KONTRAK REALISASI
SISA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN HARGA MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
JUMLAH HARGA BOBOT
Kuantitas SATUAN
(RP) (%) Bobot Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga
(RP) Kuantitas Kuantitas Kuantitas Kuantitas
(%) (RP) (%) (RP) (%) (RP) (%) (RP)
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 83,875,000.00 83,875,000.00 4.56 0.70 3.19 58,712,500.00 - - - 0.70 3.19 58,712,500.00 0.30 1.37 25,162,500.00
SUB TOTAL DIVISI 1. 83,875,000.00 4.56 3.19 58,712,500.00 - - 3.19 58,712,500.00 1.37 25,162,500.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 1,440.00 69,290.19 99,777,873.60 5.43 - - - - - - - - - 1,440.00 5.43 99,777,873.60
SUB TOTAL DIVISI 2. 99,777,873.60 5.43 - - - - - - 5.43 99,777,873.60
JUMLAH 1,839,062,055.65 100.00 12.39 227,836,391.34 9.36 172,222,466.59 21.75 400,058,857.94 78.25 1,439,003,197.71
RENCANA PROGRESS MINGGUAN 4.94 4.46 9.40
DEVIASI 7.45 4.90 12.35