REKAPITULASI LAPORAN MINGGUAN

NAMA KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM


PEKERJAAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KABUPATEN/KOTA
LOKASI : DESA OELET KECAMATAN AMANUBAN TIMUR
TAHUN : 2023
Minggu Ke : 26 23 November 2023 s/d 29 November 2023

JUMLAH S/D MINGGU LALU MINGGU INI S/D MINGGU INI


No URAIAN PEKERJAAN HARGA BOBOT (%) KET.
JUMLAH HARGA (Rp) BOBOT (%) JUMLAH HARGA (Rp) BOBOT (%) JUMLAH HARGA (Rp) BOBOT (%)
(RP.)
1 2 3 4 5 6 7 8 9 10 11
I PEKERJAAN PERSIAPAN 9,887,500.00 0.76 9,887,500.00 0.76 - - 9,887,500.00 0.76
II MATA AIR OEUKI - DESA OELET - - -
A PEKERJAAN PEMBANGUNAN BRONCAPTERING (Q : 1 Lt/dtk)) 5,467,729.97 0.42 5,467,729.97 0.42 - - 5,467,729.97 0.42
B PEKERJAAN BAK POMPA 118,676,925.83 9.12 103,784,270.26 9.00 1,500,000.00 0.12 103,784,270.26 9.12
C PEKERJAAN PAGAR BRC KELILING SOLARCEL - - - - - - - -
D PEKERJAAN PENGADAAN DAN PEMASANGAN POMPA SUBMERSIBLE & PANEL SURYA 113,143,285.00 8.69 84,239,921.50 6.47 28,903,363.50 2.22 113,143,285.00 8.69
III PEKERJAAN PEMBANGUNAN PIPA JARINGAN TRANSMISI - - -
A PEKERJAAN PEMBANGUNAN PIPA JARINGAN TRANSMISI (BAK PENGUMPUL - RESERVOIR KAP. 50 M3) - - -
a Pengadaan dan Pemasangan Pipa HDPE Ø 50 mm PN 16 141,705,953.16 10.89 139,081,153.16 10.69 2,624,800.00 0.20 141,705,953.16 10.89
b Pekerjaan Thrustblock 1,063,768.28 0.08 1,063,768.28 0.08 - - 1,063,768.28 0.08
IV PEKERJAAN BANGUNAN BAK RESERVOIR(50 M3) 137,265,717.40 10.55 132,834,547.08 10.21 4,431,170.32 0.34 137,265,717.40 10.55
V PEKERJAAN PEMBANGUNAN PIPA JARINGAN DISTRIBUSI - - -
A PENGADAAN & PEMASANGAN PIPA DARI RV KE KANTOR DESA - - -
a Pengadaan dan Pemasangan Pipa HDPE Ø 50 mm PN 10 244,678,842.57 18.80 239,120,442.57 18.37 5,558,400.00 0.43 244,678,842.57 18.80
b Pengadaan dan Pemasangan Pipa HDPE Ø 32 mm PN 16 79,842,304.92 6.13 73,013,453.45 5.61 6,828,851.48 0.52 79,842,304.92 6.13
c Pekerjaan Wash Out 2,256,488.82 0.17 1,146,444.41 0.09 1,110,044.41 0.09 2,256,488.82 0.17
d Pekerjaan Air Valve 2,556,488.82 0.20 2,092,888.82 0.16 463,600.00 0.04 2,556,488.82 0.20
B PENGADAAN & PEMASANGAN PIPA DARI RV KE ARAH KE MATA AIR - - -
a Pengadaan dan Pemasangan Pipa HDPE Ø 50 mm PN 10 79,328,847.53 6.10 77,630,447.53 5.96 1,698,400.00 0.13 79,328,847.53 6.10
b Pengadaan dan Pemasangan Pipa HDPE Ø 32 mm PN 16 21,628,644.80 1.66 20,856,644.80 1.60 772,000.00 0.06 21,628,644.80 1.66
VI PEKERJAAN SAMBUNGAN RUMAH 320,466,965.67 24.62 296,973,770.99 22.82 23,493,194.68 1.81 320,466,965.67 24.62
VII PEKERJAAN BAK KONTROL 60 x 60 cm 21,512,014.93 1.65 13,012,669.97 1.00 8,499,344.96 0.65 21,512,014.93 1.65
VIII PEKERJAAN PENYELESAIAN -
- Pembersihan Kembali Lokasi 2,000,000.00 0.15 - - 2,000,000.00 0.15 2,000,000.00 0.15
JUMLAH TOTAL 1,301,481,477.71 100.00 1,200,205,652.80 93.25 87,883,169.34 6.75 1,286,588,822.14 100.00

SoE, 29 November 2023


Diperiksa : Diperiksa : Dibuat Oleh :
Tim Teknis Lapangan Tim Teknis Lapangan Konsultan Pengawas
Dinas PRKP Kab. TTS Dinas PRKP Kab. TTS CV. Indo Design Konsultan

Rinaldy Mesakh Kase, ST Otnial Lakapu Luter T. J. Beliu, A.Md


NIP. 19900925 202012 1 003 Inspector
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

NAMA KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM


PEKERJAAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KABUPATEN/KOTA
LOKASI : DESA OELET KECAMATAN AMANUBAN TIMUR
TAHUN ANGGARAN : 2023 Minggu Ke : 26 23 November 2023 s/d 29 November 2023

HARGA JUMLAH S/D MINGGU LALU MINGGU INI S/D MINGGU INI

SATUAN

BOBOT
VOLUME

KET.
(%)
NO URAIAN PEKERJAAN SATUAN HARGA JUMLAH HARGA JUMLAH HARGA JUMLAH HARGA
(Rp) VOL. BOBOT (%) VOL. BOBOT (%) VOL. BOBOT (%)
(Rp.) (Rp.) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 16 16 17

