JATIRA ABADI PURCHASE ORDER


Jl. Lumbungsari IV/A-6 Kalicari Pedurungan, DATE # 20/12/2023
Kota Semarang, 50198 PO # 086/XII/23/JTR
Phone: 0821-3338-2020 REFF # 0
Email: jatiraabadi@gmail.com TERM # EACH TERM

SUPPLIER SHIP TO
CV. BERSINERGI KARYA GEMILANG CV. JATIRA ABADI (PROYEK PT. YURO MUSTIKA)
Jl. Gunung Sindoro No. 37B Pabuwaran Kec. Purwokerto Utara Jalan Jendral Ahmad Yani No. 2B Kalikabong,
Kandang Gampang, Kec. Kalimanah,
Kabupaten Purbalingga,
Up. Bp. Yudi Jawa Tengah 53321

NO DESCRIPTION QTY UNIT PRICE TOTAL


1 Pembuatan dan Pengadaan Sipil IPAL 1 SET Rp 394.782.000 Rp 394.782.000,00

PEMBAYARAN (TERMASUK PPN)


TERMIN I (20%, DOWN PAYMENT) = 87.641.604
TERMIN II ( 20%, PEKERJAAN BERJALAN 25%) = 87.641.604
TERMIN III (20%, PEKERJAAN BERJALAN 50%) = 87.641.604
TERMIN IV (20%, PEKERJAAN BERJALAN 75%) = 87.641.604
TERMIN V (15%, PEKERJAAN SELESAI 100%) = 65.731.203
TERMIN VI (5%, SETELAH MASA RETENSEI 6 BULAN) = 21.910.401
SUBTOTAL Rp 394.782.000,00
TAX 11% Rp 43.426.020,00
SHIPPING COST Rp -
OTHER Rp -
COMMISIONING Rp -
TOTAL Rp 438.208.020,00

Comments or Special Instructions Approve by Created by


- Pengiriman Senin s.d Jumat (08.00 -14.00)
- Pengiriman wajib melampirkan Manual Book
- Bila barang tidak sesuai spesifikasi diatas akan kami retur
- Invoice dan faktur pajak rangkap 2 dikirim ke alamat
Jl.Bangetayu Raya Kwaron No. 30 Agus Susanto Vania
RT 01 RW 12
Bangetayu Kulon, Genuk
Kota Semarang

If you have any questions about this purchase order, please contact
WA. 0821-3338-2020
CV. BERSINERGI KARYA
GEMILANG
Jl. Gunung Sindoro No. 37B Pabuwaran Kec. Purwokerto Utara
Email : beka_gemilang@yahoo.co.id

