MASTER SCHEDULE PENYELESAIAN PEKERJAAN

SISA WAKTU 19 MINGGU + 1 HARI PAGE 1


SISA MINGGU 1 - 4 1 S/D 4
MINGGU KE : MINGGU KE : MINGGU KE : MINGGU KE :
NO PEKERJAAN 1 2 3 4
20/08 21/08 22/08 23/08 24/08 25/08 26/08 27/08 28/08 29/08 30/08 31/08 01/09 02/09 03/09 04/09 05/09 06/09 07/09 08/09 09/09 10/09 11/09 12/09 13/09 14/09 15/09 16/09

I PEKERJAAN PERSIAPAN STANDART

II. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME

II.A. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME STANDART

2.1.A. PEKERJAAN STRUKTUR STANDART


1. PEKERJAAN PRODUKSI PRACETAK
2. PEKERJAAN INSTALASI PRACETAK
3. PEKERJAAN COR KONVENSIONAL
4. PEKERJAAN RANGKA ATAP

2.2.A. PEKERJAAN ARSITEKTUR STANDART


1. DINDING
3. KUSEN
3. LANTAI
4. PLAFON
5. PENUTUP ATAP
6. PENGECATAN

2.3.A. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDAR

II.B. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME NON STANDART

2.1.B. PEKERJAAN STRUKTUR NON STANDART


1. PONDASI
2. GWT DAN RUMAH POMPA
3. SEPTICTANK
4. RESAPAN

2.2.B. PEKERJAAN ARSITEKTUR NON STANDART

2.3.B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDAR


MASTER SCHEDULE PENYELESAIAN PEKERJAAN
SISA WAKTU 19 MINGGU + 1 HARI PAGE 2
SISA MINGGU 5 - 8 5 S/D 8
MINGGU KE : MINGGU KE : MINGGU KE : MINGGU KE :
NO PEKERJAAN 5 6 7 8
17/09 18/09 19/09 20/09 21/09 22/09 23/09 24/09 25/09 26/09 27/09 28/09 29/09 30/09 01/10 02/10 03/10 04/10 05/10 06/10 07/10 08/10 09/10 10/10 11/10 12/10 13/10 14/10

I PEKERJAAN PERSIAPAN STANDART

II. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME

II.A. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME STANDART

2.1.A. PEKERJAAN STRUKTUR STANDART


1. PEKERJAAN PRODUKSI PRACETAK
2. PEKERJAAN INSTALASI PRACETAK
3. PEKERJAAN COR KONVENSIONAL
4. PEKERJAAN RANGKA ATAP

2.2.A. PEKERJAAN ARSITEKTUR STANDART


1. DINDING
3. KUSEN
3. LANTAI
4. PLAFON
5. PENUTUP ATAP
6. PENGECATAN

2.3.A. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDAR

II.B. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME NON STANDART

2.1.B. PEKERJAAN STRUKTUR NON STANDART


1. PONDASI
2. GWT DAN RUMAH POMPA
3. SEPTICTANK
4. RESAPAN

2.2.B. PEKERJAAN ARSITEKTUR NON STANDART

2.3.B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDAR


MASTER SCHEDULE PENYELESAIAN PEKERJAAN
SISA WAKTU 19 MINGGU + 1 HARI PAGE 3
SISA MINGGU 9 - 12 9 S/D 12
MINGGU KE : MINGGU KE : MINGGU KE : MINGGU KE :
NO PEKERJAAN 9 10 11 12
15/10 16/10 17/10 18/10 19/10 20/10 21/10 22/10 23/10 24/10 25/10 26/10 27/10 28/10 29/10 30/10 31/10 01/11 02/11 03/11 04/11 05/11 06/11 07/11 08/11 09/11 10/11 11/11

