TIME SCHEDULE PELAKSANAAN PEKERJAAN

Tahun 2019
No. Jenis Pekerjaan Jumlah biaya Bobot AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER Ket.
( Rp. ) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

2.32 2.32 100%


1 PEKERJAAN PERSIAPAN 11,108,977.00 4.64
0.98 0.98 0.98 0.98 0.98
2 PEMBANGUNAN DRAINASE TYPE 1 P= 100 m 11,739,837.00 4.90
5.81 5.81 5.81 5.81 5.81
3 PEMBANGUNAN DRAINASE TYPE 2 P= 115m 69,570,613.00 29.05
9.96 9.96 9.96 9.96 9.96 9.96
4 PEKERJAAN REHABILITAS DRAINASE P= 128 143,048,809.73 59.74
0.56 0.56 0.56
5 PEKERJAAN AKHIR 4,000,000.00 1.67

JUMLAH 239,468,236.7 100.0 0%


PPN 10 % 23,946,823.7
TOTAL 263,415,060.4
DIBULATKAN 263,410,000.0
Rencana Mingguan (%) 2.32 0.98 0.98 0.98 5.81 5.81 5.81 0.98 0.98 9.96 9.96 9.96 5.81 5.81 9.96 9.96 9.96 0.56 0.56 2.88 Rencana
Rencana Cumulative Mingguan (%) ### 2.32 3.30 4.28 5.26 11.07 16.88 22.69 23.67 24.65 34.61 44.57 54.52 60.33 66.14 76.10 86.05 96.01 96.57 97.12 100.0

Ambon, 9 Juli 2019


PENAWAR
CV. VEMA INDAH

MAYA ANDAYANI
DIREKTRIS
PEMERINTAH PROVINSI MALUKU
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BIDANG CIPTA KARYA
Jln. D. I. Panjaitan No. 2 Telp. (0911) 353226 - Ambon

OWNER ESTIMATE
(OE)

PROGRAM :
PEMBANGUNAN SALURAN DRAINASE/ GORONG-GORONG

KEGIATAN :
PEMBANGUNAN SALURAN DRAINASE/ GORONG-GORONG GUGUS PULAU 7

PEKERJAAN :
REHABILITASI DRAINASE
KECAMATAN NUSANIWE

LOKASI :
KOTA AMBON

TAHUN ANGGARAN 2019


LEMBAR PENGESAHAN
OWNER ESTIMATE (OE)

PROGRAM :
PEMBANGUNAN SALURAN DRAINASE/ GORONG-GoRONG

KEGIATAN :
PEMBANGUNAN SALURAN DRAINASE/ GORONG-GORONG GUGUS PULAU 7

PEKERJAAN :
REHABILITASI DRAINASE
KECAMATAN NUSANIWE

LOKASI :
KOTA AMBON

Sumber Dana APBD

TAHUN ANGGARAN
2018

Diperiksa: Dibuat oleh:


PEJABAT PELAKSANA TEKNIS KEGIATAN PEMBANTU PPTK
(PPTK)

MUHIJATY TUANAYA, ST, MT. HASANAH SOULISA A.md


NIP : 19710301 200112 2 002 NIP : 19870422 201101 2 18

Mengetahui,
KEPALA BIDANG CIPTA KARYA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
PROVINSI MALUKU

Ir. ADECI AYUBA, MT


NIP. 19650118 199603 1 001
Ir. ADECI AYUBA, MT
NIP. 19650118 199603 1 001
RENCANA ANGGARAN BIAYA
(RAB)

PROGRAM : PEMBANGUNAN SALURAN DRAINASE/ GORONG-GORONG


KEGIATAN : PEMBANGUNAN SALURAN DRAIANSE / GORONG-GORONG GUGUS PULAU 7
PEKERJAAN : REHABILITAS DRAINASE KECAMATAN NUSANIWE
LOKASI : KOTA AMBON
TAHUN : 2019

REKAPITULASI
JUMLAH HARGA
NO URAIAN
(Rp.)