I PEKERJAAN PERSIAPAN
- Pembersihan Lokasi Ls 1.00 2,000,000.00 2,000,000.00 0.15 1.00 2,000,000.00 0.15 - - 1.00 2,000,000.00 0.15
- Pengukuran Dan Pematokan Ls 1.00 2,500,000.00 2,500,000.00 0.19 1.00 2,500,000.00 0.19 - - 1.00 2,500,000.00 0.19
- Biaya K3 Ls 1.00 4,767,500.00 4,767,500.00 0.37 1.00 4,767,500.00 0.37 - - 1.00 4,767,500.00 0.37
- Pemasangan Papan nama Ls 1.00 620,000.00 620,000.00 0.05 1.00 620,000.00 0.05 - - 1.00 620,000.00 0.05
Jumlah Harga Pekerjaan 9,887,500.00 0.76 9,887,500.00 0.76 - - 9,887,500.00 0.76
II MATA AIR OEUKI - DESA OELET
A PEKERJAAN PEMBANGUNAN BRONCAPTERING (Q : 1 Lt/dtk))
1 Pekerjaan Tanah
3
- Galian Tanah Biasa M 1.84 76,331.00 140,449.04 0.01 1.84 140,449.04 0.01 - - 1.84 140,449.04 0.01
- Pasangan Batu Kali 1PC : 4PS M3 2.52 938,806.00 2,365,791.12 0.18 2.52 2,365,791.12 0.18 - - 2.52 2,365,791.12 0.18
- Pekerjaan Beton Plat atap Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 0.02 1,264,636.00 30,351.26 0.00 0.02 30,351.26 0.00 - - 0.02 30,351.26 0.00
- Pekerjaan pembesian plat atap bak pengumpul Kg 10.30 18,181.90 187,237.50 0.01 10.30 187,237.50 0.01 - - 10.30 187,237.50 0.01
- Pekerjaan bekisting plat atap bak pengumpul M2 0.16 351,540.00 56,246.40 0.00 0.16 56,246.40 0.00 - - 0.16 56,246.40 0.00
- Plesteran 1PC : 5PS M² 5.28 64,266.00 339,324.48 0.03 5.28 339,324.48 0.03 - - 5.28 339,324.48 0.03
- Acian M² 5.28 37,436.00 197,662.08 0.02 5.28 197,662.08 0.02 - - 5.28 197,662.08 0.02
Pengecatan M2 5.28 41,662.00 219,975.36 0.02 5.28 219,975.36 0.02 - - 5.28 219,975.36 0.02
- Batu Pecah 1-2 M3 0.20 324,632.65 64,926.53 0.00 0.20 64,926.53 0.00 - - 0.20 64,926.53 0.00
- Batu Pecah 3-5 M3 0.20 349,632.65 69,926.53 0.01 0.20 69,926.53 0.01 - - 0.20 69,926.53 0.01
- Pipa GIP dia. 1.5" M' 12.00 95,439.66 1,145,275.92 0.09 12.00 1,145,275.92 0.09 - - 12.00 1,145,275.92 0.09
- Elbow GIP dia. 1.5" Bh 1.00 30,963.75 30,963.75 0.00 1.00 30,963.75 0.00 - - 1.00 30,963.75 0.00
- Gate Valve dia. 1.5" Bh 1.00 225,000.00 225,000.00 0.02 1.00 225,000.00 0.02 - - 1.00 225,000.00 0.02
- Nippel dia. 1.5" Bh 2.00 21,300.00 42,600.00 0.00 2.00 42,600.00 0.00 - - 2.00 42,600.00 0.00
- Watermur dia. 1.5" Bh 1.00 72,400.00 72,400.00 0.01 1.00 72,400.00 0.01 - - 1.00 72,400.00 0.01
- Dob dia. 1.5" Bh 1.00 29,600.00 29,600.00 0.00 1.00 29,600.00 0.00 - - 1.00 29,600.00 0.00
- Katup Screen Buah 1.00 250,000.00 250,000.00 0.02 1.00 250,000.00 0.02 - - 1.00 250,000.00 0.02
TOTAL PEKERJAAN PEMBANGUNAN BRONCAPTERING 5,467,729.97 0.42 5,467,729.97 0.42 - - 5,467,729.97 0.42
B PEKERJAAN BAK POMPA
- Galian tanah M3 31.52 76,331.00 2,405,953.12 0.18 31.52 2,405,953.12 0.18 - - 31.52 2,405,953.12 0.18
- Urugan Tanah Kembali M3 2.67 27,456.00 73,216.00 0.01 2.67 73,216.00 0.01 - - 2.67 73,216.00 0.01
- Urugan Pasir M3 1.30 264,625.00 343,350.94 0.03 1.30 343,350.94 0.03 - - 1.30 343,350.94 0.03
- Urugan Batu Kosong M3 6.86 492,246.00 3,378,776.54 0.26 6.86 3,378,776.54 0.26 - - 6.86 3,378,776.54 0.26
- Pasangan Pondasi M3 0.77 938,806.00 718,186.59 0.06 0.77 718,186.59 0.06 - - 0.77 718,186.59 0.06
- Plesteran Pondasi M3 0.75 64,266.00 48,199.50 0.00 0.75 48,199.50 0.00 - - 0.75 48,199.50 0.00
- Beton Tumbuk mutu f’= 9,8 MPa (K 100) M6 2.27 1,086,304.00 2,468,082.69 0.19 2.27 2,468,082.69 0.19 - - 2.27 2,468,082.69 0.19
- Pekerjaan Beton Lantai Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 4.21 1,264,636.00 5,328,543.79 0.41 4.21 5,328,543.79 0.41 - - 4.21 5,328,543.79 0.41
- Pekerjaan Beton Dinding atap Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 8.78 1,264,636.00 11,097,180.90 0.85 8.78 11,097,180.90 0.85 - - 8.78 11,097,180.90 0.85
- Pekerjaan Beton Plat atap Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 3.20 1,264,636.00 4,041,776.66 0.31 3.20 4,041,776.66 0.31 - - 3.20 4,041,776.66 0.31
- Pekerjaan pembesian lantai bak pengumpul Kg 252.23 18,181.90 4,586,027.39 0.35 252.23 4,586,027.39 0.35 - - 252.23 4,586,027.39 0.35
- Pekerjaan pembesian dinding bak pengumpul Kg 712.34 18,181.90 12,951,629.27 1.00 712.34 12,951,629.27 1.00 - - 712.34 12,951,629.27 1.00
- Pekerjaan pembesian plat atap bak pengumpul Kg 213.52 18,181.90 3,882,272.66 0.30 213.52 3,882,272.66 0.30 - - 213.52 3,882,272.66 0.30
