Anda di halaman 1dari 2

BELUM DI KERJAKAN

DINDING SALURAN PELUNCUR BELUM DI KERJAKAN


JEMBATAN SPILLWAY BARU PONDASI YANG DI COR
BELUM DI KERJAKAN KARENA ABUTMEN
BEMUM SELESAI
BELUM DI COR

BARU DI COR

BIRU DINDING KOLAM TRANSISI


YANG BARU DI COR

WARNA MERAH
DINDING APRON YANG BARU DI COR

DINDING REFETMENT RENCANA

PELIMPAH
KETERANGAN PEKERJAAN BETON DINDING
BELUM TERMASUK LANTAI
BELUM
DIKERJAKAN
1 YANG BERWARNA ITU YANG SUDAH DI
COR
2.YANG ABU-ABU BELUM DI COR

ABUTMENT JEMBATAN

UNTUK LANTAI BELUM DI COR

BELUM DIKERJAKAN

DINDING REFETMENT RENCANA


LOKASI PENEMPATAN STATION KLIMATOLOGI DAN LAIN2

SKETSA PERSPEKSIVE VOLUME YANG BARU DI KERJAKAN

January 14, 2023 Project Location BENDUNGAN PADANG PANJANG A 01


DINDING SALURAN VOLUME CUT OFF KIRI
DINDING REFETMENT DINDING KOLAM TRANSISI PELUNCUR 24.19 m³
118.33 m³ 143.86 m³ 94.11 m³
VOLUME CUTOF
DINDING KOLAM TRANSMISI DINDING SAL PELUNCUR
165.26 m³ 31.65 m³

DINDING APRON DEPAN


101.87 m³

LANTAI SALURAN
PELUNCUR DAN OLAKAN
116.32 m³

PELIMPAH
LANTAI KOLSM TRANISIS 2
140.24 m³

PEREDAM ENERGY
22.52 m³

ABUTMENT JEMBATAN
13.72 m³

KETERANGAN
LANTAI APRON DEPAN DAN KOLM TRASNISI VOLUME TERLAMPIR ITU ADALAH VOLUME
WARNA KUNING KESELURUHAN BETON
MERCU PELIMPAH
369.88 m³
18.74 m³
1 YANG BERWARNA ITU YANG SUDAH DI
COR
2.YANG ABU-ABU BELUM DI COR
DINDING REFETMENT 2
3.UNTUK LANTAI SPILLWAY BELUM DI COR
56.09 m³

SKETSA PERSPEKSIVE VOLUME BANGUNAN PELIMPAH

January 14, 2023 Project Location BENDUNGAN PADANG PANJANG A 02