I PEKERJAAN PERSIAPAN 11,108,977.00

II PEMBANGUNAN DRAINASE TYPE 1 P= 100 m 12,099,162.00

III PEMBANGUNAN DRAINASE TYPE 2 P= 115m 71,876,475.95

IV PEKERJAAN REHABILITAS DRAINASE P= 128 m 148,108,403.23

V PEKERJAAN AKHIR 4,000,000.00

A BIAYA 247,193,018.19

B PPN 10 % 24,719,301.82

C TOTAL BIAYA = A + B 271,912,320.00

D PEMBULATAN 271,912,320.00

DUA RATUS TUJUH PULUH SATU JUTA SEMBILAN RATUS DUA BELAS RIBU TIGA RATUS DUA PULUH RUPIAH

Ambon, 9 Juli 2019

PENAWARAN
CV. TIRTA UTAMA

SYAID ABDULLAH BIN SMITH


Direktur
RENCANA ANGGARAN BIAYA
(RAB)
PROGRAM : PEMBANGUNAN SALURAN DRAINASE/ GORONG-GORONG
KEGIATAN : PEMBANGUNAN SALURAN DRAIANSE / GORONG-GORONG GUGUS PULAU 7
PEKERJAAN : REHABILITAS DRAINASE KECAMATAN NUSANIWE
LOKASI : KOTA AMBON
TAHUN : 2019

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN SATUAN VOLUME
( Rp ) ( Rp )

I PEKERJAAN PERSIAPAN
1 Pembersihan Awal Ls 1.00 2,000,000.00 2,000,000.00
2 Papan Nama Proyek Ls 1.00 500,000.00 500,000.00
3 Pemasangan Bouwplank Ls 1.00 2,000,000.00 2,000,000.00
4 Operasional Kesehatan dan Keselamatan Kerja Ls 1.00 6,608,977.00 6,608,977.00
11,108,977.00
II PEMBANGUNAN DRAINASE TYPE 1 P= 100 m 100 46.00
1 Galian tanah M3 22.50 86,825.00 1,953,562.50
2 Urugan Pasir M3 3.75 550,850.00 2,065,687.50
3 Pasangan Batu Kosong M3 3.00 462,000.00 1,386,000.00
4 Pasangan Batu Kali Camp. 1 : 3 M3 9.00 474,700.00 4,272,300.00
5 Rabat Beton Lantai Dasar Saluran M3 1.50 333,000.00 499,500.00
6 Plesteran Camp. 1 : 2 M2 80.00 24,026.40 1,922,112.00
12,099,162.00
III PEMBANGUNAN DRAINASE TYPE 2 P= 115m 115 50.00
1 Galian tanah M3 66.41 86,825.00 5,766,265.31
2 Urugan Pasir M3 4.02 550,850.00 2,217,171.25
3 Pasangan Batu Kosong M3 4.60 870,490.20 4,004,254.92
4 Pasangan Batu Kali Camp. 1 : 3 M3 24.72 1,581,336.25 39,098,538.78
5 Rabat Beton Lantai Dasar Saluran M3 1.38 1,571,594.43 2,168,800.31
6 Plesteran Camp. 1 : 2 M2 195.50 95,250.36 18,621,445.38
71,876,475.95
IV PEKERJAAN REHABILITAS DRAINASE P= 128 m 128 30.00
1 Galian Tanah M3 147.65 86,825.00 12,819,915.62
2 Urug Pasir M3 6.42 550,850.00 3,536,273.87
3 Pasangan Batu Kosong M3 11.56 870,490.20 10,058,863.85
4 Pasangan Batu Kali Camp 1 :3 M3 54.57 1,581,336.25 86,289,050.65
5 Rabat Beton Lantai Dasar saluran M3 3.85 1,571,594.43 6,053,468.25
6 Plesteran Camp 1 :2 M2 308.14 95,250.36 29,350,830.99
148,108,403.23
IV PEKERJAAN AKHIR
1 Pembersihan akhir Ls 1.00 2,000,000.00 2,000,000.00
2 Laporan dan Dokumentasi Ls 1.00 2,000,000.00 2,000,000.00
4,000,000.00
ANALISA HARGA SATUAN PEKERJAAN BIDANG PEKERJAAN UMUM
BERDASARKAN :
PERATURAN MENTERI PEKERJAAN UMUM NO. 28/PRT/M/2016

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH :

A.2.3.1.1. Penggalian 1 M3 Tanah Biasa Sedalam 1 M'.