- Pekerjaan bekisting lantai bak pengumpul M2 2.58 389,217.00 1,004,179.86 0.08 2.58 1,004,179.86 0.08 - - 2.58 1,004,179.86 0.08
- Pekerjaan bekisting dinding bak pengumpul M2 120.80 351,540.00 42,464,836.76 3.26 120.80 42,464,836.76 3.26 - - 120.80 42,464,836.76 3.26
- Pekerjaan bekisting plat atap bak pengumpul M2 22.33 389,217.00 8,691,215.61 0.67 22.33 8,691,215.61 0.67 - - 22.33 8,691,215.61 0.67
- Acian M2 118.71 37,436.00 4,444,027.56 0.34 118.71 4,444,027.56 0.34 - - 118.71 4,444,027.56 0.34
- Pengecatan M2 118.71 41,662.00 4,945,696.02 0.38 118.71 4,945,696.02 0.38 - - 118.71 4,945,696.02 0.38
- Media Penyaring Ls 1.00 250,000.00 250,000.00 0.02 1.00 250,000.00 0.02 - - 1.00 250,000.00 0.02
- Tutupan Manhole Buah 2.00 862,500.00 1,725,000.00 0.13 2.00 1,725,000.00 0.13 - - 2.00 1,725,000.00 0.13
Pipa Hawa Buah 1.00 60,000.00 60,000.00 0.00 1.00 60,000.00 0.00 - - 1.00 60,000.00 0.00
- Engsel Buah 4.00 14,750.00 59,000.00 0.00 4.00 59,000.00 0.00 - - 4.00 59,000.00 0.00
- Kunci Gembok Buah 3.00 10,000.00 30,000.00 0.00 3.00 30,000.00 0.00 - - 3.00 30,000.00 0.00
- Katup Saringan Buah 1.00 250,000.00 250,000.00 0.02 1.00 250,000.00 0.02 - - 1.00 250,000.00 0.02
- Pipa Penguras GIP dia. 1.5" M' 2.00 95,439.66 190,879.32 0.01 2.00 190,879.32 0.01 - - 2.00 190,879.32 0.01
- Pipa Overflow GIP dia. 1.5" M' 1.00 95,439.66 95,439.66 0.01 1.00 95,439.66 0.01 - - 1.00 95,439.66 0.01
- Elbow GIP dia. 1.5" Buah 4.00 30,963.75 123,855.00 0.01 4.00 123,855.00 0.01 - - 4.00 123,855.00 0.01
- Gate Valve dia. 1.5" Buah 1.00 225,000.00 225,000.00 0.02 1.00 225,000.00 0.02 - - 1.00 225,000.00 0.02
- Nippel dia. 1.5" Buah 2.00 21,300.00 42,600.00 0.00 2.00 42,600.00 0.00 - - 2.00 42,600.00 0.00
- Watermur dia. 1.5" Buah 1.00 72,400.00 72,400.00 0.01 1.00 72,400.00 0.01 - - 1.00 72,400.00 0.01
- Dob dia. 1.5" Buah 1.00 29,600.00 29,600.00 0.00 1.00 29,600.00 0.00 - - 1.00 29,600.00 0.00
- Tangga Kontrol Buah 2.00 575,000.00 1,150,000.00 0.09 2.00 1,150,000.00 0.09 - - 2.00 1,150,000.00 0.09
- Pengadaan dan Pekerjaan pintu teralis besi ø 12 mm Buah 1.00 1,500,000.00 1,500,000.00 0.12 - - - 1.00 1,500,000.00 0.12 1.00 1,500,000.00 0.12
TOTAL PEKERJAAN BAK PENGUMPUL 118,676,925.83 9.12 117,176,925.83 9.00 1,500,000.00 0.12 118,676,925.83 9.12
C PEKERJAAN PAGAR BRC KELILING SOLARCEL
- Galian tanah M3 - 76,331.00 - - - - - - - - - -
- Urugan Tanah Kembali M3 - 27,456.00 - - - - - - - - - -
- Pasangan Batu Kosong M3 - 492,246.00 - - - - - - - - - -
- Pasangan Pondasi Batu Kali 1PC : 4PS M3 - 938,806.00 - - - - - - - - - -
- Sloof Beton K-125 M3 - 1,128,328.00 - - - - - - - - - -
- Pembesian Sloof Kg - 18,181.90 - - - - - - - - - -
- Bekisting Sloof M2 - 389,217.00 - - - - - - - - - -
- Pemasangan Pagar BRC Lengkap Dengan Tiang M1 - 500,000.00 - - - - - - - - - -
- Pintu Pagar BRC Bh - 1,200,000.00 - - - - - - - - - -
- - - - - - - -
D PEKERJAAN PENGADAAN DAN PEMASANGAN POMPA SUBMERSIBLE & PANEL SURYA
- Pengadaan Pompa Submersible + Controler Tenaga Surya PS4000 C-SJ 3-32 set - - - - - - - - - - -
- Pengadaan Pompa. Type submersible power 2.2. kwh/3x380 head 128m + panel control + asesoris dan jasa pemasangan
Unit 1.00 96,344,545.00 96,344,545.00 7.40 0.70 67,441,181.50 5.18 0.30 28,903,363.50 2.22 1.00 96,344,545.00 7.40
- Modul Surya 5600 wp (Mono) SNI/TKDN wp - - - - - - - - - - -
- Powerpack 4000 set - - - - - - - - - - -
- Meterlistrik 7700 + Kabel + asesories set - - - - - - - - - - - -
- Meter Listrik 6600 VA + Kabel + Asesories dan jasa pemasangan Unit 1.00 15,788,740.00 15,788,740.00 1.21 1.00 15,788,740.00 1.21 - - - 1.00 15,788,740.00 1.21
- Panel Support (Tiang Penyangga Panel Surya) set - - - - - - - - - - -
- Kabel Power Cell/Kabel Array 10mm M' - - - - - - - - - - -
- Kabel Pompa NYYHY 4 x 10 mm M' - - - - - - - - - - -
- Kabel Sensor NYYHY 2 x 0.75 mm M' - - - - - - - - - - -
- Lem Kabel Set 1.00 400,000.00 400,000.00 0.03 1.00 400,000.00 0.03 - - - 1.00 400,000.00 0.03
- PV Disconek Set - - - - - - - - - - -
- Surge Protector Set - - - - - - - - - - -
- Kawat Seling Ls 1.00 610,000.00 610,000.00 0.05 1.00 610,000.00 0.05 - - - 1.00 610,000.00 0.05
- Aksesories (mur,baut,kabel tist, dll) set - - - - - - - - - - -
- Biaya Transportasi Ls -
- Instalasi Pompa dan Setting Pompa (Teknisi Pompa dan Panel Surya) Ls -