I PEKERJAAN PERSIAPAN STANDART

II. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME

II.A. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME STANDART

2.1.A. PEKERJAAN STRUKTUR STANDART


1. PEKERJAAN PRODUKSI PRACETAK
2. PEKERJAAN INSTALASI PRACETAK
3. PEKERJAAN COR KONVENSIONAL
4. PEKERJAAN RANGKA ATAP

2.2.A. PEKERJAAN ARSITEKTUR STANDART


1. DINDING
3. KUSEN
3. LANTAI
4. PLAFON
5. PENUTUP ATAP
6. PENGECATAN

2.3.A. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDAR

II.B. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME NON STANDART

2.1.B. PEKERJAAN STRUKTUR NON STANDART


1. PONDASI
2. GWT DAN RUMAH POMPA
3. SEPTICTANK
4. RESAPAN

2.2.B. PEKERJAAN ARSITEKTUR NON STANDART

2.3.B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDAR


MASTER SCHEDULE PENYELESAIAN PEKERJAAN
SISA WAKTU 19 MINGGU + 1 HARI PAGE 4
SISA MINGGU 13 - 16 13 S/D 16
MINGGU KE : MINGGU KE : MINGGU KE : MINGGU KE :
NO PEKERJAAN 13 14 15 16
12/11 13/11 14/11 15/11 16/11 17/11 18/11 19/11 20/11 21/11 22/11 23/11 24/11 25/11 26/11 27/11 28/11 29/11 30/11 01/12 02/12 03/12 04/12 05/12 06/12 07/12 08/12 09/12

I PEKERJAAN PERSIAPAN STANDART

II. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME

II.A. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME STANDART

2.1.A. PEKERJAAN STRUKTUR STANDART


1. PEKERJAAN PRODUKSI PRACETAK
2. PEKERJAAN INSTALASI PRACETAK
3. PEKERJAAN COR KONVENSIONAL
4. PEKERJAAN RANGKA ATAP

2.2.A. PEKERJAAN ARSITEKTUR STANDART


1. DINDING
3. KUSEN
3. LANTAI
4. PLAFON
5. PENUTUP ATAP
6. PENGECATAN

2.3.A. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDAR

II.B. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME NON STANDART

2.1.B. PEKERJAAN STRUKTUR NON STANDART


1. PONDASI
2. GWT DAN RUMAH POMPA
3. SEPTICTANK
4. RESAPAN

2.2.B. PEKERJAAN ARSITEKTUR NON STANDART

2.3.B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDAR


MASTER SCHEDULE PENYELESAIAN PEKERJAAN
SISA WAKTU 19 MINGGU + 1 HARI PAGE 5
SISA MINGGU 17 - 19 17 S/D 19
MINGGU KE : MINGGU KE : MINGGU KE : MINGGU KE :
NO PEKERJAAN 17 18 19 20
10/12 11/12 12/12 13/12 14/12 15/12 16/12 17/12 18/12 19/12 20/12 21/12 22/12 23/12 24/12 25/12 26/12 27/12 28/12 29/12 30/12 31/12 01/01 02/01 03/01 04/01 05/01 06/01

I PEKERJAAN PERSIAPAN STANDART

II. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME

II.A. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME STANDART

2.1.A. PEKERJAAN STRUKTUR STANDART


1. PEKERJAAN PRODUKSI PRACETAK
2. PEKERJAAN INSTALASI PRACETAK
3. PEKERJAAN COR KONVENSIONAL
4. PEKERJAAN RANGKA ATAP

2.2.A. PEKERJAAN ARSITEKTUR STANDART


1. DINDING
3. KUSEN
3. LANTAI
4. PLAFON
5. PENUTUP ATAP
6. PENGECATAN

2.3.A. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDAR

II.B. PEKERJAAN STRUKTUR, ARSITEKTUR DAN ME NON STANDART

2.1.B. PEKERJAAN STRUKTUR NON STANDART


1. PONDASI
2. GWT DAN RUMAH POMPA
3. SEPTICTANK
4. RESAPAN

2.2.B. PEKERJAAN ARSITEKTUR NON STANDART

2.3.B. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL NON STANDAR