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.750 95,000.00 71,250.00
Mandor L.04 OH 0.025 170,000.00 4,250.00
JUMLAH TENAGA KERJA 75,500.00
B. BAHAN

JUMLAH HARGA BAHAN 0.00


C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 75,500.00
E Overhead + profit 15% x D 11,325.00
F Harga Satuan pekerjaan (D+E) 86,825.00

A.2.3.1.8. (K3) Pembuangan 1 M3 tanah sejauh 30 M'


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.330 95,000.00 31,350.00
Mandor L.04 OH 0.010 170,000.00 1,700.00
JUMLAH TENAGA KERJA 33,050.00
B. BAHAN

JUMLAH HARGA BAHAN 0.00


C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 33,050.00
E Overhead + profit 15% x D 4,957.50
F Harga Satuan pekerjaan (D+E) 38,007.50

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI :

A.3.2.1.1. Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 3 PP


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.500 95,000.00 142,500.00
Tukang Batu L.02 OH 0.750 120,000.00 90,000.00
Kepala Tukang L.03 OH 0.075 150,000.00 11,250.00
Mandor L.04 OH 0.075 170,000.00 12,750.00
JUMLAH TENAGA KERJA 256,500.00
B. BAHAN
Batu Belah M3 1.200 385,000.00 462,000.00
Semen Portland Kg 202.000 2,350.00 474,700.00
Pasir Pasang M3 0.485 375,000.00 181,875.00
JUMLAH HARGA BAHAN 1,118,575.00
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 1,375,075.00
E Overhead + profit 15% x D 206,261.25
F Harga Satuan pekerjaan (D+E) 1,581,336.25
A.3.2.1.9. Pemasangan 1 M3 batu kosong (anstamping)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.780 95,000.00 74,100.00
Tukang Batu L.02 OH 0.390 120,000.00 46,800.00
Kepala Tukang L.03 OH 0.039 150,000.00 5,850.00
Mandor L.04 OH 0.039 170,000.00 6,630.00
JUMLAH TENAGA KERJA 133,380.00
B. BAHAN
Batu Belah M3 1.200 385,000.00 462,000.00
Pasir Urug M3 0.432 374,000.00 161,568.00
JUMLAH HARGA BAHAN 623,568.00
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 756,948.00
E Overhead + profit 15% x D 113,542.20
F Harga Satuan pekerjaan (D+E) 870,490.20

A.4.1.1 HARGA SATUAN PEKERJAAN BETON :


CATATAN :
Bobot Isi Pasir = 1.400 Kg/M3, Bobot Isi Kerikil = 1.350 Kg/M3, Buckling Factor Pasir = 20%

A.4.1.1.1. Membuat 1 M3 beton mutu f'c = 7,4 Mpa


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 95,000.00 156,750.00
Tukang Batu L.02 OH 0.275 120,000.00 33,000.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 170,000.00 14,110.00
JUMLAH TENAGA KERJA 208,060.00
B. BAHAN
Semen Portland Kg 247.00 2,350.00 580,450.00
Pasir Beton Kg 869.00 267.86 232,767.86
Kerikil (maks 30 mm) Kg 999.00 333.33 333,000.00
Air Ltr 215.00 57.33 12,325.99
JUMLAH HARGA BAHAN 1,158,543.85
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 1,366,603.85
E Overhead + profit 15% x D 204,990.58
F Harga Satuan pekerjaan (D+E) 1,571,594.43