TOTAL PEKERJAAN PENGADAAN DAN PEMASANGAN POMPA SUBMERSIBLE & PANEL SURYA 113,143,285.00 8.69 - 84,239,921.50 6.47 28,903,363.50 2.22 113,143,285.00 8.69
III PEKERJAAN PEMBANGUNAN PIPA JARINGAN TRANSMISI
A PEKERJAAN PEMBANGUNAN PIPA JARINGAN TRANSMISI (BAK PENGUMPUL - RESERVOIR KAP. 50 M3)
a Pengadaan dan Pemasangan Pipa HDPE Ø 50 mm PN 16
i Pengadaan Material pipa HDPE Ø 50 mm beserta assesoris
- Coupler 50 mm Buah 12.00 137,500.00 1,650,000.00 0.13 12.00 1,650,000.00 0.13 - - - 12.00 1,650,000.00 0.13
- Check Valve 1.5" Buah 1.00 350,000.00 350,000.00 0.03 1.00 350,000.00 0.03 - - 1.00 350,000.00 0.03
- Male 50 mm Buah 4.00 150,000.00 600,000.00 0.05 4.00 600,000.00 0.05 - - - 4.00 600,000.00 0.05
- Female 50 mm Buah 2.00 150,000.00 300,000.00 0.02 2.00 300,000.00 0.02 - - - 2.00 300,000.00 0.02
Sub Jumlah 1 2,900,000.00 0.22 2,900,000.00 0.22 - - 2,900,000.00 0.22
ii Konstruksi Pemasangan pipa HDPE Ø 50mm
- Galian Tanah M3 108.96 74,981.25 8,169,944.91 0.63 108.96 8,169,944.91 0.63 - - 108.96 8,169,944.91 0.63
- Urugan Tanah Kembali M3 90.56 26,273.40 2,379,208.25 0.18 90.56 2,379,208.25 0.18 - - 90.56 2,379,208.25 0.18
- Pengadaan & Pemasangan Pipa HDPE Ø 50 mm PN 10 M' 500.00 58,664.00 29,332,000.00 2.25 500.00 29,332,000.00 2.25 - - 500.00 29,332,000.00 2.25
- Pengadaan & Pemasangan Pipa HDPE Ø 50 mm PN 16 M' 1,200.00 80,250.00 96,300,000.00 7.40 1,200.00 96,300,000.00 7.40 - - 1,200.00 96,300,000.00 7.40
- Uji coba pengaliran M' 1,700.00 1,544.00 2,624,800.00 0.20 - - - 1,700.00 2,624,800.00 0.20 1,700.00 2,624,800.00 0.20
Sub Jumlah 2 138,805,953.16 10.67 136,181,153.16 10.46 2,624,800.00 0.20 138,805,953.16 10.67
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI HDPE DIAMETER 63 MM 141,705,953.16 10.89 139,081,153.16 10.69 2,624,800.00 0.20 141,705,953.16 10.89
b Pekerjaan Thrustblock
- Galian tanah M3 0.10 76,331.00 7,633.10 0.00 0.10 7,633.10 0.00 - - 0.10 7,633.10 0.00
- Beton Tumbuk mutu f’= 9,8 MPa (K 100) M3 0.14 1,086,304.00 146,651.04 0.01 0.14 146,651.04 0.01 - - 0.14 146,651.04 0.01
- Angker Moer Baut Ø 16 mm - 25 cm Buah 4.00 30,000.00 120,000.00 0.01 4.00 120,000.00 0.01 - - 4.00 120,000.00 0.01
- Clamp Pipa Plat Strip 50.05 Buah 2.00 128,800.00 257,600.00 0.02 2.00 257,600.00 0.02 - - 2.00 257,600.00 0.02
TOTAL PEKERJAAN THRUST BLOCK 531,884.14 0.04 531,884.14 0.04 - - 531,884.14 0.04
JUMLAH 2 UNIT 1,063,768.28 0.08 531,884.14 0.08 - - 1,063,768.28 0.08
IV PEKERJAAN BANGUNAN BAK RESERVOIR(50 M3)
Pekerjaan tanah
- Galian tanah M3 24.00 76,331.00 1,831,944.00 0.14 24.00 1,831,944.00 0.14 - - 24.00 1,831,944.00 0.14
- Urugan Kembali M3 7.20 27,456.00 197,683.20 0.02 7.20 197,683.20 0.02 - - 7.20 197,683.20 0.02
- Urugan Pasir M3 2.39 264,625.00 632,453.75 0.05 2.39 632,453.75 0.05 - - - 2.39 632,453.75 0.05
Sub Jumlah 2 2,662,080.95 0.20 2,662,080.95 0.20 - - 2,662,080.95 0.20
Pekerjaan Struktur
- Pekerjaan Pasangan Batu Kosong M3 4.80 492,246.00 2,362,780.80 0.18 4.80 2,362,780.80 0.18 - - 4.80 2,362,780.80 0.18
- Pasangan Batu (1:4) M3 13.20 938,806.00 12,392,239.20 0.95 13.20 12,392,239.20 0.95 - - 13.20 12,392,239.20 0.95
- Beton Tumbuk mutu f’= 9,8 MPa (K 100) M3 4.58 1,086,304.00 4,980,160.69 0.38 4.58 4,980,160.69 0.38 - - 4.58 4,980,160.69 0.38
- Lantai Beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58 M3 4.21 1,264,636.00 5,328,543.79 0.41 4.21 5,328,543.79 0.41 - - 4.21 5,328,543.79 0.41
- Beton Dinding mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58 M3 8.12 1,264,636.00 10,266,315.05 0.79 8.12 10,266,315.05 0.79 - - 8.12 10,266,315.05 0.79
- Plat Penutup Beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58 M2 3.75 1,264,636.00 4,742,385.00 0.36 3.75 4,742,385.00 0.36 - - 3.75 4,742,385.00 0.36
- Pembesian Lantai kg 327.49 18,181.90 5,954,475.23 0.46 327.49 5,954,475.23 0.46 - - 327.49 5,954,475.23 0.46
- Pembesian Dinding kg 666.96 18,181.90 12,126,533.35 0.93 666.96 12,126,533.35 0.93 - - 666.96 12,126,533.35 0.93