DAFTAR KUANTITAS DAN HARGA


PROYEK : PEMBUATAN IPAL PT. YURO MUSTIKA
LOKASI : PURBALINGGA
PELAKSANAAN : 2023
HARGA JUMLAH HARGA
NO URAIAN KUANTITAS SAT
SATUAN (Rp) (Rp)
I PEKERJAAN PERSIAPAN 9.015.719
1 Uitzet dan bouplank 97,00 m' 65.111 6.315.719
2 Pengurasan air dengan pompa mesin 1,00 ls 2.700.000 2.700.000
-
II PEKERJAAN EQUALISASI - 44.288.006
1 Galian tanah 21,18 m3 81.900 1.734.642
2 Buang Tanah 21,18 m3 40.500 857.790
3 Lantai kerja beton 1:3:5 0,30 m3 747.212 224.164
4 Cor beton 1:2:3 12,71 m3 986.329 12.536.240
5 Pembesian 734,00 kg 20.250 14.863.500
6 Begisteng 64,22 m2 157.902 10.140.486
7 Plesteran dinding 78,51 m2 50.072 3.931.184
-
III PEKERJAAN INTERMEDIATE I - 32.289.056
1 Galian tanah 17,88 m3 81.900 1.464.372
2 Buang Tanah 17,88 m3 40.500 724.140
3 Lantai kerja beton 1:3:5 0,25 m3 747.212 186.803
4 Cor beton 1:2:3 9,229 m3 986.329 9.102.829
5 Pembesian 454,92 kg 20.250 9.212.130
6 Begisteng 56,10 m2 157.902 8.858.319
7 Plesteran dinding 54,73 m2 50.072 2.740.462
-
IV PEKERJAAN INTERMEDIATE II - 14.414.506
1 Galian tanah 3,47 m3 81.900 284.193
2 Buang Tanah 3,47 m3 40.500 140.535
3 Lantai kerja beton 1:3:5 0,09 m3 747.212 67.249
4 Cor beton 1:2:3 4,367 m3 986.329 4.307.298
5 Pembesian 244,59 kg 20.250 4.952.948
6 Begisteng 20,79 m2 157.902 3.282.789
7 Plesteran dinding 27,55 m2 50.072 1.379.495
-
V PEKERJAAN OPERATOR - 38.456.387
1 Galian tanah - m3 81.900
2 Buang Tanah - m3 40.500
3 Lantai kerja beton 1:3:5 0,32 m3 747.212 239.108
4 Cor beton 1:2:3 3,847 m3 986.329 3.794.407
5 Pembesian 867,89 kg 20.250 17.574.773
6 Begisteng 42,51 m2 157.902 6.712.427
7 Plesteran dinding 80,83 m2 50.072 4.047.352
8 Pasangan bata 56,00 m2 108.720 6.088.320
-
VI PEKERJAAN BIOLOGI 1 - 55.897.651
1 Galian tanah 20,63 m3 81.900 1.689.597
2 Buang Tanah 20,63 m3 40.500 835.515
3 Lantai kerja beton 1:3:5 0,75 m3 747.212 560.409
4 Cor beton 1:2:3 17,71 m3 986.329 17.467.885
5 Pembesian 873,54 kg 20.250 17.689.185
6 Begisteng 82,23 m2 157.902 12.984.306
7 Plesteran dinding 93,28 m2 50.072 4.670.753
-
VII PEKERJAAN BIOLOGI 2 - 80.918.856
1 Galian tanah 20,63 m3 81.900 1.689.597
2 Buang Tanah 20,63 m3 40.500 835.515
3 Lantai kerja beton 1:3:5 0,750 m3 747.212 560.409
4 Cor beton 1:2:3 22,190 m3 986.329 21.886.638
5 Pembesian 1.313,84 kg 20.250 26.605.260
6 Begisteng 135,85 m2 157.902 21.451.027
7 Plesteran dinding 157,58 m2 50.072 7.890.409
-
VIII PEKERJAAN DRYING BED - 38.919.871
1 Galian tanah - m3 81.900
2 Buang Tanah m3 40.500
3 Lantai kerja beton 1:3:5 0,750 m3 747.212 560.409
4 Cor beton 1:2:3 12,300 m3 986.329 12.131.845
5 Pembesian 710,46 kg 20.250 14.386.815
6 Begisteng 51,04 m2 157.902 8.059.333
7 Plesteran dinding 75,52 m2 50.072 3.781.468
-
IX PEKERJAAN CLARIFIER TANK - 30.479.162
1 Galian tanah 15,55 m3 81.900 1.273.545
2 Buang Tanah 15,55 m3 40.500 629.775
3 Lantai kerja beton 1:3:5 0,59 m3 747.212 440.855
4 Cor beton 1:2:3 9,500 m3 986.329 9.370.125
5 Pembesian 423,76 kg 20.250 8.581.140
6 Begisteng 44,24 m2 157.902 6.985.598
7 Plesteran dinding 63,87 m2 50.072 3.198.124
-
X PEKERJAAN REACTION TANK - 34.124.202
1 Galian tanah - m3 81.900
2 Buang Tanah m3 40.500
3 Lantai kerja beton 1:3:5 0,39 m3 747.212 291.413
4 Cor beton 1:2:3 12,30 m3 986.329 12.131.845
5 Pembesian 543,32 kg 20.250 11.002.230
6 Begisteng 41,45 m2 157.902 6.545.050
7 Plesteran dinding 50,60 m2 50.072 2.533.663
8 Tangga Layanan 3,00 m 540.000 1.620.000
-
XI PEKERJAAN TAMBAHAN ( 3 BAK KONTROL) - 15.979.288
1 Galian Tanah 1,98 m3 81.900 162.162
2 Buang Tanah 1,98 m3 40.500 80.190
3 Lantau Kerja Beton 1:3:5 0,096 m3 747.212 71.732
4 Pasangan Bata 9,6 m2 108.720 1.043.712
5 Plesteran 23,2 m2 50.072 1.161.680
6 Pembesian 84,65 kg 20.250 1.714.163
7 Cor Beton 1:2:3 0,126 m3 986.329 124.277
8 Pipa 1 1/2" 181,5 m' 64.030 11.621.372

JUMLAH 394.782.703
DIBULATKAN 394.782.000
Terbilang : Tiga Ratus Semilan Puluh Empat Juta Tujuh Ratus
Delapan Puluh Dua Ribu Rupiah

Purwokerto, Agustus 2023


Penyadia Jasa
CV. BERSINERGI KARYA GEMILANG

YUDI SETIAWAN
Direktur