A.4.1.1.5. Membuat 1 M3 beton mutu f'c = 14,5 Mpa, slump (120 ± 20) mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 1.650 95,000.00 156,750.00
Tukang Batu L.02 OH 0.275 120,000.00 33,000.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 170,000.00 14,110.00
JUMLAH TENAGA KERJA 208,060.00
B. BAHAN
Semen Portland Kg 326.00 2,350.00 766,100.00
Pasir Beton Kg 760.00 267.86 203,571.43
Kerikil (maks 30 mm) Kg 1029.00 333.33 343,000.00
Air Ltr 215.00 57.33 12,325.99
JUMLAH HARGA BAHAN 1,324,997.42
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 1,533,057.42
E Overhead + profit 15% x D 229,958.61
F Harga Satuan pekerjaan (D+E) 1,763,016.03
A.4.1.1.17. Pembesian 10 Kg dengan besi polos dan besi ulir
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.070 95,000.00 6,650.00
Tukang Besi L.02 OH 0.070 120,000.00 8,400.00
Kepala Tukang L.03 OH 0.0070 150,000.00 1,050.00
Mandor L.04 OH 0.0040 170,000.00 680.00
JUMLAH TENAGA KERJA 16,780.00
B. BAHAN
Besi Beton (Polos/Ulir) Kg 10.500 16,000.00 168,000.00
Kawat Beton Kg 0.150 24,000.00 3,600.00
JUMLAH HARGA BAHAN 171,600.00
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 188,380.00
E Overhead + profit 15% x D 28,257.00
F Harga Satuan pekerjaan (D+E) 216,637.00
G Untuk Pembesian 1 Kg (F / 10) 21,663.70

A. 4.1.1.24 (K3) Pemasangan 1 M2 bekesting untuk lantai


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.660 95,000.00 62,700.00
Tukang Kayu L.02 OH 0.330 120,000.00 39,600.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 170,000.00 5,610.00
JUMLAH TENAGA KERJA 112,860.00
B. BAHAN
Kayu Kls III M3 0.040 33,000.00 1,320.00
Paku 5 - 12 cm Kg 0.400 107,000.00 42,800.00
Minyak Bekesting Liter 0.200 106,000.00 21,200.00
Balok Kayu Kelas II M3 0.015 22,000.00 330.00
Plywood tebal 9 mm Lembar 0.350 2,500.00 875.00
Dolken Kayu (ø 8-10)-pjg 4 m Batang 6.000 106,000.00 636,000.00
JUMLAH HARGA BAHAN 702,525.00
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 815,385.00
E Overhead + profit 15% x D 122,307.75
F Harga Satuan pekerjaan (D+E) 937,692.75

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN :

A.4.4.2.2. Pemasangan 1 M2 plesteran 1 SP : 2 PP tebal 15 MM


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.3000 95,000.00 28,500.00
Tukang Batu L.02 OH 0.150 120,000.00 18,000.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 170,000.00 2,550.00
JUMLAH TENAGA KERJA 51,300.00
B. BAHAN
PC Kg 10.224 2,350.00 24,026.40
PP M3 0.020 375,000.00 7,500.00
JUMLAH HARGA BAHAN 31,526.40
C. PERALATAN

JUMLAH HARGA PERALATAN 0.00


D Jumlah (A+B+C) 82,826.40
E Overhead + profit 15% x D 12,423.96
F Harga Satuan pekerjaan (D+E) 95,250.36
A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug
NO. URAIAN KODE SATUAN KOEFISIEN
HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.3 95,000.00 28,500.00
Mandor L.04 OH 0.01 170,000.00 1,700.00
JUMLAH TENAGA KERJA 30,200.00
B BAHAN
Pasir urug m3 1.2 374,000.00 448800
JUMLAH HARGA BAHAN 448800
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 479,000.00
E Overhead & Profit (15% x D) 71,850.00
F Harga Satuan Pekerjaan (D+E) 550,850.00
DAFTAR HARGA
UPAH DAN BAHAN

JUMLAH
NO. UPAH DAN BAHAN SATUAN HARGA
(Rp.)