- Pembesian Plat Beton Penutup kg 309.08 18,181.90 5,619,707.50 0.43 309.08 5,619,707.50 0.43 - - 309.08 5,619,707.50 0.43
- Bekisting lantai reservoir M2 2.58 389,217.00 1,004,179.86 0.08 2.58 1,004,179.86 0.08 - - 2.58 1,004,179.86 0.08
- Bekisting dinding & sekat reservoir M2 107.62 351,540.00 37,831,223.18 2.91 107.62 37,831,223.18 2.91 - - 107.62 37,831,223.18 2.91
- Bekisting plat atap reservoir M2 28.00 389,217.00 10,898,076.00 0.84 28.00 10,898,076.00 0.84 - - 28.00 10,898,076.00 0.84
- Plesteran M2 106.36 67,564.00 7,186,107.04 0.55 106.36 7,186,107.04 0.55 - - - 106.36 7,186,107.04 0.55
- Acian M2 106.36 37,436.00 3,981,692.96 0.31 106.36 3,981,692.96 0.31 - - - 106.36 3,981,692.96 0.31
- Pengecatan Bak M2 106.36 41,662.00 4,431,170.32 0.34 - - - 106.36 4,431,170.32 0.34 106.36 4,431,170.32 0.34
Sub Jumlah 3 129,105,589.96 9.92 124,674,419.64 9.58 4,431,170.32 0.34 129,105,589.96 9.92
Pekerjaan Pelengkap Accessories
- Pipa Inlet GIP Ø 1.5" M1 6.00 95,439.66 572,637.96 0.04 6.00 572,637.96 0.04 - - 6.00 572,637.96 0.04
- Pipa Outlet GIP Ø 1.5" M1 6.00 95,439.66 572,637.96 0.04 6.00 572,637.96 0.04 - - 6.00 572,637.96 0.04
- Pipa OverFlow GIP Ø 1.5" M1 1.00 95,439.66 95,439.66 0.01 1.00 95,439.66 0.01 - - 1.00 95,439.66 0.01
- Pipa Penguras+ Peluap GIP Ø 1.5" M1 1.00 95,439.66 95,439.66 0.01 1.00 95,439.66 0.01 - - 1.00 95,439.66 0.01
- Gate Valve Ø 1.5" Buah 1.00 225,000.00 225,000.00 0.02 1.00 225,000.00 0.02 - - 1.00 225,000.00 0.02
- Bend GIP 90ᴼ Dia.Ø 1.5" Buah 3.00 30,963.75 92,891.25 0.01 3.00 92,891.25 0.01 - - 3.00 92,891.25 0.01
- Tee GIP Ø 1.5" Buah 2.00 75,000.00 150,000.00 0.01 2.00 150,000.00 0.01 - - 2.00 150,000.00 0.01
- Doble Nippel GIP Ø 1.5" Buah 2.00 21,300.00 42,600.00 0.00 2.00 42,600.00 0.00 - - 2.00 42,600.00 0.00
- Watermur GIP Ø 1.5" Buah 1.00 72,400.00 72,400.00 0.01 1.00 72,400.00 0.01 - - 1.00 72,400.00 0.01
- Pipa Udara Buah 2.00 287,500.00 575,000.00 0.04 2.00 575,000.00 0.04 - - 2.00 575,000.00 0.04
- Tangga Besi Buah 2.00 575,000.00 1,150,000.00 0.09 2.00 1,150,000.00 0.09 - - 2.00 1,150,000.00 0.09
- Engsel Pasang 4.00 14,750.00 59,000.00 0.00 4.00 59,000.00 0.00 - - 4.00 59,000.00 0.00
- Gembok Buah 2.00 35,000.00 70,000.00 0.01 2.00 70,000.00 0.01 - - 2.00 70,000.00 0.01
- Tutup Manhole dari plat baja Buah 2.00 862,500.00 1,725,000.00 0.13 2.00 1,725,000.00 0.13 - - 2.00 1,725,000.00 0.13
Sub Jumlah 4 5,498,046.49 0.42 5,498,046.49 0.42 - - 5,498,046.49 0.42
TOTAL PEKERJAAN BANGUNAN BAK RESERVOIR 50 M3 137,265,717.40 10.55 132,834,547.08 10.21 4,431,170.32 0.34 137,265,717.40 10.55
V PEKERJAAN PEMBANGUNAN PIPA JARINGAN DISTRIBUSI
A PENGADAAN & PEMASANGAN PIPA DARI RV KE KANTOR DESA
a Pengadaan dan Pemasangan Pipa HDPE Ø 50 mm PN 10
i Pengadaan Material pipa HDPE Ø 50 mm beserta assesoris
- Coupler 50 mm Buah 36.00 137,500.00 4,950,000.00 0.38 36.00 4,950,000.00 0.38 - - - 36.00 4,950,000.00 0.38
- End Cup 50 mm Buah 1.00 102,440.00 102,440.00 0.01 1.00 102,440.00 0.01 - - 1.00 102,440.00 0.01
Sub Jumlah 1 5,052,440.00 0.39 5,052,440.00 0.39 - - 5,052,440.00 0.39
ii Kontruksi Pemasangan pipa HDPE Ø 50 mm
- Galian Tanah M3 230.74 76,331.00 17,612,498.51 1.35 230.74 17,612,498.51 1.35 - - - 230.74 17,612,498.51 1.35
- Urugan Tanah Kembali M3 191.77 27,456.00 5,265,104.06 0.40 191.77 5,265,104.06 0.40 - - - 191.77 5,265,104.06 0.40
- Pengadaan & Pemasangan Pipa HDPE Ø 50 mm M' 3,600.00 58,664.00 211,190,400.00 16.23 3,600.00 211,190,400.00 16.23 - - 3,600.00 211,190,400.00 16.23
- Uji coba pengaliran M' 3,600.00 1,544.00 5,558,400.00 0.43 - - - 3,600.00 5,558,400.00 0.43 3,600.00 5,558,400.00 0.43
Sub Jumlah 2 239,626,402.57 18.41 234,068,002.57 17.98 5,558,400.00 0.43 239,626,402.57 18.41
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI HDPE DIAMETER 50 MM 244,678,842.57 18.80 239,120,442.57 18.37 5,558,400.00 0.43 244,678,842.57 18.80
b Pengadaan dan Pemasangan Pipa HDPE Ø 32 mm PN 16
