .... RT.00 RW.00
Desa : Cipta Desa

Kegiatan : Saluran Air


Ukuran : 300 x 1,5 M JUMLAH TOTAL BOBOT
No URAIAN Jumlah : 1 Unit ( Rp ) (%)
No.Rab :1
SWADAYA DANA DESA
I BAHAN
( Tidak perlu dirinci ) 9,100,000 55,295,000 64,395,000 51.13

II PERALATAN
( Tidak perlu dirinci ) 705,000 - 705,000 0.56

III UPAH
( Tidak perlu dirinci ) - 60,840,000 60,840,000 48.31

JUMLAH 9,805,000 116,135,000 125,940,000 100


IV Operasional 1 - 3,667,400 3,667,400
V Operasional 2 - 2,444,900 2,444,900

I JUMLAH 9,805,000 122,247,300 132,052,300

Mengetahui, Tim Pengelola Kegiatan (TPK)


Kepala Desa .................... Desa .....................

........................................ ..............................

Perencana

.................................
RENCANA ANGGARAN BIAYA ( RAB )

Provinsi : Jawa Timur No. RAB :1


Kabupaten : Situbondo Jenis Kegiatan : Talud
Desa : Cipta Desa Volume : 1 Unit
Lokasi : Cipta Desa Ukuran : 300 x 1,5 M

Volume Harga Satuan ( Rp ) B I A Y A ( Rp )


N
URAIAN Dari Satuan Upah
o Total Dari Dana Bahan Total Swadaya PNPM - MP Total
swadaya angkut

I BAHAN
1 Pasir Urug 10.00 5.00 5.00 m3 - 70,000 70,000 350,000 350,000 700,000
2 Pasir Pasang 112.00 50.00 62.00 m3 - 70,000 70,000 3,500,000 4,340,000 7,840,000
3 Batu Kali/Gunung 191.00 75.00 116.00 m3 - 70,000 70,000 5,250,000 8,120,000 13,370,000
4 Kerikil - - - m3 - 70,000 70,000 - - -
5 Semen @ 50 Kg 586.00 - 586.00 Zak 10,000 62,500 72,500 - 42,485,000 42,485,000

Sub Total 1 ) 9,100,000 55,295,000 64,395,000


II ALAT
1 Cangkul 5.00 5.00 - bh - 40,000 40,000 200,000 - 200,000
2 Sekop 6.00 6.00 - bh - 40,000 40,000 240,000 - 240,000
3 Palu-palu 2.00 2.00 - bh - 15,000 15,000 30,000 - 30,000
4 Linggis 3.00 3.00 - bh - 35,000 35,000 105,000 - 105,000
5 Ember 4.00 4.00 - bh - 20,000 20,000 80,000 - 80,000
6 Benang Nilon 1.00 1.00 - Roll - 50,000 50,000 50,000 - 50,000
Sub Total 2 ) 705,000 - 705,000
III UPAH
1 Pekerja 398.00 - 398.00 hok - 80,000 80,000 - 31,840,000 31,840,000
2 Tukang 290.00 - 290.00 hok - 100,000 100,000 - 29,000,000 29,000,000

Sub Total 3 ) - 60,840,000 60,840,000


TOTAL I ( 1 + 2 + 3 ) 9,805,000 116,135,000 125,940,000

Mengetahui, Tim Pengelola Kegiatan (TPK)


Kepala Desa .................... Desa .....................

................................. .................................

Perencana

.................................