I SATUAN UPAH
1 Pekerja Org/Hari 95,000.00
2 Tukang Org/Hari 120,000.00
3 Kepala Tukang Org/Hari 150,000.00
4 Mandor Org/Hari 170,000.00

II SATUAN BAHAN
1 Tanah Urug M3 300,000.00
2 Tanah Timbunan M3 350,000.00
3 Pasir Urug M3 374,000.00
4 Pasir Kali M3 375,000.00
5 Pasir Beton M3 375,000.00
6 Batu Kali/Batu Belah M3 385,000.00
7 Kerikil Sungai M3 450,000.00
8 Sirtu M3 290,000.00
9 Air Ltr 57.33
10 Semen 50 Kg Zak 68,000.00
11 Semen 50 Kg Kg 2,350.00
12 Besi Beton Kg 16,000.00
13 Kawat Beton Kg 24,000.00
14 Kayu Kls II M3 2,800,000.00
15 Paku Campur Kg 22,000.00
16 Minyak Bekisting Liter 33,000.00
17 Plywood tebal 9 mm Lembar 107,000.00
18 Dolken Kayu (ø 8-10)-pjg 4 m Batang 106,000.00
19 Pipa PVC 2" M 21,000.00
20 Batu Bata Bh 2,500.00
DASAR PERHITUNGAN HARGA (QUARY) BAHAN DAN UPAH KERJA.
PEKERJAAN : PEMBANGUNAN SALURAN DRAINASE WAIHERU KECAMATAN TELUK AMBON
LOKASI : KEC. TELUK AMBON - KOTA AMBON
TAHUN ANGGARAN : 2019

HARGA HARGA
GALIAN C
DASAR ONGKOS ANGKUT DI LOKASI JUMLAH DIBULATKAN
NO U R A I A N SAT
QUARY (25%)
(Rp) (Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 = (4 + 5 + 6) 8 = (7) 9
I UPAH KERJA
1 Pekerja Org/Hari 95,000.00 95,000.00
2 Tukang Org/Hari 120,000.00 120,000.00
3 Kepala Tukang Org/Hari 150,000.00 150,000.00
4 Mandor Org/Hari 170,000.00 170,000.00
II BAHAN
1 Tanah Urug M3 240,000.00 50,000.00 60,000.00 350,000.00 350,000.00 350,000.00
2 Tanah Timbunan M3 264,000.00 50,000.00 66,000.00 380,000.00 380,000.00 380,000.00
3 Pasir Urug M3 280,000.00 50,000.00 70,000.00 400,000.00 400,000.00 400,000.00
4 Pasir Kali M3 304,000.00 50,000.00 76,000.00 430,000.00 430,000.00 430,000.00
5 Pasir Beton M3 304,000.00 50,000.00 76,000.00 430,000.00 430,000.00 430,000.00
6 Batu Kali/Batu Belah M3 304,000.00 50,000.00 76,000.00 430,000.00 430,000.00 430,000.00
7 Kerikil Sungai M3 348,000.00 50,000.00 87,000.00 485,000.00 485,000.00 485,000.00
8 Sirtu M3 192,000.00 50,000.00 48,000.00 290,000.00 290,000.00 290,000.00
9 Air Ltr 75.00 75.00 75.00 0.00
10 Semen 50 Kg Zak 58,000.00 10,000.00 68,000.00 68,000.00 68,000.00
11 Semen 50 Kg Kg 2,350.00 2,350.00
12 Besi Beton Kg 14,000.00 2,000.00 16,000.00 16,000.00 16,000.00
13 Kawat Beton Kg 24,000.00 24,000.00 24,000.00 24,000.00
14 Kayu Kls II M3 2,780,000.00 20,000.00 2,800,000.00 2,800,000.00 2,800,000.00
15 Paku Campur Kg 22,000.00 22,000.00 22,000.00 22,000.00
16 Minyak Bekisting Liter 33,000.00 33,000.00 33,000.00 33,000.00
17 Plywood tebal 9 mm Lembar 106,000.00 1,000.00 107,000.00 107,000.00 107,000.00
18 Dolken Kayu (ø 8-10)-pjg 4 m Batang 106,000.00 106,000.00 106,000.00 106,000.00
19 Batu Bata Bh 2,000.00 500.00 2,500.00 2,500.00 2,500.00