i Pengadaan Material pipa HDPE Ø 32 mm beserta assesoris
- Coupler 32 mm Buah 8.00 79,350.00 634,800.00 0.05 8.00 634,800.00 0.05 - - - 8.00 634,800.00 0.05
- End Cup 32 mm Buah 2.00 72,000.00 144,000.00 0.01 2.00 144,000.00 0.01 - - - 2.00 144,000.00 0.01
Sub Jumlah 1 778,800.00 0.06 778,800.00 0.06 - - 778,800.00 0.06
ii Kontruksi Pemasangan pipa HDPE Ø 32 mm
- Galian Tanah M3 128.19 76,331.00 9,784,721.39 0.75 89.73 6,849,304.98 0.53 38.46 2,935,416.42 0.23 128.19 9,784,721.39 0.75
- Urugan Tanah Kembali M3 106.54 25,200.67 2,684,783.53 0.21 74.58 1,879,348.47 0.14 31.96 805,435.06 0.06 106.54 2,684,783.53 0.21
- Pengadaan & Pemasangan Pipa HDPE Ø 32 mm M' 2,000.00 31,753.00 63,506,000.00 4.88 2,000.00 63,506,000.00 4.88 - - - 2,000.00 63,506,000.00 4.88
- Uji coba pengaliran M' 2,000.00 1,544.00 3,088,000.00 0.24 - - - 2,000.00 3,088,000.00 0.24 2,000.00 3,088,000.00 0.24
Sub Jumlah 2 79,063,504.92 6.07 72,234,653.45 5.55 6,828,851.48 0.52 79,063,504.92 6.07
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI HDPE DIAMETER 50 MM 79,842,304.92 6.13 73,013,453.45 5.61 6,828,851.48 0.52 79,842,304.92 6.13
c Pekerjaan Wash Out
i Pembuatan Bak Kontrol Wash Out
- Galian tanah M³ 0.30 76,331.00 22,899.30 0.00 0.15 11,449.65 0.00 0.15 11,449.65 0.00 0.30 22,899.30 0.00
- Beton Tumbuk mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 M³ 0.09 1,016,439.00 92,714.48 0.01 0.05 46,357.24 0.00 0.05 46,357.24 0.00 0.09 92,714.48 0.01
- Pasangan Batu Bata 1pc : 4 ps M2 1.20 235,670.00 282,804.00 0.02 0.60 141,402.00 0.01 0.60 141,402.00 0.01 1.20 282,804.00 0.02
- Urugan Tanah Kembali M³ 0.09 27,456.00 2,471.04 0.00 0.05 1,235.52 0.00 0.05 1,235.52 0.00 0.09 2,471.04 0.00
- Plesteran 1 pc : 3 ps M2 4.32 67,564.00 291,876.48 0.02 - - - 4.32 291,876.48 0.02 4.32 291,876.48 0.02
- Acian M2 4.32 37,436.00 161,723.52 0.01 - - - 4.32 161,723.52 0.01 4.32 161,723.52 0.01
- Tutup Bak Kontrol dari plat baja Unit 1.00 862,500.00 862,500.00 0.07 0.50 431,250.00 0.03 0.50 431,250.00 0.03 1.00 862,500.00 0.07
- Engsel Psng 2.00 14,750.00 29,500.00 0.00 1.00 14,750.00 0.00 1.00 14,750.00 0.00 2.00 29,500.00 0.00
Sub Jumlah 1 1,746,488.82 0.13 646,444.41 0.05 1,100,044.41 0.08 1,746,488.82 0.13
ii Asesories Wash Out
- Tee HDPE 50" Buah 1.00 50,000.00 50,000.00 0.00 1.00 50,000.00 0.00 - - 1.00 50,000.00 0.00
- Ball Valve HDPE dia. 50" Buah 2.00 225,000.00 450,000.00 0.03 2.00 450,000.00 0.03 - - 2.00 450,000.00 0.03
- Kunci gembok Buah 1.00 10,000.00 10,000.00 0.00 - - - 1.00 10,000.00 0.00 1.00 10,000.00 0.00
Sub Jumlah 2 510,000.00 0.04 500,000.00 0.04 10,000.00 0.00 510,000.00 0.04
TOTAL PEKERJAAN WASH OUT 2,256,488.82 0.17 1,146,444.41 0.09 1,110,044.41 0.09 2,256,488.82 0.17
JUMLAH 1 UNIT 2,256,488.82 0.17 1,146,444.41 0.09 1,110,044.41 0.09 2,256,488.82 0.17
d Pekerjaan Air Valve
i Pembuatan Bak Kontrol Air Valve
- Galian tanah M³ 0.30 76,331.00 22,899.30 0.00 0.30 22,899.30 0.00 - - 0.30 22,899.30 0.00
- Beton Tumbuk mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 M³ 0.09 1,016,439.00 92,714.48 0.01 0.09 92,714.48 0.01 - - 0.09 92,714.48 0.01
- Pasangan Batu Bata 1pc : 4 ps M2 1.20 235,670.00 282,804.00 0.02 1.20 282,804.00 0.02 - - 1.20 282,804.00 0.02
- Urugan Tanah Kembali M³ 0.09 27,456.00 2,471.04 0.00 0.09 2,471.04 0.00 - - 0.09 2,471.04 0.00
- Plesteran 1 pc : 3 ps M2 4.32 67,564.00 291,876.48 0.02 - - - 4.32 291,876.48 0.02 4.32 291,876.48 0.02
- Acian M2 4.32 37,436.00 161,723.52 0.01 - - - 4.32 161,723.52 0.01 4.32 161,723.52 0.01
- Pemb Ttp Bak Kntrl Rangka Besi Siku dan Plat Unit 1.00 862,500.00 862,500.00 0.07 1.00 862,500.00 0.07 - - 1.00 862,500.00 0.07
- Engsel Buah 2.00 14,750.00 29,500.00 0.00 2.00 29,500.00 0.00 - - 2.00 29,500.00 0.00
Sub Jumlah 1 1,746,488.82 0.13 1,292,888.82 0.10 453,600.00 0.03 1,746,488.82 0.13
ii Asesories Air Valve
- Clam Sadel 50 mm x 1" Buah 1.00 50,000.00 50,000.00 0.00 1.00 50,000.00 0.00 - - 1.00 50,000.00 0.00
- Air Valve dia. 1" Buah 1.00 750,000.00 750,000.00 0.06 1.00 750,000.00 0.06 - - 1.00 750,000.00 0.06
- kunci gembok Buah 1.00 10,000.00 10,000.00 0.00 - - - 1.00 10,000.00 0.00 1.00 10,000.00 0.00
Sub Jumlah 2 810,000.00 0.06 800,000.00 0.06 10,000.00 0.00 810,000.00 0.06
TOTAL PEKERJAAN AIR VALVE GIP DIA. 50 MM 2,556,488.82 0.20 2,092,888.82 0.16 463,600.00 0.04 2,556,488.82 0.20
JUMLAH 1 UNIT 2,556,488.82 0.20 2,092,888.82 0.16 463,600.00 0.04 2,556,488.82 0.20
C PENGADAAN & PEMASANGAN PIPA DARI RV KE ARAH KE MATA AIR
a Pengadaan dan Pemasangan Pipa HDPE Ø 50 mm PN 10
i Pengadaan Material pipa HDPE Ø 50 mm beserta assesoris
- Coupler 50 mm Buah 11.00 137,500.00 1,512,500.00 0.12 11.00 1,512,500.00 0.12 - - 11.00 1,512,500.00 0.12
- End Cup 50 mm Buah 1.00 102,440.00 102,440.00 0.01 1.00 102,440.00 0.01 - - 1.00 102,440.00 0.01
Sub Jumlah 1 1,614,940.00 0.12 1,614,940.00 0.12 - - 1,614,940.00 0.12
ii Kontruksi Pemasangan pipa HDPE Ø 50 mm
- Galian Tanah M3 66.00 76,331.00 5,037,846.00 0.39 66.00 5,037,846.00 0.39 - - 66.00 5,037,846.00 0.39
- Urugan Tanah Kembali M3 58.59 27,456.00 1,608,781.80 0.12 58.59 1,608,781.80 0.12 - - - 58.59 1,608,781.80 0.12
- Pengadaan & Pemasangan Pipa HDPE Ø 50 mm M' 1,100.00 63,062.62 69,368,879.74 5.33 1,100.00 69,368,879.74 5.33 - - 1,100.00 69,368,879.74 5.33
- Uji coba pengaliran M' 1,100.00 1,544.00 1,698,400.00 0.13 - - - 1,100.00 1,698,400.00 0.13 1,100.00 1,698,400.00 0.13
Sub Jumlah 2 77,713,907.53 5.97 76,015,507.53 5.84 1,698,400.00 0.13 77,713,907.53 5.97
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI HDPE DIAMETER 50 MM 79,328,847.53 6.10 77,630,447.53 5.96 1,698,400.00 0.13 79,328,847.53 6.10
b Pengadaan dan Pemasangan Pipa HDPE Ø 32 mm
i Pengadaan Material pipa HDPE Ø 32 mm beserta assesoris
- Coupler 32 mm Buah 2.00 79,350.00 158,700.00 0.01 2.00 158,700.00 0.01 - - - 2.00 158,700.00 0.01
- Clam Sadel 50 mm x 1" Buah 30.00 50,000.00 1,500,000.00 0.12 30.00 1,500,000.00 0.12 - - 30.00 1,500,000.00 0.12
- End Cup 32 mm Buah 2.00 72,000.00 144,000.00 0.01 2.00 144,000.00 0.01 - - - 2.00 144,000.00 0.01
Sub Jumlah 1 1,802,700.00 0.14 1,802,700.00 0.14 - - 1,802,700.00 0.14
ii Kontruksi Pemasangan pipa HDPE Ø 32 mm
- Galian Tanah M3 32.05 76,331.00 2,446,180.35 0.19 32.05 2,446,180.35 0.19 - - - 32.05 2,446,180.35 0.19
- Urugan Tanah Kembali M3 26.63 27,456.00 731,264.45 0.06 26.63 731,264.45 0.06 - - - 26.63 731,264.45 0.06
- Pengadaan & Pemasangan Pipa HDPE Ø 32 mm M' 500.00 31,753.00 15,876,500.00 1.22 500.00 15,876,500.00 1.22 - - - 500.00 15,876,500.00 1.22
- Uji coba pengaliran M' 500.00 1,544.00 772,000.00 0.06 - - - 500.00 772,000.00 0.06 500.00 772,000.00 0.06
Sub Jumlah 2 19,825,944.80 1.52 19,053,944.80 1.46 772,000.00 0.06 19,825,944.80 1.52
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI HDPE DIAMETER 50 MM 21,628,644.80 1.66 20,856,644.80 1.60 772,000.00 0.06 21,628,644.80 1.66
VI PEKERJAAN SAMBUNGAN RUMAH
i Pengadaan & Pemasangan Pipa dan Accsories SR
- Pipa GIP Ǿ 15 mm M' 2,520.00 36,817.69 92,780,576.32 7.13 2,520.00 92,780,576.32 7.13 - - - 2,520.00 92,780,576.32 7.13
- Clamp Sadle HDPE ∅ 32mm x1/2" Bh 140.00 200,000.00 28,000,000.00 2.15 130.00 26,000,000.00 2.00 10.00 2,000,000.00 0.15 140.00 28,000,000.00 2.15
- Knie GIP Ǿ 1/2" Bh 840.00 10,000.00 8,400,000.00 0.65 840.00 8,400,000.00 0.65 - - - 840.00 8,400,000.00 0.65
- Socket GIP. Ǿ 1/2" Bh 140.00 15,000.00 2,100,000.00 0.16 130.00 1,950,000.00 0.15 10.00 150,000.00 0.01 140.00 2,100,000.00 0.16
- Double Nipple GIP. Ǿ 1/2" Bh 140.00 12,500.00 1,750,000.00 0.13 130.00 1,625,000.00 0.12 10.00 125,000.00 0.01 140.00 1,750,000.00 0.13
- Tee GIP. Ǿ 1/2" Bh 140.00 15,000.00 2,100,000.00 0.16 130.00 1,950,000.00 0.15 10.00 150,000.00 0.01 140.00 2,100,000.00 0.16
- Dop GIP. Ǿ 1/2" Bh 140.00 15,000.00 2,100,000.00 0.16 130.00 1,950,000.00 0.15 10.00 150,000.00 0.01 140.00 2,100,000.00 0.16
- Water Moor Ǿ 1/2" Bh 140.00 45,000.00 6,300,000.00 0.48 130.00 5,850,000.00 0.45 10.00 450,000.00 0.03 140.00 6,300,000.00 0.48
- Water Meter Onda Ǿ 1/2" Bh 140.00 450,000.00 63,000,000.00 4.84 130.00 58,500,000.00 4.49 10.00 4,500,000.00 0.35 140.00 63,000,000.00 4.84
- Gate Valve Onda 1/2" Bh 140.00 150,000.00 21,000,000.00 1.61 130.00 19,500,000.00 1.50 10.00 1,500,000.00 0.12 140.00 21,000,000.00 1.61
- Kran Air Onda Ǿ 1/2" Bh 140.00 50,000.00 7,000,000.00 0.54 130.00 6,500,000.00 0.50 10.00 500,000.00 0.04 140.00 7,000,000.00 0.54
- Plugvalve Onda Ǿ 1/2" Bh 140.00 100,000.00 14,000,000.00 1.08 130.00 13,000,000.00 1.00 10.00 1,000,000.00 0.08 140.00 14,000,000.00 1.08
- Box Water Meter Bh 140.00 150,000.00 21,000,000.00 1.61 130.00 19,500,000.00 1.50 10.00 1,500,000.00 0.12 140.00 21,000,000.00 1.61
Sub Jumlah 1 269,530,576.32 20.71 257,505,576.32 19.79 12,025,000.00 0.92 269,530,576.32 20.71
ii Pekerjaan Konstruksi & Pemasangan
- Pemasangan Instalasi Sambungan Pipa dan Acesories Unit 140.00 250,000.00 35,000,000.00 2.69 126.00 31,500,000.00 2.42 14.00 3,500,000.00 0.27 140.00 35,000,000.00 2.69
- Dudukan Box Water Meter Beton Tumbuk K 100 + Bekisting M3 11.55 1,257,805.00 14,527,647.75 1.12 5.78 7,263,823.88 0.56 5.78 7,263,823.88 0.56 11.55 14,527,647.75 1.12
- Beton Perkuatan Kran Beton Tumbuk K 100 + Bekisting M3 1.12 1,257,805.00 1,408,741.60 0.11 0.56 704,370.80 0.05 0.56 704,370.80 0.05 1.12 1,408,741.60 0.11
Sub Jumlah 2 50,936,389.35 3.91 39,468,194.68 3.03 11,468,194.68 0.88 50,936,389.35 3.91
TOTAL PEKERJAAN SAMBUNGAN RUMAH 320,466,965.67 24.62 296,973,770.99 22.82 23,493,194.68 1.81 320,466,965.67 24.62
JUMLAH 100 UNIT 320,466,965.67 24.62 296,973,770.99 22.82 23,493,194.68 1.81 320,466,965.67 24.62
VII PEKERJAAN BAK KONTROL 60 x 60 cm
1 Galian tanah M3 0.20 76,331.00 15,266.20 0.00 0.14 10,686.34 0.00 0.06 4,579.86 0.00 0.20 15,266.20 0.00
2 Pekerjaan Beton
- Lantai Kerja tebal 5 cm M3 0.05 226,404.90 11,320.25 0.00 0.04 7,924.17 0.00 0.02 3,396.07 0.00 0.05 11,320.25 0.00
- Beton Bertulang K-225 untuk dinding dan lantai bak kontrol M3 0.34 1,520,589.00 509,701.43 0.04 0.23 356,791.00 0.03 0.10 152,910.43 0.01 0.34 509,701.43 0.04
- Bekisting m2 4.72 189,074.00 892,429.28 0.07 3.30 624,700.50 0.05 1.42 267,728.78 0.02 4.72 892,429.28 0.07
- Pembesian kg 19.85 22,083.20 438,380.23 0.03 13.90 306,866.16 0.02 5.96 131,514.07 0.01 19.85 438,380.23 0.03
3 Plesteran dinding 1 PC : 5 PP m2 5.36 70,797.00 379,471.92 0.03 - - - 5.36 379,471.92 0.03 5.36 379,471.92 0.03
4 Acian saus semen M2 5.36 38,251.00 205,025.36 0.02 - - - 5.36 205,025.36 0.02 5.36 205,025.36 0.02
5 Cat warna biru M2 5.36 41,662.00 223,308.32 0.02 3.75 156,315.82 0.01 1.61 66,992.50 0.01 5.36 223,308.32 0.02
6 Gate Valve Ø 1.5" BH 2.00 225,000.00 450,000.00 0.03 1.40 315,000.00 0.02 0.60 135,000.00 0.01 2.00 450,000.00 0.03
7 Doble Nippel GIP Ø 1.5" BH 4.00 21,300.00 85,200.00 0.01 2.80 59,640.00 0.00 1.20 25,560.00 0.00 4.00 85,200.00 0.01
8 Watermur GIP Ø 1.5" BH 2.00 72,400.00 144,800.00 0.01 1.40 101,360.00 0.01 0.60 43,440.00 0.00 2.00 144,800.00 0.01
9 Tee HDPE Ø 1.5" BH 1.00 50,000.00 50,000.00 0.00 0.70 35,000.00 0.00 0.30 15,000.00 0.00 1.00 50,000.00 0.00
10 Main Hole BH 1.00 862,500.00 862,500.00 0.07 0.70 603,750.00 0.05 0.30 258,750.00 0.02 1.00 862,500.00 0.07
11 Gembok BH 1.00 35,000.00 35,000.00 0.00 0.70 24,500.00 0.00 0.30 10,500.00 0.00 1.00 35,000.00 0.00
TOTAL PEKERJAAN BOX KONTROL 60 x 60 4,302,402.99 0.33 2,602,533.99 0.20 1,699,868.99 0.13 4,302,402.99 0.33
21,512,014.93 1.65 13,012,669.97 1.00 8,499,344.96 0.65 21,512,014.93 1.65

VII PEKERJAAN PENYELESAIAN


i Pembersihan Kembali Lokasi Ls 1.00 2,000,000.00 2,000,000.00 0.15 - - - 1.00 2,000,000.00 0.15 1.00 2,000,000.00 0.15
JUMLAH 2,000,000.00 0.15 - - 2,000,000.00 0.15 2,000,000.00 0.15
JUMLAH TOTAL PEKERJAAN 1,301,481,478 100.00 1,213,066,424.23 93.25 87,883,169.34 6.75 1,301,481,477.71 100.00